Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Revision of an Alternative Closure Requirement Deadline

RIN 2050-AH42 · ENVIRONMENTAL PROTECTION AGENCYMajor · 17 references in its rule and RIA documents

A rulemaking follows one regulatory action through all its stages. A stage often has several Federal Register documents (the proposal itself, comment-period extensions, meeting notices, supplemental proposals, corrections), the regulatory impact analysis can be several files for each of the proposed and final rule, and an agency may keep more than one docket. Each document says why it is in this rulemaking and how sure that link is.

Complete Every stage OIRA reviewed is here.

5 documents in this rulemaking.
Pre-rulenoneNo OIRA review
Proposed ruleheldOIRA review 2025-10-08 · 1 document
Interim final rulenoneNo OIRA review
Final rulenoneNo OIRA review
Regulatory impact analysis2 files
Docket documents44 of 53 held1 docket; public comments not listed

Proposed rule stage: Federal Register documents (1)

Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Extension of an Alternative Closure Requirement Deadline

Proposed rule (NPRM)2025-11-28 · FR 2025-21597 · ENVIRONMENTAL PROTECTION AGENCY · 8 references
Federal Register action: Proposed rule; notice of public hearing.
In this rulemaking because: RIN printed on the document (RIN 2050-AH42) · high confidence

Other Federal Register notices (corrections, delays, withdrawals) (1)

Hazardous and Solid Waste Management System: Disposal of Coal Combustion Residuals From Electric Utilities; Extension of an Alternative Closure Requirement Deadline; Extension of Comment Period

Comment period extended or reopened2026-01-07 · FR 2026-00084 · ENVIRONMENTAL PROTECTION AGENCY
Federal Register action: Proposed rule; extension of comment period.
In this rulemaking because: RIN printed on the document (RIN 2050-AH42) · high confidence

Regulatory impact analyses (2)

For the proposed rule

Redline RIA Alternative Closure Deadline F2 Extension proposal documenting changes made during EO 12866 interagency review

RIA2025-11-28 · Regulatory impact analysis · EPA · 6 references
In this rulemaking because: RIN printed on the document (RIN 2050-AH42) · high confidence

Regulatory Impact Analysis Alternative Closure Deadline F2 Extension

RIA2025-11-28 · Regulatory impact analysis · EPA · 3 references
In this rulemaking because: RIN printed on the document (RIN 2050-AH42) · high confidence

Docket documents

EPA-HQ-OLEM-2025-2864: 53 documents, 44 held · Analyses 1 (1 held), Correspondence 13 (13 held), Other 3 (3 held), Publications 10 (1 held), Reports 22 (22 held), OIRA review record 2 (2 held), Rule documents 2 (2 held)

NIPSCO email requesting extension to 40 CFR 257.103(f)(2) deadline

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0002 · Supporting & Related Material · E-mail

Annual Progress Report (§ 257.103(f)(2)(x)) for the Baldwin Power Plant Bottom Ash Pond

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0010 · Supporting & Related Material · Letter

Baldwin Power Station Alternative Closure Demonstration – Update to Schedule and Closure Plan

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0011 · Supporting & Related Material · Letter

Annual Progress Report (§ 257.103(f)(2)(x)) for the Coleto Creek Power Plant Primary Ash Pond

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0017 · Supporting & Related Material · Letter

Annual Progress Report (§ 257.103(f)(2)(x)) for the Kincaid Power Plant Ash Pond

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0023 · Supporting & Related Material · Letter

Annual Progress Report (§ 257.103(f)(2)(x)) for the Miami Fort Power Plant

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0025 · Supporting & Related Material · Letter

2024 Progress Report, Site-Specific Alternative to Initiate Closure, Permanent Cessation of Coal-Fired Boiler(s) by a Date Certain, Naughton Power Plant, South Ash Pond, Kemmerer, Wyoming

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0027 · Supporting & Related Material · Letter

Continued Lack of Alternative Capacity and Closure Progress Report, Naughton Power Plant South Ash Pond

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0028 · Supporting & Related Material · Memorandum

Annual Progress Report (§ 257.103(f)(2)(x)) for the Newton Power Plant Primary Ash Pond

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0030 · Supporting & Related Material · Letter

Northern Indiana Public Service Company LLC, R.M. Schahfer Generating Station, Waste Disposal Area, 40 CFR §257.103(F)(2)(X) Part A Demonstration Annual Progress Report #01-24

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0032 · Supporting & Related Material · Memorandum

Northern Indiana Public Service Company LLC, R.M. Schahfer Generating Station, Waste Disposal Area, 40 CFR §257.103(F)(2)(X) Part A Demonstration Annual Progress Report #01-25

CorrespondenceHeld2025-11-28 · EPA-HQ-OLEM-2025-2864-0033 · Supporting & Related Material · Memorandum

Memorandum Containing Internet Links to Certain Documents in Docket

CorrespondenceHeld2025-12-03 · EPA-HQ-OLEM-2025-2864-0051 · Supporting & Related Material · Memorandum

Correction of Federal Register Preamble Statement

CorrespondenceHeld2025-12-04 · EPA-HQ-OLEM-2025-2864-0053 · Supporting & Related Material · Memorandum

OIRA reviews (1)

Proposed Rulereceived 2025-10-08, concluded 2025-11-21 · Consistent with Change · major