Debris Removal: Eligibility of Force Account Labor Straight-Time Costs Under the Public Assistance Program for Hurricane Sandy

RIN 1660-AA75 · DEPARTMENT OF HOMELAND SECURITY; FEDERAL EMERGENCY MANAGEMENT AGENCY · 1 reference in its rule and RIA documents

A rulemaking follows one regulatory action through all its stages. A stage often has several Federal Register documents (the proposal itself, comment-period extensions, meeting notices, supplemental proposals, corrections), the regulatory impact analysis can be several files for each of the proposed and final rule, and an agency may keep more than one docket. Each document says why it is in this rulemaking and how sure that link is.

Complete Every stage OIRA reviewed is here.

2 documents in this rulemaking.
Pre-rulenoneNo OIRA review
Proposed rulenoneNo OIRA review
Interim final ruleheldOIRA review 2012-11-05 · 1 document
Final ruleheld, not OIRA-reviewedNo OIRA review · 1 document
Regulatory impact analysisnone
Docket documents2 of 2 held1 docket; public comments not listed

Interim final rule stage: Federal Register documents (1)

Debris Removal: Eligibility of Force Account Labor Straight-Time Costs Under the Public Assistance Program for Hurricane Sandy

Interim final rule2012-11-09 · FR 2012-27382 · DEPARTMENT OF HOMELAND SECURITY; FEDERAL EMERGENCY MANAGEMENT AGENCY · 1 reference
Federal Register action: Interim final rule.
In this rulemaking because: RIN printed on the document (RIN 1660-AA75) · high confidence

Final rule stage: Federal Register documents (1)

Debris Removal: Eligibility of Force Account Labor Straight-Time Costs Under the Public Assistance Program for Hurricane Sandy

Final rule2014-08-07 · FR 2014-18709 · DEPARTMENT OF HOMELAND SECURITY; FEDERAL EMERGENCY MANAGEMENT AGENCY
Federal Register action: Final rule.
In this rulemaking because: RIN printed on the document (RIN 1660-AA75) · high confidence

Docket documents

FEMA-2012-0004: 2 documents, 2 held · Rule documents 2 (2 held)

Debris Removal: Eligibility of Force Account Labor Straight-Time Costs under the Public Assistance Program for Hurricane Sandy

Rule documentsHeld2012-11-09 · FEMA-2012-0004-0001 · Rule · Interim Final Rule · FR 2012-27382

Debris Removal: Eligibility of Force Account Labor Straight-Time Costs Under the Public Assistance Program for Hurricane Sandy

Rule documentsHeld2014-08-07 · FEMA-2012-0004-0005 · Rule · Final Rule · FR 2014-18709

OIRA reviews (1)

Interim Final Rulereceived 2012-11-05, concluded 2012-11-05 · Consistent without Change