Regulatory Framework for Fusion Machines [NRC-2023-0071]

RIN 3150-AL00 · NUCLEAR REGULATORY COMMISSION · 29 references in its rule and RIA documents

A rulemaking follows one regulatory action through all its stages. A stage often has several Federal Register documents (the proposal itself, comment-period extensions, meeting notices, supplemental proposals, corrections), the regulatory impact analysis can be several files for each of the proposed and final rule, and an agency may keep more than one docket. Each document says why it is in this rulemaking and how sure that link is.

Complete Every stage OIRA reviewed is here.

5 documents in this rulemaking.
Pre-rulenoneNo OIRA review
Proposed ruleheldOIRA review 2025-07-24 · 2 documents
Interim final rulenoneNo OIRA review
Final rulenoneNo OIRA review
Regulatory impact analysis2 files
Docket documents58 of 58 held1 docket; public comments not listed

Proposed rule stage: Federal Register documents (2)

Regulatory Framework for Fusion Systems

Proposed rule (NPRM)2023-10-04 · FR 2023-21988 · NUCLEAR REGULATORY COMMISSION · 3 references
Federal Register action: Availability of preliminary proposed rule language; public meeting.
In this rulemaking because: RIN printed on the document (RIN 3150-AL00) · high confidence

Regulatory Framework for Fusion Machines

Proposed rule (NPRM)2026-02-26 · FR 2026-03865 · NUCLEAR REGULATORY COMMISSION · 6 references, 1 linked to papers
Federal Register action: Proposed rule; guidance; and request for comment.
In this rulemaking because: RIN printed on the document (RIN 3150-AL00) · high confidence

Regulatory impact analyses (2)

For the proposed rule

SECY-24-0085 Enclosure 3 - Draft Regulatory Analysis-Fusion Machine Proposed Rule

RIA2024-12-13 · Regulatory impact analysis · NRC · 9 references
In this rulemaking because: RIN printed on the document (RIN 3150-AL00) · high confidence

Draft Regulatory Analysis for the Proposed Rule - Regulatory Framework for Fusion Machines (ML25168A339)

RIA2026-02-26 · Regulatory impact analysis · NRC · 11 references
In this rulemaking because: RIN printed on the document (RIN 3150-AL00) · high confidence

Docket documents

NRC-2023-0071: 58 documents, 58 held · Analyses 2 (2 held), Other 53 (53 held), OIRA review record 1 (1 held), Rule documents 2 (2 held)

SRM-SECY-23-0001 Options for Licensing and Regulating Fusion Energy Systems

OtherHeld2023-07-24 · NRC-2023-0071-0001 · Supporting & Related Material

SECY-23-0001 Enclosure 1 - Rulemaking Plan for Fusion Energy Systems

OtherHeld2023-07-24 · NRC-2023-0071-0002 · Supporting & Related Material

SECY-23-0001 Enclosure 3 - Approaches to Producing Energy form Fusion

OtherHeld2023-07-24 · NRC-2023-0071-0003 · Supporting & Related Material

SECY-23-0001 Enclosure 4 - Summary of Engagement on Fusion Energy Systems

OtherHeld2023-07-24 · NRC-2023-0071-0004 · Supporting & Related Material

SECY-23-0001 Options for Regulating Fusion Energy Systems

OtherHeld2023-07-24 · NRC-2023-0071-0005 · Supporting & Related Material

Public Meeting Summary - July 12 2023 Proposed Rule Fusion Energy Systems

OtherHeld2023-07-24 · NRC-2023-0071-0006 · Supporting & Related Material

Public Meeting Presentation - July 12 2023 Proposed Rule Regulatory Framework for Fusion Energy Systems

OtherHeld2023-07-24 · NRC-2023-0071-0007 · Supporting & Related Material

STC-23-053 Notification of Proposed Rulemaking

OtherHeld2023-07-25 · NRC-2023-0071-0008 · Supporting & Related Material

October 11 2023 Public Meeting Presentation - Proposed Rule Regulatory Framework for Fusion Systems

OtherHeld2023-10-10 · NRC-2023-0071-0011 · Supporting & Related Material

Fusion Systems Rulemaking - Preliminary Proposed Rule Language

OtherHeld2023-10-23 · NRC-2023-0071-0012 · Supporting & Related Material

November 1 2023 Public Meeting Handout - Preliminary Draft Guidance (NUREG-1556 Volume 22) ML23258A172

