Ltr/EPA/F. Marcinowski to DOE/I. Triay, transmitting report for inspection no. EPA-SRS-CCP-10.02-22 [A-98-49-II-A1-41]
Other documents for the same rulemaking
References: 6 extracted, 0 linked to papers
EXECUTIVE SUMMARY The U.S. Environmental Protection Agency ("EPA" or "Agency") conducted an inspection from October 22-23,2002, of the Savannah River Site (SRS) quality assurance (QA) program for the Waste Isolation Pilot Plant (WIPP) to confirm continued compliance in accordance with § 194.8(a)(4). The investigation of the activities selected for the EPA inspection sample showed that: Changes to SRS's QA Plan do not diminish the establishment of applicable Nuclear Quality Assurance (NQA) standards, The SRS Solid Waste Management Program QA Officer continues to have sufficient authority, qualifications, organizational freedom, resources, and access to work areas to properly assure the quality of the characterization of transuranic (TRU) waste, and The SRS Quality Assurance Program for WIPP related activities is actively performing quality verification activities. Concurrently during the EPA inspection, the QA Organization of DOE's Carlsbad Field Office(CBFO) conducted an audit to also assess SRS's continued proper execution of a QA Program for activities related to disposal of transuranic waste at the WIPP. DOE's audit sample showed that
NQA-2-1989 edition; and 3) ASME NQA-3-1989 edition (excluding Section 2.1(b) and (c) and Section 17.1). The Agency verified that DOE established these NQA standards in the Quality Assurance Program Document (QAPD) included in the Compliance Certification Application (CCA) for the WIPP. The QAPD is the documented QA Plan for the WIPP project, as a whole, to establish the NQA standards. The QAPD is maintained by the QA Organization of DOE's Carlsbad Field Office (CBFO), which has the authority to audit all other organizations associated with TRU-waste disposal at the WIPP to ensure that their lower-tier QA Programs establish and implement the applicable requirements of the QAPD. The DOE generator sites, which will characterize waste for disposal in the WIPP, must prepare site-specific QA Plans that establish the applicable NQA requirements. The EPA annually audits DOE's QA Program at CBFO (reference EPA Air Docket No. A-93-02, Document Nos. II-A-43 and IV-A-4, and EPA Air Docket No. A-98-49, Document No. II-A-1-4) and has found that DOE properly adheres to a QA Program that implements the NQA standards. The Agency determined in its WIPP Certification Decision (63 FR 27354, May 18, 1998) that the
Program, while in an inspection, the Agency also performs some oversight of DOE's quality assurance checks of a QA Program. The table below presents a summary of EPA inspections todate of SRS's'QA Program. Table 1: Summary of EPA Audits/Inspections of SRS's QA Program Activity Date Purpose Inspection November 7-16 2000 Initial Inspection of QA program for conformance with 40 CFR 194.8(a). Inspection December 11-13, 2001 Inspection to verify continued compliance of SRS
QA Program. Inspection October 22-23, 2002 Inspection to verify continued compliance of SRS
QA Program. SRS Background The Savannah River Site was constructed in the early 1950's to produce the basic materials used in the fabrication of nuclear weapons, primarily tritium and plutonium-239. Five reactors were built on the site. The reactors produced nuclear materials by irradiating target materials with neutrons. Also built were support facilities including two chemical separations plants, a heavy water extraction plant, a nuclear fuel and target fabrication facility, and waste management facilities. Irradiated materials were moved from the reactors to the two chemical separations facilities - the next step in the production process. In these facilities, known as "canyons," the irradiated fuel and target assemblies were chemically processed to separate useful products from waste. After refinement, some nuclear materials were shipped to other DOE sites for final use.
ASME NQA-1-1989 edition; 2) ASME NQA-2a-1990 Addenda, Part 2.7, to ASME NQA-2-1989 edition; and 3) ASME NQA-3-1989 edition (excluding Section 2.1(b) and (c) and Section 17.1). The purpose of the EPA inspection was to confirm the continued compliance of the SRS QA program with the above requirements in accordance with § 194.8(a)(4). Section 194.22(a)(2) requires that SRS properly execute a QA program for all items and activities that are important to the management and containment of TRU-waste at the WIPP. The scope of