Recovery Act Funding for DOE Carbon Capture and Sequestration (CCS) Projects
Cited in 1 place in policy documents
Carbon Capture and Storage in the United States
Peter Folger, Recovery Act Funding for DOE Carbon Capture and Sequestration (CCS) Projects, Report R44387, version 3 (Congressional Research Service, February 18, 2016), https://tinyurl.com/bddh9bnn
That "energy penalty" can require a plant to increase its electricity production by anywhere from about one-sixth to almost one-third of what it would produce without using CCS.6 High capital costs, along with cost overruns, were among the factors that contributed to the cancellation of CCS demonstration projects that received large federal subsidies under 2009 legislation (as described in Chapter 2) and other CCS projects in the United States.7 Installing CCS in existing power plants ("retrofitting") can be more costly than incorporating CCS into the design and construction of a new plant.