JH Campbell Power Plant Pond A 2021 Annual Groundwater Monitoring and Corrective Action Report
Other documents for the same rulemaking
References
ARCADIS. May 13, 2016. Summary of Monitoring Well Design, Installation, and Development – Pond A. JH Campbell Electric Generation Facility – West Olive, Michigan. Prepared for Consumers Energy Company.
ARCADIS. May 18, 2016. Electric Generation Facilities RCRA CCR Detection Monitoring Program. JH Campbell Monitoring Program Sample and Analysis Plan, West Olive, Michigan. Prepared for Consumers Energy Company. Consumers Power Company. September 1996. Hydrogeological Monitoring Plan for
TRC. October 2017. Groundwater Statistical Evaluation Plan – JH Campbell Power Plant,
TRC. January 2018. Annual Groundwater Monitoring Report, JH Campbell Power Plant, Pond A CCR Unit, West Olive, Michigan. Prepared for Consumers Energy Company.
TRC. October 15, 2018. Groundwater Protection Standards, Consumers Energy, JH Campbell
TRC. January 2019. 2018 Annual Groundwater Monitoring Report, JH Campbell Power Plant, Pond A CCR Unit, West Olive, Michigan. Prepared for Consumers Energy Company.
TRC. March 2019; Revised July 2019. Pond A Hydrogeological Monitoring Plan, JH Campbell Power Plant, West Olive, Michigan. Prepared for Consumers Energy Company.
TRC. September 2019. Assessment of Corrective Measures, JH Campbell Ponds 1-2 North and 1-2 South and Pond A Coal Combustion Residual Units, West Olive, Michigan. Prepared for Consumers Energy Company.
TRC. January 2020. 2019 Annual Groundwater Monitoring and Corrective Action Report and Fourth Quarter 2019 Hydrogeological Monitoring Report, JH Campbell Power Plant, Pond A CCR Unit, West Olive, Michigan. Prepared for Consumers Energy.
TRC. April 2020. First Quarter 2020 Hydrogeological Monitoring Report, JH Campbell Power
TRC. October 2020. Third Quarter 2020 Hydrogeological Monitoring Report, JH Campbell Power Plant, Pond A CCR Unit, West Olive, Michigan. Prepared for Consumers Energy.
USEPA. 2009. Statistical Analysis of Groundwater Monitoring Data at RCRA Facilities, Unified Guidance. Office of Conservation and Recovery. EPA 530/R‐09‐007.
USEPA. April 2015. 40 CFR Parts 257 and 261. Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals from Electric Utilities; Final Rule. 80 Federal Register 74 (April 17, 2015), pp. 21301-21501 (80 FR 21301).
USEPA. July 2018. 40 CFR Part 257. Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals from Electric Utilities; Amendments to the National Minimum Criteria (Phase One, Part One); Final Rule. 83 Federal Register 146 (July 30, 2018), pp. 36435-36456 (83 FR 36435).
USEPA. April 2018. Barnes Johnson (Office of Resource Conservation and Recovery) to James Roewer (c/o Edison Electric Institute) and Douglas Green, Margaret Fawal (Venable
LLP). Re: Coal Combustion Residuals Rule Groundwater Monitoring Requirements. April 30, 2018. United States Environmental Protection Agency, Washington, D.C. 20460. Office of Solid Waste and Emergency Response, now the Office of Land and Emergency Management.
TRC | Consumers Energy X:\WPAAM\PJT2\418422\0000\2021Q2\R418422.0 POND A.DOCX Final July 2021 Table 1 Summary of Groundwater Elevation Data – Second Quarter 2021
TRC. January 2021. Sample and Analysis Plan, Electric Generation Facilities RCRA CCR Assessment Monitoring Program, JH Campbell Power Plant Pond A, West Olive, Michigan. Prepared for Consumers Energy.
TRC. April 2021. First Quarter 2021 Hydrogeological Monitoring Report, JH Campbell Power
TRC. October 2021. Third Quarter 2021 Hydrogeological Monitoring Report, JH Campbell Power Plant, Pond A CCR Unit, West Olive, Michigan. Prepared for Consumers Energy.
TRC | Consumers Energy X:\WPAAM\PJT2\418422\0000\2021Q4\R418422.0 POND A.DOCX Final January 2022 Table 1 Summary of Groundwater Elevation Data – Fourth Quarter 2021
Olive, Michigan. Prepared for Consumers Energy Company. Golder Associates. January 2018. JH Campbell Generating Facility Bottom Ash Ponds 1-2 Closure
TRC Environmental Corporation. January 2022. 2021 Annual Groundwater Monitoring and Corrective Action Report, JH Campbell Power Plant, Pond A CCR Unit. Prepared for Consumers Energy Company.
TRC Environmental Corporation. January 2021. Sample Analysis Plan for JH Campbell Bottom Ash Ponds 1-2 and Pond 3. Prepared for Consumers Energy Company.
TRC Environmental Corporation. September 2019. Assessment of Corrective Measures, Consumers Energy Company JH Campbell Ponds 1-2 North and 1-2 South and Pond A Coal Combustion Residual Units. Prepared for Consumers Energy Company.
TRC Environmental Corporation. March 2019; Revised July 2019. Pond A Hydrogeological Monitoring Plan, JH Campbell Power Plant, West Olive, Michigan. Prepared for Consumers Energy Company