{"document":{"doc_id":72452,"source":"fr_rule","org":"DEPARTMENT OF THE INTERIOR; Bureau of Ocean Energy Management; Bureau of Safety and Environmental Enforcement","doc_type":"Rule","title":"Renewable Energy Modernization Rule","date":"2024-05-15","url":"https://www.federalregister.gov/documents/2024/05/15/2024-08791/renewable-energy-modernization-rule","source_native_id":"2024-08791","status":"fetched","abstract":"The Department of the Interior (the Department or DOI), acting through the Bureau of Ocean Energy Management (BOEM) and the Bureau of Safety and Environmental Enforcement (BSEE) (\"the agencies\"), is finalizing regulatory amendments to its renewable energy regulations under the authority of the Outer Continental Shelf Lands Act (OCSLA). The notice of proposed rulemaking (NPRM) for this final rule was published in the Federal Register on January 30, 2023. While the NPRM contemplated amendments only to the Department's existing renewable energy regulations that are administered by BOEM, this final rule also finalizes regulatory amendments previously proposed by BOEM that are now administered by BSEE and includes amendments to regulations resulting from the \"Reorganization of Title 30--Renewable Energy and Alternative Uses of Existing Facilities on the Outer Continental Shelf\" direct final rule, issued by the Department on January 31, 2023. This final rule eliminates unnecessary requirements for the deployment of meteorological (met) buoys; increases survey flexibility; improves the project design and installation verification process; establishes a public Renewable Energy Leasing Schedule; reforms BOEM's renewable energy auction regulations; tailors financial assurance requirements and instruments; clarifies safety management system regulations; revises other provisions; and makes technical corrections. This final rule advances the Department's energy policies in a safe and environmentally sound manner that will provide a fair return to the U.S. taxpayer.","action":"Final rule."},"dockets":["BOEM-2023-0005"],"rins":["RIN 1010-AE04"],"related":[{"doc_id":72473,"source":"fr_rule","org":"DEPARTMENT OF THE INTERIOR; Bureau of Ocean Energy Management","doc_type":"Proposed Rule","title":"Renewable Energy Modernization Rule","date":"2023-01-30"},{"doc_id":128271,"source":"docket_item","org":"BOEM","doc_type":"analysis","title":"Mod Rule RIA_FINAL","date":"2023-01-30"},{"doc_id":204249,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Draft Form Performance Measures Data","date":"2023-01-30"},{"doc_id":204252,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Mod Rule CER","date":"2023-01-30"},{"doc_id":72470,"source":"fr_rule","org":"DEPARTMENT OF THE INTERIOR; Bureau of Ocean Energy Management","doc_type":"Proposed Rule (administrative)","title":"Renewable Energy Modernization Rule; Correction","date":"2023-02-06"},{"doc_id":204065,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Note to Stakeholders - Extension of Public Comment Period","date":"2023-03-31"},{"doc_id":72469,"source":"fr_rule","org":"DEPARTMENT OF THE INTERIOR; Bureau of Ocean Energy Management","doc_type":"Proposed Rule","title":"Renewable Energy Modernization Rule","date":"2023-04-03"},{"doc_id":72457,"source":"fr_rule","org":"DEPARTMENT OF THE INTERIOR; Bureau of Safety and Environmental Enforcement; Bureau of Ocean Energy Management","doc_type":"Proposed Rule (administrative)","title":"Renewable Energy Modernization Rule; Correction","date":"2024-01-03"},{"doc_id":81745,"source":"ria","org":"BOEM","doc_type":"regulatory_impact_analysis","title":"Reference used in the RIA: An excerpt of the relevant chapter from The Cost of Offshore Wind Energy in the United States from 2025 - 2050. NREL Technical Report, in review.","date":"2024-05-15"},{"doc_id":81750,"source":"ria","org":"BOEM","doc_type":"regulatory_impact_analysis","title":"Renewable Energy Modernization Final Rule Regulatory Impact Analysis","date":"2024-05-15"},{"doc_id":201006,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Stakeholder Meeting: ACP (July 18, 2023)","date":"2024-05-15"},{"doc_id":201007,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Consultation Invitation","date":"2024-05-15"},{"doc_id":201008,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Letter from BOEM to Makah Tribal Council","date":"2024-05-15"},{"doc_id":201009,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Stakeholder Meeting: Shell (November 21, 2023)","date":"2024-05-15"},{"doc_id":201010,"source":"docket_item","org":"BOEM","doc_type":"other","title":"ANCSA Outreach: Consultation Invitation","date":"2024-05-15"},{"doc_id":201011,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Stakeholder Meeting: ACP (August 31, 2023)","date":"2024-05-15"},{"doc_id":201012,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Summary Memo of Outreach on Renewable Energy Modernization Rule","date":"2024-05-15"},{"doc_id":201013,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Stakeholder Meeting: ACP (August 21, 2023)","date":"2024-05-15"},{"doc_id":201014,"source":"docket_item","org":"BOEM","doc_type":"other","title":"NEPA