Policy Replication

← Rulemakings

Electric Power Transmission and Distribution; Electrical Protective Equipment

RIN 1218-AB67 · DEPARTMENT OF LABOR; Occupational Safety and Health Administration · Econ. significantMajor · 272 references in its rule and RIA documents

A rulemaking follows one regulatory action through all its stages. A stage often has several Federal Register documents (the proposal itself, comment-period extensions, meeting notices, supplemental proposals, corrections), the regulatory impact analysis can be several files for each of the proposed and final rule, and an agency may keep more than one docket. Each document says why it is in this rulemaking and how sure that link is.

Complete Every stage OIRA reviewed is here, with the regulatory impact analysis.

13 documents in this rulemaking, plus 1 identical copy not counted again. 1 document filed under another rulemaking also names this one (listed at the end).
Pre-rulenoneNo OIRA review
Proposed ruleheldOIRA review 2005-02-15 · 3 documents
Interim final rulenoneNo OIRA review
Final ruleheldOIRA review 2012-06-27 · 1 document
Regulatory impact analysis7 files
Docket documents13 of 426 held2 dockets; public comments not listed

Proposed rule stage: Federal Register documents (3)

Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment

Proposed rule (NPRM)2005-06-15 · FR 05-11585 · DEPARTMENT OF LABOR; Occupational Safety and Health Administration · 38 references, 6 linked to papers
Federal Register action: Proposed rule.
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Limited Reopening of Record

Comment period extended or reopened2008-10-22 · FR E8-25079 · DEPARTMENT OF LABOR; Occupational Safety and Health Administration · 5 references
Federal Register action: Notice of limited reopening of rulemaking record.
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Limited Reopening of Record; Notice of Informal Public Hearing

Comment period extended or reopened2009-09-14 · FR E9-22002 · DEPARTMENT OF LABOR; Occupational Safety and Health Administration · 1 reference, 1 linked to papers
Federal Register action: Proposed rule; limited reopening of the rulemaking record and notice of public hearing.
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Final rule stage: Federal Register documents (1)

Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment

Final rule2014-04-11 · FR 2013-29579 · DEPARTMENT OF LABOR; Occupational Safety and Health Administration · 94 references, 28 linked to papers
Federal Register action: Final rule.
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Other Federal Register notices (corrections, delays, withdrawals) (2)

Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Extension of Comment Period; Change in Date of Public Hearing

Comment period extended or reopened2005-10-12 · FR 05-20421 · DEPARTMENT OF LABOR; Occupational Safety and Health Administration
Federal Register action: Notice of hearing; extension of comment period; reopening of the period to file notices of intention to appear at an informal public hearing; additional issues for comment.
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Corrections

Correction2014-09-24 · FR 2014-22148 · DEPARTMENT OF LABOR; Occupational Safety and Health Administration
Federal Register action: Correcting amendments.
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Regulatory impact analyses (7)

For the proposed rule

Supporting Exhibit 7-3; PREPARATION OF AN ECONOMIC IMPACT STUDY FOR THE PROPOSED OSHA REGULATION COVERING ELECTRIC POWER GENERATION, TRANSMISSION, AND DISTRIBUTION. TASK ORDER NO. 1 CONTRACT NO. J-9-F-5-0057.

RIA appendix1986-05-31 · Regulatory impact analysis · OSHA · 26 references
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Supporting Exhibit 2; OFFICE OF REGULATORY ANALYSIS, OSHA

RIA appendix1987-10-23 · Regulatory impact analysis · OSHA · 7 references
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Supporting Exhibit 32; Regulatory Impact and Regulatory Flexibility Analysis of the Electrical Safety-Related Work Practices Standard for General Industry (29 CFR 1910, Subpart S)

RIA appendix1990-06-12 · Regulatory impact analysis · OSHA · 7 references
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Supporting Exhibit 2-4; A BRIEF SUMMARY OF OSHAS PRELIMINARY ESTIMATES OF THE ECONOMIC IMPACTS, COSTS, AND BENEFITS OF THE PROPOSED RULE AS A WHOLE. CONTRACT NO. J-9-F-9-0013. TASK ORDER NUMBER 29. OPTION YEAR 3.

RIA appendix2003-02-14 · Regulatory impact analysis · OSHA · 9 references
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Supporting Exhibit 3; FINAL REPORT. ANAYTICAL SUPPORT AND DATA GATHERING FOR A PRELIMINARY ECONOMIC ANALYSIS FOR A PROPOSED STANDARD FOR WORK ON ELEC POWER TRANSMISSION AND DISTRIBUTION LINES AND EQUIP (29 CFR 1910.269 AND 29 CFR 1926 - SUBPART V). CONTRACT NO. J-9-F-9-0013

RIA appendix2003-02-14 · Regulatory impact analysis · OSHA · 31 references
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Supporting Exhibit 2-3; DRAFT COPY OF OSHAS PRELIMINARY INITIAL REGULATORY FLEXIBILITY ANALYSIS, WHICH INCLUDES THE AGENCYS ANALYSIS OF SOME ALTERNATIVES TO THE PROPOSED RULE.

