The cost and risk impacts of rerouting railroad shipments of hazardous materials
Open-access copyPublisher page (DOI)OpenAlex record
Cited in 4 places in policy documents
Hazardous Materials: Enhanced Tank Car Standards and Operational Controls for High-Hazard Flammable Trains
Glickman, Theodore S. Erkut, Efhan, and Zschocke, Mark S. 2007. The cost and risk impacts of rerouting railroad shipments of hazardous materials. Accident Analysis and Prevention. 39. 1015-1025.
Glickman's estimate of safety improvements achievable by routing changes is based on an examination of how routing might vary as a rail carrier applies progressively heavier weights on various safety factors.\115\ In practice, it is impossible to know how much weight rail carriers will give to safety when making routing decisions.
DOT/PHMSA - Final Regulatory Impact Analysis (RIA)- Hazardous Materials: Enhanced Tank Car Standards and Operational Controls for High-Hazard Flammable Trains; Final Rule
Glickman, Theodore S. Erkut, Efhan, and Zschocke, Mark S. 2007. The cost and risk impacts of rerouting railroad shipments of hazardous materials. Accident Analysis and Prevention. 39. 1015-1025.
DOT/PHMSA - Final Regulatory Impact Analysis (RIA)- Hazardous Materials: Enhanced Tank Car Standards and Operational Controls for High-Hazard Flammable Trains; Final Rule
Glickman, Theodore S., Erkut, Efhan, and Zschocke, Mark S. 2007. The cost and risk impacts of rerouting railroad shipments of hazardous materials. Accident Analysis and Prevention. 39. 1015-1025.
U.S. DOT/PHMSA - Draft Regulatory Impact Analysis - Hazardous Materials: Enhanced Tank Car Standards and Operational Controls for High-Hazard Flammable Trains; Notice of Proposed Rulemaking
Glickman, Theodore S., Erkut, Efhan, and Zschocke, Mark S. 2007. The cost and risk impacts of rerouting railroad shipments of hazardous materials. Accident Analysis and Prevention. 39. 1015-1025.