Categorical Exclusion Review for Final Rule","date":"2024-05-15"},{"doc_id":201015,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach:  BOEM and BSEE engagement with the Tribes on the renewable energy modernization final rule","date":"2024-05-15"},{"doc_id":201016,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Stakeholder Meeting: ACP (August 15, 2023)","date":"2024-05-15"},{"doc_id":201017,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Shinnecock Indian Nation","date":"2024-05-15"},{"doc_id":201018,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Resighini Rancheria","date":"2024-05-15"},{"doc_id":201019,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Mashpee Wampanoag Tribe to discuss the renewable energy modernization final rule","date":"2024-05-15"},{"doc_id":201020,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Makah Tribe (June 29, 2023)","date":"2024-05-15"},{"doc_id":201021,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: CTCLUSI","date":"2024-05-15"},{"doc_id":201022,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Makah Tribe (May 17, 2023)","date":"2024-05-15"},{"doc_id":201023,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Mashpee Wampanoag Tribe","date":"2024-05-15"},{"doc_id":201024,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Makah Tribe (June 12, 2023)","date":"2024-05-15"},{"doc_id":201025,"source":"docket_item","org":"BOEM","doc_type":"other","title":"Tribal Outreach: Hoh Tribe","date":"2024-05-15"}],"references":[{"citation_id":425318,"raw_reference":"Reorganization of Title 30—Renewable Energy and Alternative Uses of Existing Facilities on the Outer Continental Shelf direct final rule, issued by the Department on January 31, 2023","cited_authors":null,"cited_year":"2023","cited_title":"Reorganization of Title 30—Renewable Energy and Alternative Uses of Existing Facilities on the Outer Continental Shelf","cited_venue":"Department of the Interior","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Summary","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":425319,"raw_reference":"Office of Inspector Gen., Dept of Interior, U.S. Department of the Interior's Offshore Renewable Energy Program 9 (2013) (Report No. CR-EV-BOEM-0001-2013).","cited_authors":"Office of Inspector General, Department of the Interior","cited_year":"2013","cited_title":"U.S. Department of the Interior's Offshore Renewable Energy Program","cited_venue":"Department of the Interior Office of Inspector General","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"fn 8","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":425320,"raw_reference":"BOEM report 2018-054 by DNV","cited_authors":"Det Norske Veritas","cited_year":"2018","cited_title":"BOEM report 2018-054","cited_venue":"Bureau of Ocean Energy Management","cited_doi":null,"cited_url":"https://www.boem.gov/sites/default/files/environmental-stewardship/Environmental-Studies/Renewable-Energy/Data-Gathering-Process.pdf","ref_kind":"research_report","section":"fn 12","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":425321,"raw_reference":"A Citizen's Guide to the Bureau of Ocean Energy Management's Renewable Energy Authorization Process, Dec. 2016","cited_authors":"Bureau of Ocean Energy Management","cited_year":"2016","cited_title":"A Citizen's Guide to the Bureau of Ocean Energy Management's Renewable Energy Authorization Process","cited_venue":"Bureau of Ocean Energy Management","cited_doi":null,"cited_url":"https://www.boem.gov/sites/default/files/renewable-energy-program/KW-CG-Broch.pdf","ref_kind":"government_report","section":"fn 10","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":425322,"raw_reference":"Information Needed for Issuance of a Notice of Intent (NOI) Under the National Environmental Policy Act (NEPA) for a Construction and Operations Plan (COP)","cited_authors":"Bureau of Ocean Energy Management","cited_year":"2023","cited_title":"Information Needed for Issuance of a Notice of Intent (NOI) Under the National Environmental Policy Act (NEPA) for a Construction and Operations Plan (COP)","cited_venue":"Bureau of Ocean Energy Management","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Response to comments on COP data requirements (section II.C.2)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":425885,"raw_reference":"Renewable Energy Modernization Rule: Initial Regulatory Impact Analysis, Docket No. BOEM-2023-0005","cited_authors":"BOEM","cited_year":null,"cited_title":"Renewable Energy Modernization Rule: Initial Regulatory Impact Analysis","cited_venue":"Docket No. BOEM-2023-0005","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"VI.B Regulatory Flexibility Act (RFA)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":425886,"raw_reference":"Renewable Energy Modernization Rule Final Regulatory Impact Analysis","cited_authors":"BOEM","cited_year":null,"cited_title":"Renewable Energy Modernization Rule Final Regulatory Impact Analysis","cited_venue":"Docket","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"VI.A Executive Order 12866","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":426958,"raw_reference":"Recommendations for Pre-Notice of Intent (NOI) Federal Interagency Engagement on Construction and Operations Plans (COP) for Offshore Wind, (Aug. 2023)","cited_authors":"BOEM","cited_year":"2023","cited_title":"Recommendations for Pre-Notice of Intent (NOI) Federal Interagency Engagement on Construction and Operations Plans (COP) for Offshore Wind","cited_venue":"Bureau of Ocean Energy Management","cited_doi":null,"cited_url":"https://www.boem.gov/sites/default/files/documents/renewable-energy/state-activities/BOEM%20NOI%20Checklist.pdf","ref_kind":"government_report","section":"fn 17","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":426959,"raw_reference":"Standardizing Integrated Ecosystem-Based Assessments (SIEBA) study","cited_authors":"BOEM","cited_year":null,"cited_title":"Standardizing Integrated Ecosystem-Based Assessments (SIEBA)","cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"3. Environmental Reviews and Evaluations (Response on PEIS and regional studies)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":427198,"raw_reference":"Safety Management System Expectations for Renewable Energy Companies Operating on the OCS, posted on the BSEE website at https://www.bsee.gov/technical-presentations/ooc-presentation-sms-in-ocs-renewable-projects-may-13","cited_authors":"BSEE","cited_year":null,"cited_title":"Safety Management System Expectations for Renewable Energy Companies Operating on the OCS","cited_venue":"BSEE website","cited_doi":null,"cited_url":"https://www.bsee.gov/technical-presentations/ooc-presentation-sms-in-ocs-renewable-projects-may-13","ref_kind":"web_page","section":"Summary of comments, § 285.810 (SMS comment response)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":427217,"raw_reference":"Offshore Wind Submarine Cable Spacing Guidance | Bureau of Ocean Energy Management: https://www.boem.gov/newsroom/notes-stakeholders/offshore-wind-submarine-cable-spacing-guidance","cited_authors":"Bureau of Ocean Energy Management","cited_year":"2015","cited_title":"Offshore Wind Submarine Cable Spacing Guidance","cited_venue":"Bureau of Ocean Energy Management","cited_doi":null,"cited_url":"https://www.boem.gov/newsroom/notes-stakeholders/offshore-wind-submarine-cable-spacing-guidance","ref_kind":"government_report","section":"L/M. Potential Revisions to Regulations Governing Transmission, Response on spacing","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":427218,"raw_reference":"An Action Plan for Offshore Wind Transmission Development in the U.S. Atlantic Region (https://www.energy.gov/gdo/atlantic-offshore-wind-transmission-action-plan)","cited_authors":"DOE and BOEM","cited_year":"2023","cited_title":"An Action Plan for Offshore Wind Transmission Development in the U.S. Atlantic Region","cited_venue":"U.S. Department of Energy and Bureau of Ocean Energy Management","cited_doi":null,"cited_url":"https://www.energy.gov/gdo/atlantic-offshore-wind-transmission-action-plan","ref_kind":"government_report","section":"M. Potential Revisions to Regulations Governing Transmission, Section 3","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":427219,"raw_reference":"Offshore Compliance Recommended Practices: 2022 Edition (OCRP-1-2022)","cited_authors":null,"cited_year":"2022","cited_title":"Offshore Compliance Recommended Practices: 2022 Edition","cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"other","section":"G. Risk Management and Financial Assurance, Response on hurricanes and weather risks","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":427220,"raw_reference":"Safety Management System Expectations for Renewable Energy Companies Operating on the OCS","cited_authors":"Bureau of Safety and Environmental Enforcement","cited_year":null,"cited_title":"Safety Management System Expectations for Renewable Energy Companies Operating on the OCS","cited_venue":"BSEE","cited_doi":null,"cited_url":"https://www.bsee.gov/technical-presentations/ooc-presentation-sms-in-ocs-renewable-projects-may-13","ref_kind":"web_page","section":"H. Safety Management Systems, Response on SMS clarification guidance","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":427221,"raw_reference":"Information Needed for Issuance of a Notice of Intent (NOI) Under the National Environmental Policy Act (NEPA) for a Construction and Operations Plan (COP), (Aug. 2023)","cited_authors":"Bureau of Ocean Energy Management","cited_year":"2023","cited_title":"Information Needed for Issuance of a Notice of Intent (NOI) Under the National Environmental Policy Act (NEPA) for a Construction and Operations Plan (COP)","cited_venue":"Bureau of Ocean Energy Management","cited_doi":null,"cited_url":"https://www.boem.gov/sites/default/files/documents/renewable-energy/state-activities/BOEM%20NOI%20Checklist.pdf","ref_kind":"government_report","section":"K. Other Proposed Changes in Part 585, footnote 15","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null}]}