{"document":{"doc_id":2863,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Rule","title":"Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors","date":"2026-03-30","url":"https://www.federalregister.gov/documents/2026/03/30/2026-06048/risk-informed-technology-inclusive-regulatory-framework-for-advanced-reactors","source_native_id":"2026-06048","status":"fetched","abstract":"The U.S. Nuclear Regulatory Commission (NRC) is amending its regulations by adding a risk-informed, performance-based, and technology-inclusive regulatory framework for commercial nuclear plants in response to the Nuclear Energy Innovation and Modernization Act (NEIMA). The current application and licensing requirements were primarily developed to address license requests concerning light water- cooled reactors and operational requirements for those types of reactors. This final rule responds to NEIMA by creating an alternative, technology-inclusive regulatory framework to accommodate licensing of future commercial nuclear plants, including advanced reactor designs that may not employ light-water technology.","action":"Final rule."},"dockets":["NRC-2019-0062"],"rins":["RIN 3150-AK31"],"related":[{"doc_id":6542,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Proposed Rule","title":"Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors","date":"2020-11-06"},{"doc_id":5994,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Proposed Rule","title":"Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors","date":"2021-11-08"},{"doc_id":6240,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Proposed Rule (administrative)","title":"Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors","date":"2021-12-10"},{"doc_id":4048,"source":"ria","org":"NRC","doc_type":"regulatory_analysis","title":"SECY-23-0021:  Enclosure 3 - Draft Regulatory Analysis","date":"2023-03-07"},{"doc_id":2634,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Proposed Rule","title":"Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors","date":"2024-10-31"},{"doc_id":4051,"source":"ria","org":"NRC","doc_type":"regulatory_analysis","title":"Draft Regulatory Analysis Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors","date":"2024-10-31"},{"doc_id":2656,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Proposed Rule (administrative)","title":"Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors","date":"2024-11-22"},{"doc_id":4055,"source":"ria","org":"NRC","doc_type":"regulatory_analysis","title":"Regulatory Analysis for Risk-Informed Techology-Inclusive Regulatory Framework for Advanced Reactors","date":"2026-03-30"},{"doc_id":127349,"source":"docket_item","org":"NRC","doc_type":"review_record","title":"NRC Form 893 - Single Positive Test (Part 53 Rulemaking) for OIRA","date":"2026-03-30"},{"doc_id":127350,"source":"docket_item","org":"NRC","doc_type":"review_record","title":"NRC Form 361S - Part 53 Plant Event Notification for OIRA","date":"2026-03-30"},{"doc_id":127351,"source":"docket_item","org":"NRC","doc_type":"review_record","title":"NRC Form 396 - Certification of Medical Examination (Part 53 Rulemaking) for OIRA","date":"2026-03-30"},{"doc_id":127352,"source":"docket_item","org":"NRC","doc_type":"review_record","title":"NRC Form 366 - Licensee Event Report (Part 53 Rulemaking) for OIRA","date":"2026-03-30"},{"doc_id":127353,"source":"docket_item","org":"NRC","doc_type":"review_record","title":"NRC Form 366A - Licensee Event Report Continuation Sheet (Part 53 Rulemaking) for OIRA","date":"2026-03-30"},{"doc_id":127354,"source":"docket_item","org":"NRC","doc_type":"review_record","title":"NRC Form 398 - Personal Qualification Statement (Part 53 Rulemaking) for OIRA","date":"2026-03-30"},{"doc_id":127355,"source":"docket_item","org":"NRC","doc_type":"review_record","title":"NRC Form 366B - Licensee Event Report Failure Continuation Sheet (Part 53 Rulemaking) for OIRA","date":"2026-03-30"},{"doc_id":127356,"source":"docket_item","org":"NRC","doc_type":"review_record","title":"NRC Form 894 - Annual Reporting Form (Part 53 Rulemaking) for OIRA","date":"2026-03-30"},{"doc_id":2887,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Rule (administrative)","title":"Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors; Correction","date":"2026-04-13"},{"doc_id":3075,"source":"fr_rule","org":"NUCLEAR REGULATORY COMMISSION","doc_type":"Rule (administrative)","title":"Risk-Informed, Technology-Inclusive Regulatory Framework for Advanced Reactors; Correction","date":"2026-07-28"}],"references":[{"citation_id":699,"raw_reference":"NUREG-1860, \"Feasibility Study for a Risk-Informed and Performance-Based Regulatory Structure for Future Plant Licensing,\" published in 2007.","cited_authors":null,"cited_year":"2007","cited_title":"Feasibility Study for a Risk-Informed and Performance-Based Regulatory Structure for Future Plant Licensing","cited_venue":"NUREG-1860","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"II. Discussion / I. Background, NRC Advanced Reactor Readiness","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":700,"raw_reference":"Nuclear Energy Institute (NEI) 18-04, Revision 1, \"Risk-Informed Performance-Based Technology-Inclusive Guidance for Non-Light Water Reactor Licensing Basis Development,\" issued August 2019.","cited_authors":"Nuclear Energy Institute","cited_year":"2019","cited_title":"Risk-Informed Performance-Based Technology-Inclusive Guidance for Non-Light Water Reactor Licensing Basis Development","cited_venue":"Nuclear Energy Institute","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"I. Background, NRC Advanced Reactor Readiness","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":701,"raw_reference":"\"Report to Congress: Advanced Reactor Licensing,\" issued August 2012.","cited_authors":"U.S. Nuclear Regulatory Commission","cited_year":"2012","cited_title":"Report to Congress: Advanced Reactor Licensing","cited_venue":"U.S. Nuclear Regulatory Commission","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"II. Discussion, B. Need for Changes to the Existing Regulatory Framework","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":702,"raw_reference":"NUREG/BR-0058, \"Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission.\"","cited_authors":"U.S. Nuclear Regulatory Commission","cited_year":null,"cited_title":"Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission","cited_venue":"NUREG/BR-0058","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"III. Part 53 Framework, Subpart B","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":703,"raw_reference":"NUREG-0880, Safety Goals policy-related reference (consistent with NUREG-0880)","cited_authors":"U.S. Nuclear Regulatory Commission","cited_year":null,"cited_title":null,"cited_venue":"NUREG-0880","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"III. Part 53 Framework, Subpart B","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":704,"raw_reference":"American Society of Civil Engineers (ASCE)/Structural Engineering Institute (SEI) 43-19, \"Seismic Design Criteria for Structures, Systems, and Components in Nuclear Facilities\"","cited_authors":"American Society of Civil Engineers; Structural Engineering Institute","cited_year":"2019","cited_title":"Seismic Design Criteria for Structures, Systems, and Components in Nuclear Facilities","cited_venue":"ASCE/SEI 43-19","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"III. Part 53 Framework, Subpart C (§ 53.480)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":705,"raw_reference":"ASME/American Nuclear Society Risk Assessment Standard (RA-S)-1.4-2021","cited_authors":"American Society of Mechanical Engineers; American Nuclear Society","cited_year":"2021","cited_title":"Risk Assessment Standard (RA-S)-1.4-2021","cited_venue":"ASME/ANS","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"III. Part 53 Framework, A. Discussion of Definitions in Part 53","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7826,"raw_reference":"NUREG/CR-5884, \"Revised Analyses of Decommissioning for the Reference Pressurized Water Reactor Power Station,\"","cited_authors":null,"cited_year":null,"cited_title":"Revised Analyses of Decommissioning for the Reference Pressurized Water Reactor Power Station","cited_venue":"NUREG/CR-5884","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Subpart G—Decommissioning Requirements","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7827,"raw_reference":"NUREG/CR-6187, \"Revised Analyses of Decommissioning for the Reference Boiling Water Reactor Power Station.