Estimating the Effects of Pavement Condition on Vehicle Operating Costs NCHRP 720 2012
Original sourcePDF at sourceAttachment at source
Other documents for the same rulemaking
References: 58 extracted, 0 linked to papers
US Department of Energy (2006). Basic Research Needs for Clean and Efficient Combustion of 21st Century Transportation Fuels, science.energy.gov/~/media/bes/pdf/reports/files/ctf_rpt.pdf
VTRIS (2005). “Vehicle Travel Information System,” fhwapap07.fhwa. dot.gov/vtris/
Watanatada, T. (1987). Highway Design and Maintenance Standards Model (HDM) Model Description and User’s Manual—Release II,
Bhandari, A., and Tsunokawa, K. (1987). The Highway Design and Maintenance Standards Model, Volume 1: Description, The World
Bank, John Hopkins University Press. Winfrey, R. (1969). Economic Analysis for Highways, International Textbook Company, Scranton, PA.
Zaniewski, J. P., Butler, B. C., Cunningham, G., Elkins, G. E., Paggi, M. S., and Machemehl, R. (1982). “Vehicle Operating Costs, Fuel Consumption, and Pavement Type and Condition Factors,”
Then, to install the software, click on the “VOC Module Setup” link in the installation wizard (Figure 1). You will need to unzip the file to a preferred location on the hard drive. Once the file is unzipped, click on the “VOC Module” Excel spreadsheet to launch the program. You will also be able to see an example of project-level analysis data and the data collected as part of NCHRP Project 1-45. Figure 1. Installation wizard. Getting Started To make sure that the software is running, the security level for Excel must be set to “Medium” or “Low.” Figure 2a shows the path to follow to change the security level in Excel 2003. For Excel 2007, you should go to the Developer tab and select “Macro security.” Figure 2b shows how to change the security level in Excel 2007 and up. Home Screen Figure 3 shows the home screen of the VOC model. This is the starting screen when no project is currently open. It consists of two main sections: analysis levels (i.e., project or network levels) and unit system (i.e., US customary units or International System of units). You should choose an option from each section and click on the “Run” button, which will open the main spreadsheet. The VOC model calculates vehicle operating costs based on traffic and highway conditions. Three components are included in cost calculations (fuel consumption, tire wear, and repair and maintenance cost). The variables used to predict consumption rates of each VOC component include:
VOC = VMT × ∑ ( Rate × Price )i i =1 (a) For Microsoft Excel 2003 (b) For Microsoft Excel 2007 and up Figure 2. Set up of the security level. Figure 3. Home screen. where: