{"document":{"doc_id":80796,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Proposed Rule","title":"In Situ Recovery Monitoring and Decommissioning Timeliness","date":"2026-09-10","url":"https://www.federalregister.gov/documents/2026/09/10/2026-18504/in-situ-recovery-monitoring-and-decommissioning-timeliness","source_native_id":"2026-18504","status":"fetched","abstract":"The U.S. Nuclear Regulatory Commission (NRC) proposes to amend its regulations that govern the licensing of uranium mills and the disposition of tailings and waste that arise from the extraction and milling of uranium by issuing risk-informed requirements for groundwater protection at uranium in situ recovery (ISR) facilities. The NRC's current regulations are focused on conventional uranium milling and do not expressly address uranium extraction by the ISR process. Additionally, NRC proposes to amend its regulations that govern decommissioning timeliness for all licensees to provide additional flexibility for licensees to delay the initiation of decommissioning activities in situations where safety would not be impacted.","action":"Proposed rule and draft guidance; request for comment."},"dockets":["NRC-2025-1204"],"rins":["RIN 3150-AL48"],"related":[{"doc_id":168674,"source":"docket_item","org":"NRC","doc_type":"other","title":"10-23-25 Letter from Eric Hiede to Chairman Wright","date":"2025-11-19"},{"doc_id":168675,"source":"docket_item","org":"NRC","doc_type":"other","title":"10-29-25 Letter from Katie Sweeney NMA to NRC Chairman Wright","date":"2025-11-19"},{"doc_id":168676,"source":"docket_item","org":"NRC","doc_type":"other","title":"10-16-25 Letter from Travis Deti WMA to Chairman Wright","date":"2025-11-19"}],"references":[{"citation_id":539488,"raw_reference":"Regulatory Analysis, “In Situ Recovery & Decommissioning Timeliness,” August 2026 ML26243A343","cited_authors":null,"cited_year":"2026","cited_title":"In Situ Recovery & Decommissioning Timeliness (Regulatory Analysis)","cited_venue":"U.S. Nuclear Regulatory Commission","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Availability of Documents table (ML26243A343)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539489,"raw_reference":"NUREG 1569, “Standard Review Plan for In Situ Leach Uranium Extraction License Applications,” June 2003 ML032250177","cited_authors":"U.S. Nuclear Regulatory Commission","cited_year":"2003","cited_title":"Standard Review Plan for In Situ Leach Uranium Extraction License Applications (NUREG-1569)","cited_venue":"NUREG","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Supplementary Information; Availability of Documents (ML032250177)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539490,"raw_reference":"NUREG/CR-6733, “A Baseline Risk-Informed, Performance-Based Approach for In Situ Leach Uranium Extraction Licensees,” September 2001 ML14236A064","cited_authors":"U.S. Nuclear Regulatory Commission (CR report)","cited_year":"2001","cited_title":"A Baseline Risk-Informed, Performance-Based Approach for In Situ Leach Uranium Extraction Licensees (NUREG/CR-6733)","cited_venue":"NUREG/CR","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Supplementary Information; Availability of Documents (ML14236A064)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539491,"raw_reference":"NUREG/CR-3967, “An Analysis of Excursions at Selected In Situ Uranium Mines in Wyoming and Texas,” July 1986 ML14237A635","cited_authors":"U.S. Nuclear Regulatory Commission (CR report)","cited_year":"1986","cited_title":"An Analysis of Excursions at Selected In Situ Uranium Mines in Wyoming and Texas (NUREG/CR-3967)","cited_venue":"NUREG/CR","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Criterion 14(b)(4) discussion; Availability of Documents (ML14237A635)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539492,"raw_reference":"SECY-21-0067, Enclosure 1—Proposed Rule. 2021 ML21067A127","cited_authors":"U.S. Nuclear Regulatory Commission staff","cited_year":"2021","cited_title":"SECY-21-0067, Enclosure 1—Proposed Rule, Groundwater Protection at Uranium In Situ Recovery Facilities","cited_venue":"NRC SECY paper","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Current Rulemaking Context and Development; Availability of Documents (ML21067A127)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539493,"raw_reference":"SECY-19-0123, “Regulatory Options for Uranium In Situ Recovery Facilities,” December 16, 2019 ML19221B519","cited_authors":"U.S. Nuclear Regulatory Commission staff","cited_year":"2019","cited_title":"Regulatory Options for Uranium In Situ Recovery Facilities (SECY-19-0123)","cited_venue":"NRC SECY paper","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Current Rulemaking Context and Development; Availability of Documents (ML19221B519)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539494,"raw_reference":"SRM-SECY-19-0123, “Staff Requirements—Regulatory Options for In Situ Recovery Facilities,” October 22, 2020 ML20296A469","cited_authors":"U.S. Nuclear Regulatory Commission","cited_year":"2020","cited_title":"Staff Requirements Memorandum — Regulatory Options for In Situ Recovery Facilities (SRM-SECY-19-0123)","cited_venue":"NRC SRM","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Current Rulemaking Context and Development; Availability of Documents (ML20296A469)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539495,"raw_reference":"“Memorandum of Understanding Between the U.S. Nuclear Regulatory Commission and the U.S. Environmental Protection Agency Concerning the Regulation of Uranium in situ Recovery Activities,” July 23, 2020 ML20218A248","cited_authors":"U.S. Nuclear Regulatory Commission; U.S. Environmental Protection Agency","cited_year":"2020","cited_title":"Memorandum of Understanding Between the NRC and EPA Concerning the Regulation of Uranium In Situ Recovery Activities","cited_venue":"Interagency MOU","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Section D; Availability of Documents (ML20218A248)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539496,"raw_reference":"Draft