Regulatory Impact Analysis; EPA's 2019 RCRA Proposed Rule; Hazardous and Solid Waste Management System: Disposal of CCR; A Holistic Approach to Closure Part B: Alternate Demonstration for Unlined Surface Impoundments; Implementation of Closure (February 2020)
Other documents for the same rulemaking (all, by stage)
References: 7 extracted, 0 linked to papers
Geo-Hydro, Inc., 2019, accessed at https://www.regulations.gov/document?D=EPA-HQ-OLEM-2018-0533-0195
Application of Kentucky Utilities Company for Certificates of Public Convenience and Necessity and Approval of its 2016 Compliance Plan for Recovery by Environmental Surcharge, Case No. 2016-00026. Direct Testimony of John N. Voyles, Jr. January 29th, 2016.
U.S. EPA (2014) Guidelines for Preparing Economic Analyses, National Center for Environmental Economics, Office of Policy, U.S. Environmental Protection Agency.
See the Plant Yates closure plan described above (Geo-Hydro, Inc., 2019).
Application of Kentucky Utilities Company for Certificates of Public Convenience and Necessity and Approval of its 2016 Compliance Plan for Recovery by Environmental Surcharge, Case No. 2016-00026. Direct Testimony of John N. Voyles, Jr. January 29th, 2016. Available at: https://lge-ku.com/sites/default/files/documents/KUVoyles%20Testimony-Exhibits.pdf
See filings and testimony associated with the verified petition of Southern Indiana Gas and Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc. with the Indiana Utility Regulatory Commission, filed August 14, 2019, Cause No. 45280.
Department of Energy, Energy Information Administration, published data series of wholesale weighted average costs/MW volume and retail electricity prices can be found at https://www.eia.gov/electricity/wholesale/#history