U.S. EPA Report. Carbon Dioxide Pipelines in the United States. Submitted by The Cadmus Group, Inc., Under Subcontract to Eastern Research Group, Inc. June 25, 2012
Other documents for the same rulemaking (all, by stage)
References: 52 extracted, 0 linked to papers
ADM. 2012. Archer Daniels Midland Permit Application.
Arizona Geology. 2012. Accessed at: http://arizonageology.blogspot.com/2012/04/kinder-morganoutlines-plans-for-major.html
Barrie, J., K. Brown, P.R. Hatcher, and H.U. Schellhase. 2004. Carbon Dioxide Pipelines: A Preliminary Review of Design and Risks. Presented at GHGT 2004.
Bergman, P.P., and E.M. Winter. 1997. Disposal of Power Plant CO2 in Depleted Oil and Gas Reservoirs in Texas. Energy Conversion and Management. V. 38 pp. S211 – S216.
Bock, B., R. Rhudy, H. Herzog, M. Klett, J. Davidson, D.G. De La Torre, and D. Simbeck. 2003. Economic Evaluation of CO2 Storage and Sink Enhancement Options.
BSRCSP. 2012. Accesses at: http://www.bigskyco2.org/research/geologic/kevinstorage Carbon Sequestration Leadership Forum. Undated. CO2 Transportation: Is it Safe and Reliable? http://www.cslforum.org/publications/documents/CSLF_inFocus_CO2Transportation.pdf
Carr, T.R., and M.K. Dubois. 2007. Results of Integrated Biofuels and Value Added Sequestration Project in Russel, KS. Presented at the 6th Annual Conference on Carbon Capture and Sequestration.
CIEE. 2010. Background Reports for the California Carbon Capture and Storage Review Panel. California Institute for Energy and Environment.
Clean Energy Systems. 2012. Accessed at http://www.cleanenergysystems.com/faq.html#17
Cosham, A., and R. Eiber. 2007. Fracture Control in Carbon Dioxide Pipelines. Journal of Pipeline Engineering. 3rd quarter. p. 147
Chapparal Energy. 2011. Wells Fargo Energy Conference. Available at http://www.chaparralenergy.com/pressreleases/Wells%20Fargo%20Energy%20Conference_To%20print %20for%208K%20and%201x1.pdf
DOE. 2006. Final Risk Assessment Report for the FutureGen Project Environmental Impact Statement.
DOE. 2007. Mesaba Energy Project, Draft EIS.
DOE. 2011. Mountaineer Commercial Scale Carbon Capture and Storage Project: Draft Environmental Impact Statement Summary.
Dooley, J.J., R.T. Dahowski, C.L. Davidson. 2009. Comparing Existing Pipeline Networks with the Potential Scale of Future U.S. CO2 Pipeline Networks. Energy Procedia 1. Pp. 1595-1602. Draft June 25, 2012
EPA. 2011. Assessment of the Potential Costs, Benefits, and Other Impact of the Conditional Exclusion from the RCRA Definition of Hazardous Waste for CO2 Streams Managed in UIC Class VI Wells for the Purposes of Geologic Sequestration
FERC. 2006. 115 FERC 962,266 Fredet, A., S. Saysset, P. Odru, P. Broudin, J. Ruer, and M. Bonnisel. 2007. Technical and Economic Assessement of CO2 Transportation for CCS Purposes.
Fugleburg, J. 2011. Construction of Carbon Dioxide Pipeline Starts this Year. Wyoming Star-Tribune May 26, 2011. Global CCS Institute. 2010. Global Status of BECCS Projects 2010.
Hydrogen Energy California. 2009. Revised Application for Certification for Hydrogen Energy California.
INGAA. 2009. Carbon Sequestration and Storage: Developing a Transportation Infrastructure.
IOGCC. 2010. A Policy, Legal, and Regulatory Evaluation of the Feasibility of a National Pipeline Infrastructure for the Transport and Storage of Carbon Dioxide.
Investorhub. 2012. Available at http://investorshub.advfn.com/boards/read_msg.aspx?message_id=72260578
Lee, D.S.W., 2011. FutureGen “Clean Coal” Project Still has Hurdles to Clear. McDonough Voice.com April 6, 2011.