RIA appendix2003-04-07 · Regulatory impact analysis · OSHA · 4 references
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Supporting Exhibit 7-1; REVISED FINAL REPORT - ANALYTICAL SUPPORT AND DATA GATHERING FRO A PRELIMINARY ECONOMIC ANALYSIS FOR PROPOSED STANDARDS FOR WORK ON ELECTRIC POWER GENERATION, TRANSMISSION, AND DISTRIBUTION LINES AND EQUIPMENT (29 CFR 1910.269 AND 29 CFR 1926-SUBPART V)

RIA appendix2005-06-08 · Regulatory impact analysis · OSHA · 50 references
In this rulemaking because: RIN printed on the document (RIN 1218-AB67) · high confidence

Docket documents

OSHA-S016-2006-0646: 70 documents, 3 held · Analyses 2 (2 held), Other 67, Rule documents 1 (1 held)
OSHA-S215-2006-0063: 356 documents, 10 held · Analyses 7 (5 held), Correspondence 19, Data 15, Other 298 (1 held), Publications 5, Reports 7, OIRA review record 1 (1 held), Rule documents 4 (3 held)

Supporting Exhibit 7-3; PREPARATION OF AN ECONOMIC IMPACT STUDY FOR THE PROPOSED OSHA REGULATION COVERING ELECTRIC POWER GENERATION, TRANSMISSION, AND DISTRIBUTION. TASK ORDER NO. 1 CONTRACT NO. J-9-F-5-0057.

AnalysesHeld1986-05-31 · OSHA-S215-2006-0063-0082 · Supporting & Related Material · References/Supporting Documents

Supporting Exhibit 2; OFFICE OF REGULATORY ANALYSIS, OSHA

AnalysesHeld1987-10-23 · OSHA-S016-2006-0646-0003 · Supporting & Related Material · Final

Supporting Exhibit 32; Regulatory Impact and Regulatory Flexibility Analysis of the Electrical Safety-Related Work Practices Standard for General Industry (29 CFR 1910, Subpart S)

AnalysesHeld1990-06-12 · OSHA-S016-2006-0646-0122 · Supporting & Related Material · Final

Supporting Exhibit 2-4; A BRIEF SUMMARY OF OSHAS PRELIMINARY ESTIMATES OF THE ECONOMIC IMPACTS, COSTS, AND BENEFITS OF THE PROPOSED RULE AS A WHOLE. CONTRACT NO. J-9-F-9-0013. TASK ORDER NUMBER 29. OPTION YEAR 3.

AnalysesHeld2003-02-14 · OSHA-S215-2006-0063-0011 · Supporting & Related Material · SER Letters/Supporting Documents

Supporting Exhibit 3; FINAL REPORT. ANAYTICAL SUPPORT AND DATA GATHERING FOR A PRELIMINARY ECONOMIC ANALYSIS FOR A PROPOSED STANDARD FOR WORK ON ELEC POWER TRANSMISSION AND DISTRIBUTION LINES AND EQUIP (29 CFR 1910.269 AND 29 CFR 1926 - SUBPART V). CONTRACT NO. J-9-F-9-0013

AnalysesHeld2003-02-14 · OSHA-S215-2006-0063-0017 · Supporting & Related Material · Agency References/Submissions

Supporting Exhibit 2-3; DRAFT COPY OF OSHAS PRELIMINARY INITIAL REGULATORY FLEXIBILITY ANALYSIS, WHICH INCLUDES THE AGENCYS ANALYSIS OF SOME ALTERNATIVES TO THE PROPOSED RULE.

AnalysesHeld2003-04-07 · OSHA-S215-2006-0063-0010 · Supporting & Related Material · SER Letters/Supporting Documents

Supporting Exhibit 7-1; REVISED FINAL REPORT - ANALYTICAL SUPPORT AND DATA GATHERING FRO A PRELIMINARY ECONOMIC ANALYSIS FOR PROPOSED STANDARDS FOR WORK ON ELECTRIC POWER GENERATION, TRANSMISSION, AND DISTRIBUTION LINES AND EQUIPMENT (29 CFR 1910.269 AND 29 CFR 1926-SUBPART V)

AnalysesHeld2005-06-08 · OSHA-S215-2006-0063-0080 · Supporting & Related Material · References/Supporting Documents

U.S. Bureau of Economic Analysis. 2010. National Income and Product Accounts Gross Domestic Product, 3rd quarter 2010 (second estimate); Corporate Profits, 3rd quarter 2010 (preliminary)

Analyses2014-04-01 · OSHA-S215-2006-0063-0637 · Supporting & Related Material · Economic Analysis

U.S. Bureau of Economic Analysis. 2011. Implicit Price Deflators for Gross Domestic Product

Analyses2014-04-01 · OSHA-S215-2006-0063-0638 · Supporting & Related Material · Economic Analysis

Documents filed under another rulemaking that also name this one (1)

Electrical Safety-Related Work Practices; Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Corrections · 2015-10-05 · counted under 1218-AA32

OIRA reviews (2)

Proposed Rulereceived 2005-02-15, concluded 2005-05-16 · Consistent with Change · econ. significant
Final Rulereceived 2012-06-27, concluded 2013-12-20 · Consistent with Change · econ. significant · major