Policy Replication

Resource Adequacy Report: Evaluating the Reliability and Security of the United States Electric Grid, July 2025

Docket document2025-11-28 · EPA · publication · EPA-HQ-OLEM-2025-2864-0003
RIN 2050-AH42 · Docket EPA-HQ-OLEM-2025-2864

Other documents for the same rulemaking (all, by stage)

2025-11-28 Federal RegisterHazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Extension of an Alternative Closure Requirement Deadline
2025-11-28 Regulatory impact analysisRedline RIA Alternative Closure Deadline F2 Extension proposal documenting changes made during EO 12866 interagency review
2025-11-28 Regulatory impact analysisRegulatory Impact Analysis Alternative Closure Deadline F2 Extension
2025-11-28 Docket documentRedline NPRM Alternative Closure Deadline F2 Extension proposal documenting changes made during EO 12866 interagency review
2025-11-28 Docket document2024 Long-Term Reliability Assessment, December 2024 (corrected July 11, 2025)
2025-11-28 Docket document40 CFR 257.103(f)(2) Alternative Closure Requirements Annual Alternative Capacity Update and Impoundment Closure Progress Report CLECO Power LLC Brame Energy Center Lena, LA
2025-11-28 Docket documentSouthwestern Electric Power Company, Welsh Power Plant Alternative Closure Demonstration
2025-11-28 Docket documentExtending the Deadline in 40 C.F.R. § 257.103(f)(2)
2025-11-28 Docket documentCoal Combustion Residual Rule 2024 Annual Groundwater Monitoring and Corrective Action Report, Primary Ash Pond, Coleto Creek Power Station Fannin, Texas
2025-11-28 Docket document2024 Annual Groundwater Monitoring and Corrective Action Report, Pond System, Miami Fort Power Plant, North Bend, Ohio, CCR Unit 115
2025-11-28 Docket documentKincaid Power Station Revised Alternative Closure Demonstration
2025-11-28 Docket document2024 40 C.F.R. § 257 Annual Groundwater Monitoring and Corrective Action Report Bottom Ash Pond Baldwin Power Plant Baldwin, Illinois CCR Unit 601
2025-11-28 Docket documentOctober 2025 Annual Progress Report, Documenting the Continued Lack of Alternative Capacity and the Progress Towards the Closure of the Coal-Fired Boilers, Intermountain Generating Facility, Delta, Utah
2025-11-28 Docket document2024 Annual Groundwater Monitoring and Corrective Action Report, South Ash Pond, Naughton Power Plant, Kemmerer, Wyoming
2025-11-28 Docket documentBaldwin Power Station Revised Alternative Closure Demonstration
2025-11-28 Docket document2024 Annual Groundwater Monitoring and Corrective Action Summary Report, Intermountain Generating Facility, Delta, Utah
2025-11-28 Docket document2024 Annual Groundwater Monitoring Report for the Coal Combustion Residuals Rule
2025-11-28 Docket documentAnnual Groundwater Monitoring Report, Southwestern Electric Power Company, Welsh Power Plant, Primary Bottom Ash Pond
2025-11-28 Docket document40 CFR 257.103(f)(2) Alternative Closure Requirements Annual Alternative Capacity Update and Impoundment Closure Progress Report
2025-11-28 Docket documentAnnual Report- 04, Alternative Closure Requirements Primary Bottom Ash Pond, J. Robert Welsh Power Plant Southwestern Electric Power Company
2025-11-28 Docket documentNewton Power Plant Alternative Closure Demonstration – Update to Schedule and Closure Plan
2025-11-28 Docket documentColeto Creek Power Plant Alternative Closure Demonstration
2025-11-28 Docket document2025 Summer Reliability Assessment, May 2025
2025-11-28 Docket document2024 Annual Groundwater Monitoring Report for the Coal Combustion Residuals Rule, Cleco Power LLC Brame Energy Center Bottom Ash and Fly Ash Ponds Lena, LA
2025-11-28 Docket document2024 40 C.F.R. § 257 Annual Groundwater Monitoring and Corrective Action Report, Ash Pond, Kincaid Power Plant, Kincaid, Illinois, CCR Unit 141
2025-11-28 Docket documentOrder No. 202-25-3
2025-11-28 Docket documentExecutive Order 25-50 by the State of Indiana
2025-11-28 Docket documentNorthern Indiana Public Service Company LLC, R.M. Schahfer Generating Station, Waste Disposal Area, 40 CFR §257.103(F)(2)(X) Part A Demonstration Annual Progress Report #01-24
2025-11-28 Docket documentAnnual Progress Report (§ 257.103(f)(2)(x)) for the Kincaid Power Plant Ash Pond
2025-11-28 Docket documentAnnual Progress Report (§ 257.103(f)(2)(x)) for the Miami Fort Power Plant
2025-11-28 Docket documentAnnual Progress Report (§ 257.103(f)(2)(x)) for the Coleto Creek Power Plant Primary Ash Pond
2025-11-28 Docket documentNorthern Indiana Public Service Company LLC, R.M. Schahfer Generating Station, Waste Disposal Area, 40 CFR §257.103(F)(2)(X) Part A Demonstration Annual Progress Report #01-25
2025-11-28 Docket documentAnnual Progress Report (§ 257.103(f)(2)(x)) for the Baldwin Power Plant Bottom Ash Pond
2025-11-28 Docket documentNIPSCO email requesting extension to 40 CFR 257.103(f)(2) deadline
2025-11-28 Docket documentBaldwin Power Station Alternative Closure Demonstration – Update to Schedule and Closure Plan
2025-11-28 Docket document2024 Progress Report, Site-Specific Alternative to Initiate Closure, Permanent Cessation of Coal-Fired Boiler(s) by a Date Certain, Naughton Power Plant, South Ash Pond, Kemmerer, Wyoming
2025-11-28 Docket documentContinued Lack of Alternative Capacity and Closure Progress Report, Naughton Power Plant South Ash Pond
2025-11-28 Docket documentAnnual Progress Report (§ 257.103(f)(2)(x)) for the Newton Power Plant Primary Ash Pond
2025-12-03 Docket documentMemorandum Containing Internet Links to Certain Documents in Docket
2025-12-04 Docket documentNewton 2024 Annual Groundwater Monitoring and Corrective Action Report non-confidential
2025-12-04 Docket documentCorrection of Federal Register Preamble Statement
2026-01-07 Federal RegisterHazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Extension of an Alternative Closure Requirement Deadline; Extension of Comment Period
2026-02-02 Docket documentVirtual Public Hearing on Proposed CCR Alternative Closure Deadline Extension Rule

References

Page 1Download these results: CSV · JSON
1. AESO. 2019. “Annual Market Statistics Report” https://public.tableau.com/app/profile/market.analytics/viz/AnnualStatistics_1616185422 8350/Introduction Last updated May 13, 2025.
datasetNot linked to a paper · refsec · cited link
2. AESO. “Hourly Metered Volumes and Pool Price and AIL” https://www.aeso.ca/assets/Uploads/datarequests/Hourly_Metered_Volumes_and_Pool_Price_and_AIL.csv Accessed May 30, 2025.
datasetNot linked to a paper · refsec · cited link
3. AESO. 2016 “Historical Generation Data (CSD)” https://www.aeso.ca/market/marketand-system-reporting/data-requests/historical-generation-data Accessed May 30, 2025.
datasetNot linked to a paper · refsec · cited link
4. BC Hydro. 2025. “Historical Transmission Data” https://www.bchydro.com/energy-inbc/operations/transmission/transmission-system/balancing-authority-load-data/historicaltransmission-data.html
research reportNot linked to a paper · refsec · cited link
5. BPA. “Rolling 30 Days and Monthly History” https://transmission.bpa.gov/business/operations/paths/ Accessed May 30, 2025.
datasetNot linked to a paper · refsec · cited link
6. BPA. “VER* Generation and Total Load in The BPA Balancing Authority” https://transmission.bpa.gov/business/operations/wind/ Accessed May 30, 2025. 7. Government of Canada. 2022. “Historical Data on Electricity Consumption and Production in Quebec” https://open.canada.ca/data/en/dataset/bd6a1401-15db-438d9b8b-ff11af48064e Updated July 24, 2024.
datasetNot linked to a paper · refsec · cited link
8. IESO. 2025. “Data Directory” https://www.ieso.ca/power-data/data-directory
research reportNot linked to a paper · refsec · cited link
9. IESO. 2019. “Yearly Intertie Actual Schedule and Flow Report” https://reportspublic.ieso.ca/public/IntertieScheduleFlowYear/ Updated May 30, 2025.
research reportNot linked to a paper · refsec · cited link
10. IESO. 2018. ”Hourly Demand Report” https://reports-public.ieso.ca/public/Demand/ Updated May 30, 2025.
research reportNot linked to a paper · refsec · cited link
11. IESO. 2025. “Generator Output by Fuel Type Hourly Report” https://reportspublic.ieso.ca/public/GenOutputbyFuelHourly/ Updated May 30, 2025.
research reportNot linked to a paper · refsec · cited link
12. ISO-NE. 2025. “Energy, Load, and Demand Reports: Zonal Information” https://www.isone.com/isoexpress/web/reports/load-and-demand/-/tree/zone-info
research reportNot linked to a paper · refsec · cited link
13. ISO-NE. 2025. “Energy, Load, and Demand Reports: Historical Hourly Flows and Limits” https://www.iso-ne.com/isoexpress/web/reports/load-and-demand/-/tree/historical-hourlyflows-and-limits
research reportNot linked to a paper · refsec · cited link
14. MISO. “Load, Generation, and Interchange API” https://dataexchange.misoenergy.org/api-details#api=load-generation-and-interchangeapi&operation=get-v1-real-time-date-interchange-net-actual Accessed May 30, 2025. U.S. Department of Energy Report on Strengthening U.S. Grid Reliability and Security
datasetNot linked to a paper · refsec · cited link
15. NB Power. 2025. “System Information Archive” https://tso.nbpower.com/Public/en/system_information_archive.aspx Accessed May 30, 2025.
datasetNot linked to a paper · refsec · cited link
16. NYISO. 2002 “Internal and External Interface Limits and Flows” https://mis.nyiso.com/public/P-32list.htm Updated May 30, 2025.
research reportNot linked to a paper · refsec · cited link
17. NYISO. 2004 “Day-Ahead Markey Daily Energy Report" https://mis.nyiso.com/public/P30list.htm Updated May 30, 2025 18. Stephen et al. 2022. “Clarifying the Interpretation and Use of the LOLE Resource Adequacy Metric” https://www.spp.org/documents/69303/lole%20metric.pdf U.S. Department of Energy Report on Strengthening U.S. Grid Reliability and Security
research reportNot linked to a paper · refsec · cited link
EO 14262 U.S. Department of Energy Report on Strengthening U.S. Grid Reliability and Security Available at (accessed on 5/27/2025): https://www.federalregister.gov/documents/2025/04/14/2025-06381/strengthening-the-reliabilityand-security-of-the-united-states-electric-grid U.S. Department of Energy For more information, visit: energy.gov/topics/reliability
research reportNot linked to a paper · refsec · cited link
DOE/Publication Number • July, 7 2025 DOE/GO-000000-0000 ▪ Month Year
research reportNot linked to a paper · refsec