Report to Congress - Implementation and Enforcement of the Combined Sewer Overflow Control Policy
Other documents for the same rulemaking (all, by stage)
References: 27 extracted, 0 linked to papers
ATL-5 Bremerton, WA—Region 10 Community Case Study S Outfall $ Wastewater Treatment Plant Number of CSO Outfalls Dyes Inlet Combined Sewer Area 19 (originally) 16 (currently) East Bremerton Combined Sewer Service Area 5.2 square miles Wastewater Treatment Capacity 32.5 mgd (primary) 7.6 mgd (secondary) ir I Bremerton Receiving Water(s) Port Washington Narrows, Dyes Inlet and Sinclair Inlet of Puget Sound Kitsap County, WA Program Highlights Controls ● Sewer separation projects were initiated in 1983. ● CSO outfalls have been reduced from 19 to 16. ● The city ordinance provides reimbursement for storm water
Ballbach, D. 1999. Mediation Resolution, Agreed Amendments to September 27, 1993 Consent Decree. Signed by the Puget Soundkeeper Alliance and the City of Bremerton.
Berthiaume, Chance, and City of Bremerton. 2000. "City of Bremerton's CSO Reduction Program and Drinking Water Quality & Conservation." http://www.cityofbremerton.com Black and Veatch, 2000. 2000 Washington Water and Wastewater Rate Survey. Seattle, WA. CH2M Hill, 1992. Combined Sewer Overflow Reduction Plan. Prepared for the City of
Bremerton, Washington. 1992. City of Bremerton, 1999. Combined Sewer Overflow Reduction Plan—Amendment No. 2.
Bremerton, WA. HDR, 2000. Bremerton CSO Reduction Plan Update. Prepared for the City of Bremerton,
Washington. 2000. BRE-6 Burlington, IA—Region 7 Community Case Study Number of CSO Outfalls 20 (originally) 11 (currently) Combined Sewer Service Area Mississip Wastewater Treatment Capacity 18 mgd Illinois pi River 2.9 square miles Burlington Receiving Water(s) S Outfall Mississippi River $ Wastewater Treatment Plant Combined Sewer Area Controls ● CSO outfalls have been reduced from 20 to 11. ● Burlington has been separating portions of its CSS since the 1970s through major street reconstruction projects. ● Burlington developed a plan to eliminate CSO discharges with sewer separation that will be completed by 2017. ● Work on eliminating individual CSOs started in 1982. ● As part of a 1996 CSO study, a number of CSO control alternatives were evaluated, but the city decided to continue to pursue sewer separation. Program Highlights Photo: Great River Bridge over the Mississippi River in Burlington.
Carhoff, Bob. 2000. "Computer Technology Improves Sewer TV Inspection and Reporting." Public Works, March, pp. 42-43. City of Burlington, Iowa. 1993. Report of Combined Sewer Overflows: Part 1. City of
Burlington, Burlington, IA. City of Burlington, Iowa. 1995. Report of Combined Sewer Overflows: Part 2. City of
GAO, 1979. Combined Sewer Flooding and Pollution—A National Problem: The Search for Solutions in Chicago, CED 79-77. Washington, DC.
MWRDGC, 1998. Report No. 98-23: Water Quality Improvements in the Chicago and Calumet Waterways Between 1975 and 1993 Associated with the Operation of Water Reclamation
AMSA, 1994. Approaches to Combined Sewer Overflow Program Development: A CSO Assessment Report. AMSA, Washington D.C. November 1994.
Kubiak, David, Massachusetts Water Resource Authority, Boston,MA. Personal communication with Limno-Tech, Inc. staff on details of the combined sewer overflow plan and program. Summer 2001.
MWRA, 1994. Final CSO Conceptual Plan and System Master Plan. Boston, MA.
MWRA, 1997. Final CSO Facilities Plan and Environmental Impact Report. Boston, MA.
NMC. ● Better O&M practices (e.g., sewer flushing and street sweeping) have improved system performance during wet weather. ● The presumption approach was used as the basis for development of the LTCP scheduled to be submitted to the state by November 2001. Program Highlights ● Muncie is working on a Use Attainability Analysis (UAA) to request a temporary suspension of designated uses during wet weather.
Amlin, Eugene P.E., 1999. Stream Reach and Characterization and Evaluation Report.
Muncie, IN. Huyck, Richard, Director, Bureau of Water Quality, Muncie Sanitary District. Personal communication with Limno-Tech,Inc. staff on details of CSO system and CSO control planning in Muncie, and review of case study. Spring/Summer 2001.
EPA, 2001. Combined Sewer Overflows in Region 2: Audit Report of the Inspector General. New York, NY.
Killam, 1977. Combined Sewer Overflow Characterization Study. Milburn, NJ.
Fischer, Robert, Executive Director, North Bergen Municipal Utilities Authority. Personal communication with Limno-Tech, Inc. staff on details of the combined sewer overflow plan and program. Summer 2001.
Kooiker, Brian, State of Vermont, Agency of Natural Resources, Department of Environmental Conservation, Wastewater Management Division. Personal communication. Spring/Summer 2001.
Richmond, VA. City of Richmond, Virginia. 2001. Draft Long-Term CSO Control Plan Re-evaluation. Submitted to Virginia Department of Environmental Quality, Richmond, VA.
CA. Personal communication with Limno-Tech, Inc. staff on details of the combined sewer overflow plan and program. Summer 2001.
Portland, ME. City of South Portland, Maine. 1997. Combined Sewer Overflows: Documentation for Nine Minimum Controls. Report submitted to Maine Department of Environmental Protection. South Portland, ME.
Pineo, David, Engineering Department, City of South Portland, ME. Personal communication with Limno-Tech, Inc. staff on details of the combined sewer overflow plan and program. Summer 2001.
DC Department of Health, 2001. Biochemical Oxygen Demand Total Maximum Daily Load for the Anacostia River. Washington, DC. Delon Hampton and Associates (DHA), 1996. CSO Abatement Program: Nine Minimum Control Compliance Report. Prepared for WASA. Washington, DC. Engineering Program Management Consultant (EPMC) III, 1999. Combined Sewer System Nine Minimum Controls Summary Report - Draft. Prepared for WASA. Washington,. DC. Engineering Program Management Consultant (EPMC) III, 2001. Draft Report: Combined Sewer System Long Term Control Plan. Prepared for WASA. Washington, DC.
GGJ Consulting Engineers, Inc., 2001. Capital Needs Improvement Project Review. Report prepared for the City of Wheeling. Wheeling, WV. King Campbell, Superintendent, City of Wheeling Water Pollution Control Division. Personal communication with Limno-Tech, Inc. staff on details of the combined sewer overflow plan and program. Summer 2001.