\"","cited_authors":null,"cited_year":null,"cited_title":"Revised Analyses of Decommissioning for the Reference Boiling Water Reactor Power Station","cited_venue":"NUREG/CR-6187","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Subpart G—Decommissioning Requirements","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7828,"raw_reference":"NUREG/CR-2601, \"Technology, Safety and Costs of Decommissioning Reference Light Water Reactors Following Postulated Accidents.\"","cited_authors":null,"cited_year":null,"cited_title":"Technology, Safety and Costs of Decommissioning Reference Light Water Reactors Following Postulated Accidents","cited_venue":"NUREG/CR-2601","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Subpart H—Section 53.1720","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7829,"raw_reference":"Irene Wærø, Ragnar Rosness, and Stine Skaufel Kilska, \"Human performance and safety in Arctic environments,\" SINTEF (2018).","cited_authors":"Irene Wærø, Ragnar Rosness, Stine Skaufel Kilska","cited_year":"2018","cited_title":"Human performance and safety in Arctic environments","cited_venue":"SINTEF","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"fn 3","page":null,"context_sentence":null,"paper_id":622,"paper_title":"Human performance and safety in Arctic environments","paper_year":2018,"paper_doi":null},{"citation_id":7830,"raw_reference":"Russell Mannion and Carl Thompson, \"Systematic biases in group decision-making: implications for patient safety,\" International Journal for Quality in Health Care, Vol. 26, No. 6 (2014): 606-612.","cited_authors":"Russell Mannion, Carl Thompson","cited_year":"2014","cited_title":"Systematic biases in group decision-making: implications for patient safety","cited_venue":"International Journal for Quality in Health Care, Vol. 26, No. 6","cited_doi":"10.1093/intqhc/mzu083","cited_url":null,"ref_kind":"journal_article","section":"fn 4","page":null,"context_sentence":null,"paper_id":623,"paper_title":"Systematic biases in group decision-making: implications for patient safety","paper_year":2014,"paper_doi":"10.1093/intqhc/mzu083"},{"citation_id":7831,"raw_reference":"David Hofmann and Adam Stetzer, \"A Cross-Level Investigation of Factors Influencing Unsafe Behaviors and Accidents,\" Personnel Psychology, Vol. 49 (1996).","cited_authors":"David Hofmann, Adam Stetzer","cited_year":"1996","cited_title":"A Cross-Level Investigation of Factors Influencing Unsafe Behaviors and Accidents","cited_venue":"Personnel Psychology, Vol. 49","cited_doi":"10.1111/j.1744-6570.1996.tb01802.x","cited_url":null,"ref_kind":"journal_article","section":"fn 5","page":null,"context_sentence":null,"paper_id":624,"paper_title":"A CROSS‐LEVEL INVESTIGATION OF FACTORS INFLUENCING UNSAFE BEHAVIORS AND ACCIDENTS","paper_year":1996,"paper_doi":"10.1111/j.1744-6570.1996.tb01802.x"},{"citation_id":7832,"raw_reference":"NEI 22-05, Revision 0, \"Technology Inclusive Risk Informed Change Evaluation (TIRICE).\"","cited_authors":"Nuclear Energy Institute","cited_year":null,"cited_title":"Technology Inclusive Risk Informed Change Evaluation (TIRICE)","cited_venue":"Nuclear Energy Institute","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Subpart I—Section 53.1550","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7915,"raw_reference":"PNNL, Technical Letter Report, “The Use of Electronic Communications to Perform Determinations of Fitness,” dated August 2017.","cited_authors":"PNNL","cited_year":"2017","cited_title":"The Use of Electronic Communications to Perform Determinations of Fitness","cited_venue":"Pacific Northwest National Laboratory","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"fn 9","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7916,"raw_reference":"National Library of Medicine, National Institutes of Health, Workshop Summary, “The Evolution of Telehealth: Where Have We Been and Where Are We Going?,” dated November 2012","cited_authors":"National Library of Medicine, National