U.S. Department of State. 2014. Final Supplemental Environmental Impact Statement for the Keystone XL Project. United States Department of State Bureau of Oceans and International Environmental and Scientific Affairs.
Original sourcePDF at sourceAttachment at source
Other documents for the same rulemaking
References
Council, et al., to the Department of State on the Supplemental Environmental Impact Statement for the TransCanada Keystone XL Pipeline, Submitted July 30, 2012.
NEB. See National Energy Board. North Dakota Petroleum Council. 2010. UET Announces Start of Unit Trail Railing of Bakken Crude Oil from Mountrail County, ND to St. James, LA. Industry News. Website: http://www.ndoil.org/?id=25&ncid=4&nid=135. Accessed February 14, 2013. NuStar Energy L.P. 2010. NuStar Unloads First Bakken Shipment At La. Terminal. Downstream Today. Website: http://www.downstreamtoday.com/(X(1)S(aica202gdwd0on45kwhs53rk))/news/article.as px?a_id=22284&AspxAutoDetectCookieSupport=1. Accessed February 14, 2013.
Oil Sands Developers Group. 2013. Oil Sands Project List 2013—Updated July 2013. Website: http://www.oilsandsdevelopers.ca/index.php/library/. Accessed: July 2013.
OPEC. See Organization of the Petroleum Exporting Countries. Organization of the Petroleum Exporting Countries (OPEC). 2012. World Oil Outlook. P. 174.
OSDG. See Oil Sands Developers Group. Parraga, Marianna. 2013. PDVSA’s oil exports to Citgo decline, U.S. firms buy more –EIA. http://www.reuters.com/article/2013/11/25/oil-venezuela-us-idUSL2N0J721420131125.
Pembina Institute. 2013. The Climate Implications of the Proposed Keystone XL Oilsands Pipeline. Published January 17, 2013.
Pemex. 2013. Petroleum Statistics. June. Website: http://www.ri.pemex.com/index.cfm? action=content§ionID=21&catID=12177. 1.4-146 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 1 Introduction
Penty, Rebecca. 2012. Irving Refinery Said to Get 90,000 Barrels a Day by Rail. Business Week. Website: http://www.businessweek.com/news/2012-12-26/irving-refinery-said-to-get-90000-barrels-a-day-by-rail. Accessed January 29, 2013. ____________. 2013. Irving Oil Boosting Crude by Rail Capacity with Alberta Loading. Bloomberg News. November 29, 2013.
Persily, Larry. 2013. Trans Mountain Expands Oil Pipeline Project to B.C. Coast. Alaska Natural Gas Transportation Projects, Office of the Federal Coordinator. Website: http://www.arcticgas.gov/2013/trans-mountain-expands-oil-pipeline-project-bc-coast. Accessed January 14, 2013. Peters and Co. Limited. 2013. Crude Oil Rail Activity in Western Canada: Rapidly Increasing Exports Provides Some Near-Term Relief for Producers. January 2013. Petroleum Human Resources Council of Canada. 2013. Website: http://www.petrohrsc.ca/.
Platts. 2013. New Crudes, New Markets. March. Website: http://www.platts.com/IM.Platts. Content/InsightAnalysis/IndustrySolutionPapers/NewCrudesNewMarkets.pdf. Accessed: April 2013.
PLG Consulting. 2013. Crude by Rail Report. November 22. Poten and Partners. 2013. US Gulf Crude Oil Export—2015 Outlook (ICF). January 2013.
Rail Energy Transportation Advisory Committee. 2013. Rail Fleet Update. September 13. Website: http://www.stb.dot.gov/stb/docs/RETAC/2013/Sept/RETAC%20Railcars%20-%20Presentation%209%2019%2013%20Final.pdf. Accessed December 2013.
RBC Capital Markets. 2013. Energy Insights: Keystone XL—Weighing the Outcomes. February 11, 2013.
Reuters. 2013. Update 1—Enbridge, Partner to Convert Gas Pipeline to Ease Crude Glut. Website: http://www.reuters.com/article/2013/02/15/enbridge-pipelineidUSL4N0BF50620130215. Accessed February 15, 2013. Rodgers Oil and Gas Consulting. 2012. The Economics of Alberta’s Oil Sands. September 1.
Shiah, Helin. 2013, December 13. Personal Communication. Statistics Canada. 2013. Government Canada Statistics. http://www.statcan.gc.ca/start-debut-eng.html. Accessed September 2013. Website:
Suncor Energy. 2013. Third Quarter 2013 Report to shareholders for the period ended September 30, 2013. Website: http://www.suncor.com/pdf/Suncor_Q3_Report_2013_en.PDF. Accessed October 2013.
Surface Transportation Board. 2013. Freight Commodity Statistics. Website: http://www.stb.dot.gov/econdata.nsf/FCStatistics?OpenView&Start=1&Count=300&Exp and=1.1#1.1. Accessed October 22, 2013.
TD Economics. 2012. Pipeline Expansion is a National Priority. Special Report. December 17, 2012. 1.4-147 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 1 Introduction
Titterton, Paul. 2013. Crude Oil Tank Car Update. GATX Presentation. Website: http://mwrailshippers.com/mars_pdfs/2013_titterton_presentation.pdf. Accessed: September 2013.
Torq Transloading. 2012. Resource and Contract Requirements Necessary to Make Rail a Fully Integrated Part of Crude Takeaway Infrastructure. Presentation at the Crude Oil Markets, Rail & Pipeline Takeaway Summit. Calgary, AB. October 24 & 25, 2012. TransCanada. 2012. TransCanada Set to Re-Apply for Keystone XL Permit Proceeding with Gulf Coast Project. Website: http://www.transcanada.com/5966.html. Accessed November 2, 2012
Vanderklippe, Nathan. 2013. Nexen Closer to Moving Crude Oil to West Coast by Train. The Globe and Mail. Website: http://www.theglobeandmail.com/globe-investor/nexen-closerto-moving-crude-oil-to-west-coast-by-train/article7981477/. Accessed February 4, 2013. 1.4-148 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 1 Introduction
Walton, Rod. 2010. Rail Bringing Crude Oil to Stroud Unloading Site. Tulsa World. Website: http://www.tulsaworld.com/business/article.aspx?subjectid=49&articleid=20100105_49_ E4_Aptoem697692. Accessed February 14, 2013.
Watkins, Victoria. 2013, December 10. PIRA Energy Group. Personal Communication. Additional references are included in Appendix C, Supplemental Information to Market Analysis. 1.4-149 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 1 Introduction -Page Intentionally Left Blank- 1.4-150 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 1 Introduction
AGENCY PARTICIPATION 1.5.1 Federal Lead Agency—U.S. Department of State As noted in Section 1.3.2, Department of State Purpose and Need, the U.S. Department of State (the Department) is responsible for issuance of Presidential Permits for certain cross-border facilities. In addition, the Department is the lead agency for the environmental review consistent with the National Environmental Policy Act (NEPA), the National Historic Preservation Act of 1986 (NHPA) Section 106 consultation process, and the Endangered Species Act (ESA) Section 7 consultation process for the proposed Project. As the lead agency, the Department directed the preparation of the Final Supplemental Environmental Impact Statement (EIS) for the proposed Project consistent with NEPA, directed the Section 106 tribal consultation process consistent with the NHPA (16 United States Code [USC] § 470 et seq.), and initiated both informal and formal consultation with the U.S. Fish and Wildlife Service (USFWS) under Section 7 of the
Lexington MA. ____________. 2011. Keystone XL Assessment – No Expansion Review. Prepared for DOE and