Lydersen, K. 2012. With no sources of CO2, Midwest pipeline project in limbo. Midwest Energy News, April 26, 2012.
Marston Law. 2012. http://www.marstonlaw.com/index_files/CO2pipeline_regulation.htm accessed on 5/16/2012
McGee, D. 2009. Tech, Dominion Propose Carbon-Capture Project. Richmond Times Dispatch, August 26, 2009.
MIT. 2007. The Future of Coal: Options for a Carbon Constrained World.
NETL. 2008. Plains CO2 Reduction Partnership, Williston Basin Demonstration Test Fact Sheet. Accessed at http://www.netl.doe.gov/publications/proceedings/08/rcsp/factsheets/20PCOR_Williston%20Basin%20Demo%20Test_PhIII_and_EOR_Demo.pdf Oil and Gas Journal. 2010. Exxon Mobil Finishes Shute Creek Carbon Capture Expansion.
Pew Charitable Trust. 2008. The Role of CO2 Enhanced Oil Recovery in Ohio’s Economy and Energy Future. Draft June 25, 2012
Radevsky, R., and D. Scott. 2004. Pipeline Insurance: Technical Aspects of Underwriting and Claims. Presented at the Conference on Terrain and Geohazard Challenges Facing Onshore Oil and Gas.
Rubin, E.S., M.B. Berkenpas, and S.T. McCoy. 2008. Technical Documentation: The Economics of CO2 Transport by Pipeline Storage in Saline Aquifers and Oil Reserves. Carnegie Mellon University.
Seevam, P., J.M. Race, and M.J. Downie. 2007. Carbon Dioxide Pipelines for Sequestration in the UK: an Engineering Gap Analysis. Journal of Pipeline Engineering 2007, 3rd quarter. pp. 133-146.
TEC. 2012. Taylorville Energy Center UIC Permit Application.
Tetra Tech. 2009. Assessment of Risk, Legal Issues, and Insurance for Geologic Carbon Sequestration in Pennsylvania. Pennsylvania Department of Conservation and Natural Resources.
Texas RRC. 2012. Texas RRC T-4 Permits viewed at: https://rrcsearch3.neubus.com/esd3rrc/index.php?_module_=esd&_action_=keysearch&profile=12 Draft June 25, 2012 Appendix A Standards Incorporated by Reference into Federal Pipeline Regulations
API Recommended Practice 1165, “Recommended Practice for Pipeline SCADA Displays,” Draft June 25, 2012
API Standard 2000 “Venting Atmospheric and Low-Pressure Storage Tanks”
API Recommended Practice 2003 “Protection Against Ignitions Arising out of Static,
Lightning, and Stray Currents” API Publication 2026 “Safe Access/Egress Involving Floating Roofs of Storage Tanks in Petroleum Service”
ASME/ANSI B16.9-20073 (February 2004) “Factory-Made Wrought Steel Buttwelding Fittings”
ASME/ANSI B31.4-20062 (October 2002) “Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids”
ASME/ANSI B31G-1991 (Reaffirmed; 2004) “Manual for Determining the Remaining Strength of Corroded Pipelines”
ASME/ANSI B31.8-20073 (February 2004) “Gas Transmission and Distribution Piping Systems”
MSS SP-75-2004 “Specification for High Test Wrought Butt Welding Fittings”
ASTM Designation: A53/A53M-07,04a (2004) “Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless”
ASTM Designation: A106/A106M-08,04b (2004) “Standard Specification for Seamless Carbon Steel Pipe for High-Temperature Service”
ASTM Designation: A 381-96 (Reapproved 20051), “Standard Specification for Metal-ArcWelded Steel Pipe for Use With High-Pressure Transmission Systems” Draft June 25, 2012
ASTM Designation: A 671-06,04 (2004) “Standard Specification for Electric-Fusion-Welded Steel Pipe for Atmospheric and Lower Temperatures”
ASTM Designation: A 672-0896 (Reapproved 2001) “Standard Specification for ElectricFusion-Welded Steel Pipe for High-Pressure Service at Moderate Temperatures”
NFPA 30(2003) “Flammable and Combustible Liquids Code”