Policy Replication

Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Limited Reopening of Record

Federal Register2008-10-22 · DEPARTMENT OF LABOR; Occupational Safety and Health Administration · Proposed Rule · E8-25079
Notice of limited reopening of rulemaking record.

On June 15, 2005, OSHA published a proposed rule to revise the general industry and construction standards for electric power generation, transmission, and distribution work and for electrical protective equipment. Public comments were received, a hearing was held, and the final posthearing briefs were due on July 14, 2006. The proposed general industry and construction standards for electric power generation, transmission, and distribution work included revised minimum approach distance tables. Those tables limit how close an employee (or a conductive object he or she is contacting) may get to an energized circuit part. After the rulemaking record on the proposal closed, the technical committee responsible for developing the tables in the consensus standards on which the proposal was based discovered what in their view was an error in their calculation of minimum approach distances for certain voltages. OSHA is reopening the record on this proposal to obtain comments related to the affected minimum approach distances. The record will remain open on this limited basis for 30 days.

RIN 1218-AB67 · Docket OSHA-S215-2006-0063

Other documents for the same rulemaking

1986-05-31 Regulatory impact analysisSupporting Exhibit 7-3; PREPARATION OF AN ECONOMIC IMPACT STUDY FOR THE PROPOSED OSHA REGULATION COVERING ELECTRIC POWER GENERATION, TRANSMISSION, AND DISTRIBUTION. TASK ORDER NO. 1 CONTRACT NO. J-9-F-5-0057.
1987-10-23 Regulatory impact analysisSupporting Exhibit 2; OFFICE OF REGULATORY ANALYSIS, OSHA
1990-06-12 Regulatory impact analysisSupporting Exhibit 32; Regulatory Impact and Regulatory Flexibility Analysis of the Electrical Safety-Related Work Practices Standard for General Industry (29 CFR 1910, Subpart S)
2003-02-14 Regulatory impact analysisSupporting Exhibit 2-4; A BRIEF SUMMARY OF OSHAS PRELIMINARY ESTIMATES OF THE ECONOMIC IMPACTS, COSTS, AND BENEFITS OF THE PROPOSED RULE AS A WHOLE. CONTRACT NO. J-9-F-9-0013. TASK ORDER NUMBER 29. OPTION YEAR 3.
2003-02-14 Regulatory impact analysisSupporting Exhibit 3; FINAL REPORT. ANAYTICAL SUPPORT AND DATA GATHERING FOR A PRELIMINARY ECONOMIC ANALYSIS FOR A PROPOSED STANDARD FOR WORK ON ELEC POWER TRANSMISSION AND DISTRIBUTION LINES AND EQUIP (29 CFR 1910.269 AND 29 CFR 1926 - SUBPART V). CONTRACT NO. J-9-F-9-0013
2003-04-07 Regulatory impact analysisSupporting Exhibit 2-3; DRAFT COPY OF OSHAS PRELIMINARY INITIAL REGULATORY FLEXIBILITY ANALYSIS, WHICH INCLUDES THE AGENCYS ANALYSIS OF SOME ALTERNATIVES TO THE PROPOSED RULE.
2005-06-08 Regulatory impact analysisSupporting Exhibit 7-1; REVISED FINAL REPORT - ANALYTICAL SUPPORT AND DATA GATHERING FRO A PRELIMINARY ECONOMIC ANALYSIS FOR PROPOSED STANDARDS FOR WORK ON ELECTRIC POWER GENERATION, TRANSMISSION, AND DISTRIBUTION LINES AND EQUIPMENT (29 CFR 1910.269 AND 29 CFR 1926-SUBPART V)
2005-06-15 Federal RegisterElectric Power Generation, Transmission, and Distribution; Electrical Protective Equipment
2005-10-12 Federal RegisterElectric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Extension of Comment Period; Change in Date of Public Hearing
2009-09-14 Federal RegisterElectric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Limited Reopening of Record; Notice of Informal Public Hearing
2014-04-01 Docket documentOffice of Management and Budget. 2003. Circular A-4
2014-04-11 Federal RegisterElectric Power Generation, Transmission, and Distribution; Electrical Protective Equipment
2014-09-24 Federal RegisterElectric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Corrections
2015-10-05 Federal RegisterElectrical Safety-Related Work Practices; Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Corrections

References: 5 extracted, 0 linked to papers

Page 1Download these results: CSV · JSON
ANSI/IEEE Standard 516-1987
otherNot linked to a paper · Supplementary Information, minimum approach distance principles
Transmission Line Reference Book for 115 to 138 kV
research reportNot linked to a paper · Supplementary Information, minimum approach distance principles
Draft #9 of IEEE Standard 516
otherNot linked to a paper · Supplementary Information, Table 1 discussion
Draft #10 of IEEE Standard 516
otherNot linked to a paper · Supplementary Information, Table 1 discussion
National Electrical Safety Code (NESC, ANSI C2)
otherNot linked to a paper · Supplementary Information, minimum approach distance principles