Project, the Department is continuing throughout the Supplemental EIS process to engage in consultation on the Supplemental EIS, the proposed Project generally, and on cultural resources consistent with Section 106 of the NHPA with identified consulting parties, including federal agencies, state agencies, State Historic Preservation Offices (SHPOs), the Advisory Council on Historic Preservation, and interested federally recognized Indian tribes (70 Federal Register 71194) in the vicinity of the proposed Project. Starting in September 2012, the Department notified Indian tribes of its intent to amend the Programmatic Agreement to reflect changes to the proposed Project route since 2011 and comments received from consulting parties. Tribal meetings were held in October 2012 in Montana, South Dakota, and Nebraska, and May 2013 in South Dakota. Discussion of the consultation efforts and a complete list, to date, are included in Section 3.11.4.3, Tribal Consultation, and the amended Programmatic Agreement (see
SHPO Consultation The Department initiated consultation with the SHPOs on February 2, 2009. Consultation to date has included in-person meetings in Lincoln, Nebraska; Helena, Montana; and Pierre, South Dakota; as well as on-going communication via conference calls and email. The SHPOs have provided extensive feedback to the Department throughout this process. Additional meetings were held with the Montana SHPO to address mitigation measures for potential adverse effects to historic properties in Montana. 1.6-1 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 1 Introduction -Page Intentionally Left Blank- 1.6-2 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 1 Introduction
Intermap, iPC, METI, NRCAN, Esri Japan, METI, Esri China (Hong Kong), Esri (Thailand), TomTom, 2013, Bing Maps. TransCanada Keystone Pipeline, LP. 2012. Keystone Cushing Extension information provided via shapefile. Received November 16, 2012. Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 2 Description of the Proposed Project and Alternatives -Page Intentionally Left Blank Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 2 Description of the Proposed Project and Alternatives
Montana, South Dakota, and Nebraska, as follows: 1 Montana–approximately 285 miles South Dakota–approximately 316 miles Nebraska–approximately 274 miles Certain ancillary facilities (e.g., pump stations, access roads, and mainline valves [MLVs]) would be needed to support pipeline operations. Table 2.1-1 outlines these ancillary facilities by state and by type. In addition, other facilities are needed to support pipeline construction, including access roads, pipe yards, railroad sidings, and construction camps. A description of this is included in Sections 2.1.5, Ancillary Facilities, and 2.1.6, Access Roads. Table 2.1-1 Ancillary Facilities Supporting Operations by State State Montana South Dakota Nebraska Kansas Ancillary Facilities 6 Pump Stations 21 permanent access roads 25 IMLVsa 7 Pump Stations 18 permanent access roads 15 IMLVs 5 Pump Stations [TBD] permanent access roadsb 15 IMLVs 2 Pump Stations Source: exp Energy Services, Inc. 2012a.
Intermap, iPC, METI, NRCAN, Esri Japan, METI, Esri China (Hong Kong), Esri (Thailand), TomTom, 2013, Bing Maps. exp Energy Services, Inc. 2012a. TransCanada Keystone XL Pipeline Project Supplemental Environmental Report for the Nebraska Reroute. Document Number KXL-TAL-1005002. Tallahassee, FL. September 5, 2012. ___________. 2012b. TransCanada Keystone XL Pipeline Project Environmental Report. Document Number KXL-TAL-1005-002. Tallahassee, FL. September 7, 2012.
McSweeney, T., B.N. Leis, S. Mawalkar, M.C. Harley, K.R. Rine, and D.M. Sanzone. 2013. Risk Analysis of the Proposed Keystone XL Pipeline Route DRAFT. Battelle Memorial
Institute, June 2013. NDEQ. See Nebraska Department of Environmental Quality. Nebraska Department of Environmental Quality. 2013. NDEQ-Identified Sand Hills Region:
NDEQ Identifies Sandhills Regions to be Avoided in Alternative Pipeline Route. Website: http://www.deq.state.ne.us/Press.nsf/pages/PR122911. Accessed May 30, 2013. National Transportation Safety Board (NTSB). 2012. Enbridge Incorporated. Hazardous Liquid Pipeline Ruptured and Release. Marshall, Michigan, July 25, 2010. Accident Report.
NTSB. See National Transportation Safety Board. TransCanada Keystone Pipeline LP (TC). 2012. Application to the Department of State for a Presidential Permit. May 4, 2012.
Transportation Research Board. 2013. Special Report 311: Effects of Diluted Bitumen on Crude Oil Transmission Pipelines. Washington D.C.: National Academies Press. Website: http://www.nap.edu/openbook.php?record_id=18381&page=R1. Accessed December 2013. 2.1-96 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 2 Description of the Proposed Project and Alternatives
USEPA. 1991. Technical Guidance – Stage II Vapor Recovery Systems for Control of Vehicle Refueling Emissions at Gasoline Dispensing Facilities. Volume I: Chapters. Office of Air Quality Planning and Standards. EPA-450/3-91-022a. Research Triangle Park, NC: U.S. Environmental Protection Agency. November 1991. U.S. Geological Survey. 2012 National Hydrography Dataset. Website: ftp://nhdftp.usgs.gov/ DataSets/Staged/States/FileGDB/HighResolution/. Accessed September 17, 2012. 2.1-97 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 2 Description of the Proposed Project and Alternatives -Page Intentionally Left Blank- 2.1-98 Final Supplemental Environmental Impact Statement Keystone XL Project 2.2.1 Chapter 2 Description of the Proposed Project and Alternatives
Bismarck Tribune. 2012. Railroad beefs up to handle crude oil shipments. September 04. Website: http://bismarcktribune.com/news/state-and-regional/railroad-beefs-up-tohandle-crude-oil-shipments/article_a07cef42-f6db-11e1-a50c-001a4bcf887a.html. Accessed November 2, 2012.
Campbell, Robert. 2012. Did Spearhead signal a Brent-WTI bottom?: Campbell. Reuters. September 27, 2012. Website: http://www.reuters.com/article/2012/09/27/columncampbell-idUSL1E8KR4DQ20120927. Accessed July 16, 2013. Canadian Association of Petroleum Producers. 2012. Crude Oil Forecast, Markets & Pipelines.
Calgary, AB. Website: http://www.capp.ca/getdoc.aspx?DocId=209546&DT=NTV. Accessed November 15, 2012.
Canadian Environmental Assessment Agency. 2013. Enbridge Northern Gateway Project Joint Review Panel. Website: http://gatewaypanel.review-examen.gc.ca/clfnsi/nwsrls/2013/nwsrls03-eng.html. Accessed August 30, 2013. Canadian Pacific Railway System (CPRS). 2012. Canadian Pacific expands its oil by rail operation to Lloydminster, Saskatchewan. Website: http://www.cpr.ca/en/news-andmedia/news/Pages/oil-by-rail.aspx. February 2. Accessed November 15, 2012.
CBC. 2013. Oil brought by rail, truck to Burnaby refinery. July 16. Website: http://www.cbc.ca/news/canada/british-columbia/story/2013/07/15/bc-chevronburnaby-oil-refinery.html. Accessed: October 31, 2013.
Clark, Aaron. 2012. Enbridge Spearhead, Ozark Oil Lines Oversubscribed in July. Bloomberg. June 27. Website: http://www.bloomberg.com/news/2012-06-27/enbridge-spearheadozark-oil-lines-oversubscribed-in-july-1-.html. Accessed December 2, 2013. Council on Environmental Quality (CEQ). 1981. Memorandum to Agencies (as amended), Forty Most Asked Questions Concerning CEQ’s National Environmental Policy Act
EIA. See Energy Information Agency. Enbridge Northern Gateway Project Joint Review Panel. 2013. Joint Review Panel recommends approving the Enbridge Northern Gateway Project. Website: http://gatewaypanel.reviewexamen.gc.ca/clf-nsi/nwsrls/2013/nwsrls05-eng.html. Accessed December 20, 2013. Enbridge Pipelines (FSP) LLC. 2012a. Enbridge Upsizes Capacity of Gulf Coast Access Projects. eBRIDGE, Vol. 76. March 27, 2012. Website: http://ebridge.enbridge.com/ eBridge/ volume76/article1.php. Accessed December 2, 2013. 2.2-75 Final Supplemental Environmental Impact Statement Keystone XL Project Chapter 2 Description of the Proposed Project and Alternatives ___________. 2012b. Energy Matters - First Quarter Interim Report to Shareholders for the three months ended March 31, 2012. Website: http://www.enbridge.com/InvestorRelations/ FinancialInformation/~/media/www/Site%20Documents/Investor%20Relations/2012/201 2_ENB_Q1_Combined_Financials.ashx. Accessed August 30, 2013. ___________. 2012c. Enterprise and Enbridge to Proceed With 450,000 Barrel Per Day Expansion of Seaway Crude Oil Pipeline. March 26. Website: http://www.enbridge.com/ MediaCentre/News.aspx?yearTab=en2012&id=1589619. Accessed November 15, 2012. ___________. 2012d. Mainline Expansions Enbridge U.S. Website: http://www.enbridgeus.com/ Delivering-Energy/Growth-Projects/Mainline-Expansions/. Accessed December 2, 2013. Energy Information Agency (EIA). 2010a. Independent Statistics and Analysis, Refinery Yield,
PADD III. Website: http://tonto.eia.doe.gov/dnav/pet/pet_pnp_pct_dc_r30_pct_a.htm. Accessed July 16, 2013. ___________. 2010b. Independent Statistics and Analysis, Sales of Distillate Fuel By End Use, Gulf Coast (PADD III). Website: http://tonto.eia.doe.gov/dnav/pet/pet_cons_821dst_dcu_R30_a.htm. Accessed December 2, 2013. ___________. 2012. Annual Energy Outlook 2012 with Projections to 2035. DOE/EIA-0383 (2012). ___________. 2013c. Annual Energy Outlook – 2013 Early Release. Website: http://www.eia.gov/forecasts/aeo/er/pdf/0383er(2013).pdf. Accessed January 21, 2013. EnSys. See EnSys Energy and Systems, Inc. EnSys Energy and Systems, Inc. (EnSys). 2010. Keystone XL Assessment Final Report. 1775 Massachusetts Avenue, Lexington MA. Prepared for the U.S. Department of Energy. 118 pp. December 23. ___________. 2011. Keystone XL Assessment-No Expansion Update. Final Report. Prepared for the U.S. Department of Energy and U.S. Department of State. August 12.
Intermap, iPC, METI, NRCAN, Esri Japan, METI, Esri China (Hong Kong), Esri (Thailand), TomTom, 2013, Bing Maps. exp Energy Services. 2012. Environmental Report. Prepared for TransCanada Keystone Pipeline,
Financial Post. 2012a. Eastern oil pipeline proposal technically, economically feasible: TransCanada. October 31. Website: http://business.financialpost.com/2012/10/31/easternoil-pipeline-proposal-technically-economically-feasible-transcanada/. Accessed November 2, 2012. ___________. 2012b. Oil producers eye Arctic backup plan as pipelines face uncertain future. October 31. Website: http://business.financialpost.com/2012/10/31/oil-producers-eyearctic-backup-plan-as-pipelines-face-uncertain-future/. Accessed November 2, 2012.
Google Maps. 2013. Bruderheim rail terminal (aerial map). Retrieved from Google Earth Pro on October 7, 2013. Created July 17, 2013 and west half updated August 27, 2013.
Government Accountability Office. 2010. Pipeline Security, Report to Congressional Committees.
Illinois Commerce Commission. 2012. Application For Certification And Other Relief. Website: http://www.icc.illinois.gov/downloads/public/edocket/320606.pdf. May 15. Accessed November 15, 2012.
INGAA. See Interstate Natural Gas Association of America. International Energy Agency (IEA). 2010. World Energy Outlook 2010. Website: http://www. worldenergyoutlook.org/publications/weo-2010/. Nov. 9. Accessed November 15, 2012. ____________. 2011. World Energy Outlook. SBN: 978-92-64-12413-4. ___________. 2012. World Energy Outlook 2012. SBN: 978-92-64-1804-0. Interstate Natural Gas Association of America (INGAA). 1999. Interstate Natural Gas Association of America (INGAA), 1999. Temporary Right-of-Way Width Requirements for Pipeline Construction. Gulf Interstate Engineering. Houston, TX.