Effluent Limitations Guidelines and Standards for the Steam Electric Power Generating Point Source Category-Deadline Extensions
The U.S. Environmental Protection Agency (the EPA or Agency) is proposing a Clean Water Act (CWA) rule to extend deadlines, promulgated in the 2024 "Supplemental Effluent Limitations Guidelines and Standards for the Steam Electric Power Generating Point Source Category" (2024 rule), update the transfer provisions to allow facilities to switch between compliance alternatives, and create authority for an alternative applicability dates and paperwork submission dates, based on site-specific factors. The EPA is also seeking comment on several issues relevant to a separate, future rulemaking on the underlying standards.
Original sourceXML (173 KB)PDF (352 KB)
Other documents for the same rulemaking (all, by stage)
References: 13 extracted, 0 linked to papers
Howland, E. 2025. FERC's Christie Calls for Dispatchable Resources After Grid Operators Come "Close to the Edge." June 27. Available online at: https://www.utilitydive.com/news/ferc-christie-dispatchable-resources-heat-wave-pjm-miso-iso-ne/751821/
Guo, K. 2025. ERCOT Approves $54 Million Plan to Move CenterPoint's Mobile Generators to San Antonio. February 25.
U.S. DOE (Department of Energy). 2025. Secretary Wright Issues Emergency Order to Secure Southeast Power Grid Amid Heat Wave. June 24.
We Energies. 2025. We Energies Announces Updated Timeline for Oak Creek Plant Retirements. June 25.
PJM. 2024. Energy Transition in PJM: Flexibility for the Future. June 24.
IEA (International Energy Agency). 2025. Energy Supply for AI. Available online at: https://www.iea.org/reports/energy-and-ai/energy-supply-for-ai
Illinois Drives Electric. 2025. CEJA and Climate Action. Available online at: https://ev.illinois.gov/illinois-commitment/ceja-and-climate-action.html
American Electric Power. 2015. AEP Ohio Files Settlement Agreement on Expanded PPA Agreement Provides Price Stability, Supports Economic Development, Adds Significant Environmental Commitments. December 14.
https://penncapital-star.com/energy-environment/pjm-capacity-price-hits-cap-as-clean-energy-projects-remain-stalled/. (DCN: SE11973).
In the December 2024 LTRA, the NERC identified increasing resource adequacy challenges for the upcoming 10 years (DCN: SE11905).
The MISO recently affirmed the importance of these resources in its 2024 Reliability Imperative report (DCN: SE11929).
In its 2024 U.S. Data Center Energy Usage Report, the DOE found that "U.S. data center energy use has continued to grow at an increasing rate . . ." (DCN: SE11906).
The National Renewable Energy Center's "Data Center Infrastructure for 2025" (DCN: SE11922).