Pipeline Safety: Issues Related to the Use of Plastic Pipe in Gas Pipeline Industry

RIN 2137-AE93 · DEPARTMENT OF TRANSPORTATION; Pipeline and Hazardous Materials Safety Administration · 24 references in its rule and RIA documents

A rulemaking follows one regulatory action through all its stages. A stage often has several Federal Register documents (the proposal itself, comment-period extensions, meeting notices, supplemental proposals, corrections), the regulatory impact analysis can be several files for each of the proposed and final rule, and an agency may keep more than one docket. Each document says why it is in this rulemaking and how sure that link is.

Complete Every stage OIRA reviewed is here.

4 documents in this rulemaking.
Pre-rulenoneNo OIRA review
Proposed ruleheld, not OIRA-reviewedNo OIRA review · 1 document
Interim final rulenoneNo OIRA review
Final ruleheldOIRA review 2018-06-20 · 1 document
Regulatory impact analysis2 files
Docket documents14 of 21 held1 docket; public comments not listed

Proposed rule stage: Federal Register documents (1)

Pipeline Safety: Plastic Pipe Rule

Proposed rule (NPRM)2015-05-21 · FR 2015-12113 · DEPARTMENT OF TRANSPORTATION; Pipeline and Hazardous Materials Safety Administration · 2 references
Federal Register action: Notice of Proposed Rulemaking (NPRM).
In this rulemaking because: RIN printed on the document (RIN 2137-AE93) · high confidence

Final rule stage: Federal Register documents (1)

Pipeline Safety: Plastic Pipe Rule

Final rule2018-11-20 · FR 2018-24925 · DEPARTMENT OF TRANSPORTATION; Pipeline and Hazardous Materials Safety Administration · 4 references
Federal Register action: Final rule.
In this rulemaking because: RIN printed on the document (RIN 2137-AE93) · high confidence

Regulatory impact analyses (2)

For the proposed rule

Plastic Pipe - Regulatory Impact Analysis and Initial Regulatory Flexibility Act Analysis

RIA2015-05-21 · Regulatory impact analysis · PHMSA · 4 references
In this rulemaking because: RIN printed on the document (RIN 2137-AE93) · high confidence
For the final rule

Regulatory Impact Analysis & Environmental Assessment

RIA2018-11-20 · Regulatory impact analysis · PHMSA · 14 references, 1 linked to papers
In this rulemaking because: RIN printed on the document (RIN 2137-AE93) · high confidence

Docket documents

PHMSA-2014-0098: 21 documents, 14 held · Analyses 2 (2 held), Correspondence 3 (3 held), Other 11 (4 held), Reports 3 (3 held), Rule documents 2 (2 held)

AGA Petition for Rulemaking Related to Plastic Pipe

Other2014-07-10 · PHMSA-2014-0098-0001 · Other · Petition for Rulemaking

Plastic Pipe - Environmental Assessment

OtherHeld2015-05-21 · PHMSA-2014-0098-0005 · Supporting & Related Material · Environmental Assessment

American Gas Association - Petition to Extend Comment Period

Other2015-06-04 · PHMSA-2014-0098-0007 · Other · Petition(s)

Plastics Pipe Institute - Petition to Extend the Comment Period

OtherHeld2015-06-22 · PHMSA-2014-0098-0011 · Other · Petition(s)

Gas Processors Association - Request to Extend Comment Period

Other2015-07-23 · PHMSA-2014-0098-0014 · Other · Request

U.S. DOT/PHMSA - Request - American Gas Association

Other2015-10-09 · PHMSA-2014-0098-0057 · Other · Request

U.S. DOT/PHMSA - Plastic Pipe Institute

Other2015-10-09 · PHMSA-2014-0098-0058 · Other · Agency Response

U.S. DOT/PHMSA- Texas Pipeline Association

Other2015-10-09 · PHMSA-2014-0098-0059 · Other · Agency Response

U.S. DOT/PHMSA - Gas Processors Association

OtherHeld2015-10-09 · PHMSA-2014-0098-0060 · Other · Agency Response

American Gas Association - Petition for Reconsideration for the Plastic Pipe

OtherHeld2018-12-20 · PHMSA-2014-0098-0063 · Other · Petition(s)

American Gas Association - Petition for Reconsiration

Other2019-08-23 · PHMSA-2014-0098-0065 · Other · Petition(s)

OIRA reviews (1)

Final Rulereceived 2018-06-20, concluded 2018-09-27 · Consistent with Change