Policy Replication

Acquisition Costs of the Navy’s Medium Landing Ship

Congressional Budget Office
RePEc: Research Papers in Economics · preprint · 0 scholarly citations

This paper is behind a paywall; we link to the publisher only.

Cited in 3 places in policy documents

Testimony on the Navy’s 2025 Shipbuilding Plan and Its Implications for the Shipbuilding Industrial Base

CBO report2025-03-11 · CBO · fn 42
Congressional Budget Office, Acquisition Costs of the Navy's Medium Landing Ship (April 2024), www.cbo.gov/publication/60071
The Navy, which did not specify the size of the ship that it used in its calculations, estimates that the 55 LSMs would cost less than $200 million per ship, on average. In its analysis of the Navy's 2025 shipbuilding plan, CBO estimated the costs of the smaller ship, which the agency projects would be an average of $350 million per ship.42

An Analysis of the Navy’s 2025 Shipbuilding Plan

CBO report2025-01-06 · CBO · fn 42
Congressional Budget Office, Acquisition Costs of the Navy's Medium Landing Ship (April 2024), www.cbo.gov/publication/60071.
The Navy, which did not specify the size of the ship that it used in its calculations, estimates that the 55 LSMs would cost less than $200 million per ship, on average. In its analysis of the Navy's 2025 shipbuilding plan, CBO estimated the costs of the smaller ship, which the agency projects would be an average of $350 million per ship.42

Testimony on How CBO Supports the Congress

CBO report2024-09-11 · CBO · fn 19
Congressional Budget Office, Acquisition Costs of the Navy's Medium Landing Ship (April 2024), www.cbo.gov/publication/60071.
CBO also sometimes compares its work with the policy analyses of other organizations.19 Comparisons are often discussed with Congressional staff when time does not allow for a formal presentation.