Coordination of Federal Authorizations for Electric Transmission Facilities

Federal Register2023-08-16 · DEPARTMENT OF ENERGY · Proposed Rule · 2023-17283
Notice of proposed rulemaking and request for comment.

The Department of Energy (DOE) is proposing to amend its regulations for the timely coordination of Federal authorizations for proposed interstate electric transmission facilities pursuant to the Federal Power Act (FPA). Specifically, DOE is proposing to establish an integrated and comprehensive Coordinated Interagency Transmission Authorizations and Permits Program (CITAP Program); make participation by application in the Integrated Interagency Preapplication (IIP) Process a pre-condition for a decision under the CITAP Program; require project proponents to develop resource reports and public engagement plans for communities that would be affected by a proposed qualifying project through an iterative and collaborative process with Federal agencies while providing that Federal entities would remain responsible for completion of environmental reviews, for government-to-government consultation with Indian Tribes (and government-to-sovereign consultation in the context of Native Hawaiian relations), and for any findings and determinations; require project proponents to conduct robust engagement with all Tribes and communities of interest that would be affected by a proposed qualifying project; ensure that DOE may carry out its statutory obligation to prepare a single Environmental Impact Statement (EIS) sufficient for the purposes of all Federal authorizations necessary to site a qualifying project; and align and harmonize the IIP Process and implementation of the FPA with Title 41 of the Fixing America's Surface Transportation (FAST) Act.

RIN 1901-AB62 · Docket DOE-HQ-2023-0050

Other documents for the same rulemaking (all, by stage)

2023-08-22 Federal RegisterCoordination of Federal Authorizations for Electric Transmission Facilities
2024-05-01 Federal RegisterCoordination of Federal Authorizations for Electric Transmission Facilities

References: 8 extracted, 1 linked to papers

Page 1Download these results: CSV · JSON
Millstein, A. et al. (2022) Empirical estimates of transmission value using locational marginal prices, Electricity Markets and Policy Group, 6. Available at: https://emp.lbl.gov/publications/empirical-estimates-transmission.
Grid operation benefits include a reduction in the congestion costs for generating and delivering energy; mitigation of weather and variable generation uncertainty enhanced diversity of supply, which increases market competition and reduces the need for regional backup power options; and increased market liquidity and competition.\12\ From a system planning standpoint, accelerated transmission investments will allow the development of new, low cost power plants in areas of high congestion which might not otherwise see investment due to capacity constraints, and additional grid hardening or resilience.
Berkeley Lab, Queued up: Characteristics of power plants seeking transmission interconnection (2023), Electricity Markets and Policy Group. Available at: https://emp.lbl.gov/queues.
research reportNot linked to a paper · fn 15 · cited link
Transmission congestion costs rise again in U.S. RTOS (2023), Grid Strategies LLC. Available at: https://gridstrategiesllc.com/wp-content/uploads/2023/07/GS_Transmission-Congestion-Costs-in-the-U.S.-RTOs1.pdf.
research reportNot linked to a paper · fn 16 · cited link
Howland, E. (2023) US grid congestion costs jumped 56% to $20.8B in 2022: Report, Utility Dive.
newsNot linked to a paper · fn 18 · cited link
Nationwide transmission congestion costs rise to $20.8 billion in 2022 (2023). Advanced Power Alliance. Available at: https://poweralliance.org/2023/07/13/nationwide-transmission-congestion-costs-rise-to-20-8-billion-in-2022/
web pageNot linked to a paper · fn 19 · cited link
Jenkins, J.D. et al. (2022) Electricity transmission is key to unlock the full potential of the Inflation Reduction Act, Zenodo.
otherNot linked to a paper · fn 20 · cited link
Technical support document: Social cost of carbon, methane, (2021) whitehouse.gov.
government reportNot linked to a paper · fn 22 · cited link
DOE, National Transmission Needs Study (Feb. 2023), available at: https://www.energy.gov/sites/default/files/2023-02/022423-DRAFTNeedsStudyforPublicComment.pdf.
government reportNot linked to a paper · fn 1 · cited link