OtherHeld2023-11-03 · NRC-2023-0071-0013 · Supporting & Related Material

November 1 2023 Public Meeting Presentation - Fusion Systems Preliminary Draft Guidance

OtherHeld2023-11-03 · NRC-2023-0071-0014 · Supporting & Related Material

November 9 2023 Public Meeting Presentation - Fusion Systems Proposed Rule

OtherHeld2023-11-09 · NRC-2023-0071-0015 · Supporting & Related Material

October 11 2023 Public Meeting Summary - Proposed Rule Regulatory Framework for Fusion Systems

OtherHeld2023-12-20 · NRC-2023-0071-0016 · Supporting & Related Material

November 1 2023 Public Meeting Summary - Fusion Systems Preliminary Draft Guidance

OtherHeld2023-12-20 · NRC-2023-0071-0017 · Supporting & Related Material

November 9 2023 Public Meeting Transcript - Fusion Systems Proposed Rule

OtherHeld2023-12-20 · NRC-2023-0071-0018 · Supporting & Related Material

November 9 2023 Public Meeting Summary - Fusion Systems Proposed Rule

OtherHeld2023-12-20 · NRC-2023-0071-0019 · Supporting & Related Material

Letter from Fusion Industry Association to J. Lubinski dated December 15, 2023 - Fusion System Proposed Rule

OtherHeld2023-12-20 · NRC-2023-0071-0020 · Supporting & Related Material

NRC Response to Fusion Industry Association Letter dated December 15, 2023 - Preliminary Proposed Rule Language for the Regulation of Fusion Systems.

OtherHeld2024-01-12 · NRC-2023-0071-0021 · Supporting & Related Material

January 17 2024 Public Meeting Presentation - Proposed Rule: Regulatory Framework for Fusion Systems

OtherHeld2024-01-16 · NRC-2023-0071-0022 · Supporting & Related Material

January 17 2024 Public Meeting Handout - Preliminary Draft Guidance (NUREG-1556, Volume 22) ML23355A143

OtherHeld2024-01-16 · NRC-2023-0071-0023 · Supporting & Related Material

Helion Paper - Preparing for At-Scale Deployment of Fusion Energy via a Design-Specific License

OtherHeld2024-01-24 · NRC-2023-0071-0024 · Supporting & Related Material

January 17 2024 Public Meeting Summary - Fusion Systems - Proposed Rule

OtherHeld2024-02-09 · NRC-2023-0071-0025 · Supporting & Related Material

March 11 2024 and March 18 2024, NRC Meeting Handout for Fusion Systems Proposed Rule - Preliminary Draft (NUREG-1556, Volume 22) (ML24067A227)

OtherHeld2024-03-11 · NRC-2023-0071-0026 · Supporting & Related Material

March 18 2024 Public Meeting Announcement and Agenda - Proposed Rule: Regulatory Framework for Fusion Systems

OtherHeld2024-03-11 · NRC-2023-0071-0027 · Supporting & Related Material

March 18 2024 Public Meeting Presentation - Proposed Rule: Regulatory Framework for Fusion Systems

OtherHeld2024-03-18 · NRC-2023-0071-0028 · Supporting & Related Material

Letter from Commonwealth Fusion Systems, LLC, to J. Lubinski dated March 6, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems

OtherHeld2024-03-29 · NRC-2023-0071-0029 · Supporting & Related Material

NRC Response to Commonwealth Fusion Systems, LLC, Letter dated March 6, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems

OtherHeld2024-03-29 · NRC-2023-0071-0030 · Supporting & Related Material

Letter from TAE Technologies (TAE) to J. Lubinski dated May 22, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems

OtherHeld2024-07-02 · NRC-2023-0071-0031 · Supporting & Related Material

Letter from Fusion Industry Association (FIA) to J. Lubinski dated May 22, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems

OtherHeld2024-07-02 · NRC-2023-0071-0032 · Supporting & Related Material

Letter from Commonwealth Fusion Systems (CFS) to J. Lubinski dated May 21, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems

OtherHeld2024-07-02 · NRC-2023-0071-0033 · Supporting & Related Material

NRC Response to FIA Letter dated May 22, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems – June 2024

OtherHeld2024-07-02 · NRC-2023-0071-0034 · Supporting & Related Material

NRC Response to TAE Letter dated May 22, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems – June 2024

OtherHeld2024-07-02 · NRC-2023-0071-0035 · Supporting & Related Material

NRC Response to CFS Letter dated May 21, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems – June 2024