Institutes of Health","cited_year":"2012","cited_title":"The Evolution of Telehealth: Where Have We Been and Where Are We Going?","cited_venue":"National Library of Medicine, National Institutes of Health","cited_doi":null,"cited_url":"https://www.ncbi.nlm.nih.gov/books/NBK207141/","ref_kind":"research_report","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7917,"raw_reference":"NUREG-1530, Revision 1, “Reassessment of NRC's Dollar Per Person-Rem Conversion Factor Policy, Final Report,” dated February 2022","cited_authors":"NRC","cited_year":"2022","cited_title":"Reassessment of NRC's Dollar Per Person-Rem Conversion Factor Policy, Final Report","cited_venue":"NUREG-1530, Revision 1","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7918,"raw_reference":"NUREG-1860, Volumes 1 and 2, “Feasibility Study for a Risk-Informed and Performance-Based Regulatory Structure for Future Plant Licensing,” dated December 2007","cited_authors":"NRC","cited_year":"2007","cited_title":"Feasibility Study for a Risk-Informed and Performance-Based Regulatory Structure for Future Plant Licensing","cited_venue":"NUREG-1860","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7919,"raw_reference":"Nuclear Innovation Alliance (NIA), “Clarifying `Major Portions' of a Reactor Design in Support of a Standard Design Approval,” dated April 2017","cited_authors":"Nuclear Innovation Alliance","cited_year":"2017","cited_title":"Clarifying Major Portions of a Reactor Design in Support of a Standard Design Approval","cited_venue":"Nuclear Innovation Alliance","cited_doi":null,"cited_url":"https://www.nuclearinnovationalliance.org/clarifying-major-portions-reactor-design-support-standard-design-approval","ref_kind":"research_report","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7920,"raw_reference":"Research Information Letter 2021-04, “Feasibility Study on a Potential Consequence-Based Seismic Design Approach for Nuclear Facilities,” dated April 2021","cited_authors":"NRC","cited_year":"2021","cited_title":"Feasibility Study on a Potential Consequence-Based Seismic Design Approach for Nuclear Facilities","cited_venue":"NRC Research Information Letter 2021-04","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7921,"raw_reference":"ASCE/SEI 43-19, “Seismic Design Criteria for Structures, Systems, and Components in Nuclear Facilities”","cited_authors":"ASCE/SEI","cited_year":"2019","cited_title":"Seismic Design Criteria for Structures, Systems, and Components in Nuclear Facilities","cited_venue":"American Society of Civil Engineers","cited_doi":"10.1061/9780784415405","cited_url":"https://doi.org/10.1061/9780784415405","ref_kind":"other","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":227,"paper_title":"Seismic Design Criteria for Structures, Systems, and Components in Nuclear Facilities","paper_year":2021,"paper_doi":"10.1061/9780784415405"},{"citation_id":7922,"raw_reference":"NUREG/CR-2601, “Technology, Safety and Costs of Decommissioning Reference Light Water Reactors Following Postulated Accidents” dated November 1982","cited_authors":"NRC","cited_year":"1982","cited_title":"Technology, Safety and Costs of Decommissioning Reference Light Water Reactors Following Postulated Accidents","cited_venue":"NUREG/CR-2601","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7923,"raw_reference":"NUREG/CR-5884, “Revised Analyses of Decommissioning for the Reference Pressurized Water Reactor Power Station,” dated November 1995","cited_authors":"NRC","cited_year":"1995","cited_title":"Revised Analyses of Decommissioning for the Reference Pressurized Water Reactor Power Station","cited_venue":"NUREG/CR-5884","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":7924,"raw_reference":"NUREG/CR-6187, Volume 1, “Revised Analyses of Decommissioning for the Reference Boiling Water Reactor Power Station,” dated July 1996","cited_authors":"NRC","cited_year":"1996","cited_title":"Revised Analyses of Decommissioning for the Reference Boiling Water Reactor Power Station","cited_venue":"NUREG/CR-6187","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Availability of Documents","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null}]}