Interim Staff Guidance (ISG) DUWP-ISG-04, “Requirements for the Initiation of Decommissioning for Nuclear Materials Facilities” ML26243A379","cited_authors":"U.S. Nuclear Regulatory Commission staff","cited_year":"2026","cited_title":"DUWP-ISG-04: Requirements for the Initiation of Decommissioning for Nuclear Materials Facilities (Draft ISG)","cited_venue":"NRC draft guidance","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Availability of Guidance; Availability of Documents (ML26243A379)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539497,"raw_reference":"DUWP-ISG-05, “Approval of an Alternate Schedule for Decommissioning of Nuclear Reactor Facilities Beyond 60 Years from Permanent Cessation of Operations” ML26243A380","cited_authors":"U.S. Nuclear Regulatory Commission staff","cited_year":"2026","cited_title":"DUWP-ISG-05: Approval of an Alternate Schedule for Decommissioning of Nuclear Reactor Facilities Beyond 60 Years (Draft ISG)","cited_venue":"NRC draft guidance","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Availability of Guidance; Availability of Documents (ML26243A380)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539498,"raw_reference":"OMB Supporting Statement—ISR & Decommissioning Timelines Proposed Rule ML25337A102","cited_authors":"Office of Management and Budget / NRC","cited_year":"2025","cited_title":"OMB Supporting Statement — ISR & Decommissioning Timelines Proposed Rule","cited_venue":"OMB/NRC paperwork submission","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Availability of Documents (ML25337A102)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539499,"raw_reference":"OMB Burden Tables—ISR & Decommissioning Timelines Proposed Rule ML26013A038","cited_authors":"Office of Management and Budget / NRC","cited_year":"2026","cited_title":"OMB Burden Tables — ISR & Decommissioning Timelines Proposed Rule","cited_venue":"OMB/NRC paperwork submission","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Availability of Documents (ML26013A038)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539500,"raw_reference":"SECY-24-0073, “Site-Specific Considerations for Review of Requests to Complete Power Reactor Decommissioning Beyond 60 Years from Permanent Cessation of Operations,” September 3, 2024 ML24100A760","cited_authors":"U.S. Nuclear Regulatory Commission staff","cited_year":"2024","cited_title":"Site-Specific Considerations for Review of Requests to Complete Power Reactor Decommissioning Beyond 60 Years (SECY-24-0073)","cited_venue":"NRC SECY paper","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Background: Decommissioning Timeliness; Availability of Documents (ML24100A760)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539501,"raw_reference":"NUREG-1757 Vol. 1, Revision 2, “Consolidated Decommissioning Guidance: Decommissioning Process for Materials Licensees,” September 2006 ML063000243","cited_authors":"U.S. Nuclear Regulatory Commission","cited_year":"2006","cited_title":"Consolidated Decommissioning Guidance: Decommissioning Process for Materials Licensees (NUREG-1757 Vol. 1, Rev. 2)","cited_venue":"NUREG","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Availability of Documents (ML063000243)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539502,"raw_reference":"NUREG-1757 Vol. 3, Revision 1, “Consolidated Decommissioning Guidance: Financial Assurance, Recordkeeping, and Timeliness,” February 2012 ML12048A683","cited_authors":"U.S. Nuclear Regulatory Commission","cited_year":"2012","cited_title":"Consolidated Decommissioning Guidance: Financial Assurance, Recordkeeping, and Timeliness (NUREG-1757 Vol. 3, Rev. 1)","cited_venue":"NUREG","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Discussion of extension request criteria; Availability of Documents (ML12048A683)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539503,"raw_reference":"Regulatory Guide (RG) 1.185, “Standard Format and Content for Post-Shutdown Decommissioning Activities Report,” June 2013 ML13140A038","cited_authors":"U.S. Nuclear Regulatory Commission","cited_year":"2013","cited_title":"Regulatory Guide 1.185: Standard Format and Content for Post-Shutdown Decommissioning Activities Report","cited_venue":"NRC Regulatory Guide","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Background: Decommissioning Timeliness; Availability of Documents (ML13140A038)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539504,"raw_reference":"Letter from Wyoming Mining Association on the Proposed ISR Rulemaking, October 16, 2025 ML25322A241","cited_authors":"Wyoming Mining Association","cited_year":"2025","cited_title":"Letter on Proposed ISR Rulemaking","cited_venue":"Public comment / correspondence","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Current Rulemaking Context and Development; Availability of Documents (ML25322A241)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539505,"raw_reference":"Letter from Cameco Resources on proposed uranium in situ recovery rulemaking, October 23, 2025 ML25322A232","cited_authors":"Cameco Resources","cited_year":"2025","cited_title":"Letter on Proposed Uranium In Situ Recovery Rulemaking","cited_venue":"Public comment / correspondence","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Current Rulemaking Context and Development; Availability of Documents (ML25322A232)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":539506,"raw_reference":"Letter from National Mining Association on Upcoming NRC Rulemaking on Groundwater Protection at Uranium in Situ Recovery Facilities, October 29, 2025 ML25304A001","cited_authors":"National Mining Association","cited_year":"2025","cited_title":"Letter on Upcoming NRC Rulemaking on Groundwater Protection at Uranium In Situ Recovery Facilities","cited_venue":"Public comment / correspondence","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Current Rulemaking Context and Development; Availability of Documents (ML25304A001)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null}]}