OtherHeld2024-07-02 · NRC-2023-0071-0036 · Supporting & Related Material

Letter from Helion to J. Lubinski dated August 1, 2024 - Preliminary Rulemaking Process for a Regulatory Framework for Fusion Systems

OtherHeld2024-08-07 · NRC-2023-0071-0037 · Supporting & Related Material

SECY-24-0085 Proposed Rule Regulatory Framework for Fusion Machines (3150-AL00; NRC-2023-0071)

OtherHeld2024-12-13 · NRC-2023-0071-0038 · Supporting & Related Material

SECY-24-0085 Enclosure 1 - Fusion Machine Proposed Rule FRN

OtherHeld2024-12-13 · NRC-2023-0071-0039 · Supporting & Related Material

SECY-24-0085 Enclosure 2 - Draft EA-Fusion Machine Proposed Rule

OtherHeld2024-12-13 · NRC-2023-0071-0040 · Supporting & Related Material

SECY-24-0085 Enclosure 4 - Alternative Views-Fusion Machine Proposed Rule

OtherHeld2024-12-13 · NRC-2023-0071-0042 · Supporting & Related Material

SECY-24-0085 Enclosure 5 - Options NRC Staff Considered Related to Distinctions between Particle Accelerators and Fusion Machines--Fusion Machine Proposed Rule

OtherHeld2024-12-13 · NRC-2023-0071-0043 · Supporting & Related Material

Letter from Fusion Industry Association (FIA) to the EDO, Mirela Gavrilas, PhD, dated September 13, 2024 - Preliminary Proposed Definition of Particle Accelerator for a Regulatory Framework for Fusion Machines

OtherHeld2025-01-07 · NRC-2023-0071-0044 · Supporting & Related Material

NRC Response to FIA Letter dated September 13, 2024 - Preliminary Proposed Definition of Particle Accelerator for a Regulatory Framework for Fusion Machines - January 2025

OtherHeld2025-01-07 · NRC-2023-0071-0045 · Supporting & Related Material

December 11 2024 SECY-24-0085 - Preliminary Draft Guidance (NUREG-1556, Volume 22) ML24295A002

OtherHeld2025-03-12 · NRC-2023-0071-0046 · Supporting & Related Material

Letter from Fusion Industry Association (FIA) to Chairman, dated January 29, 2025 - Proposed Rule

OtherHeld2025-03-14 · NRC-2023-0071-0047 · Supporting & Related Material

NRC Response to FIA Letter dated January 29, 2025 from J. Lubinski, dated March 7, 2025 - Proposed Rule

OtherHeld2025-03-14 · NRC-2023-0071-0048 · Supporting & Related Material

Organization of Agreement States (OAS) Board Letter to Commissioners, dated February 3, 2025 - Proposed Rule

OtherHeld2025-03-14 · NRC-2023-0071-0049 · Supporting & Related Material

NRC Response to OAS Board Letter dated February 3, 2025 from Rob Lewis, dated March 6, 2025 - Proposed Rule

OtherHeld2025-03-14 · NRC-2023-0071-0050 · Supporting & Related Material

Letter from Helion to Commissioners, dated February 3, 2025 - Proposed Rule

OtherHeld2025-03-14 · NRC-2023-0071-0051 · Supporting & Related Material

NRC Response to Helion Letter dated February 3, 2025 from J. Lubinski, dated March 7, 2025 - Proposed Rule

OtherHeld2025-03-14 · NRC-2023-0071-0052 · Supporting & Related Material

Draft Report for Comment - NUREG-1556, Volume 22, Consolidated Guidance About Materials Licenses Program: Specific Guidance About Possession Licenses for Fusion Machines (ML24092A377)

OtherHeld2026-02-26 · NRC-2023-0071-0054 · Supporting & Related Material

Draft Environmental Assessment for the Proposed Rule - Regulatory Framework for Fusion Machines (ML25168A335)

OtherHeld2026-02-26 · NRC-2023-0071-0055 · Supporting & Related Material

March 25 2026 Public Meeting Announcement and Agenda - Proposed Rule: Regulatory Framework for Fusion Machines

OtherHeld2026-03-24 · NRC-2023-0071-0066 · Supporting & Related Material

March 25 2026 Public Meeting Presentation - Proposed Rule: Regulatory Framework for Fusion Machines

OtherHeld2026-03-25 · NRC-2023-0071-0069 · Supporting & Related Material

OIRA reviews (1)

Proposed Rulereceived 2025-07-24, concluded 2026-02-20 · Consistent with Change