Policy Replication

OSHA. February 14, 1992. Final Regulatory Impact and Regulatory Flexibility Analysis of the Final Standard for Process Safety Management of Highly Hazardous Chemicals (§1910.119, SubPart H)

Regulatory impact analysis2016-03-14 · EPA · regulatory_flexibility_analysis · EPA-HQ-OEM-2015-0725-0092
RIN 2050-AG95, RIN 2050-AG82, RIN 2050-AG91 · Docket EPA-HQ-OEM-2015-0725

Other documents for the same rulemaking

2016-03-14 Regulatory impact analysisEPA. February 23, 2016. Interagency Communications regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Original 1996 Regulatory Impact Analysis
2016-03-14 Regulatory impact analysisEPA. February 8, 2016. EO 12866 Interagency Review Communications on Risk Management Modernization RIN 2050-AG82 regarding Notice of Proposed Rulemaking and Regulatory Impact Analysis (redline version), Interagency Comments and Two Public Comments on the RMP Request for Information from NASTTPO and OK MERC. Office of Land and Emergency Management, USPEA, Washington, DC
2016-03-14 Regulatory impact analysisEPA. February 24, 2016. Interagency Communications regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Comment on Notice of Proposed Rulemaking and Regulatory Impact Analysis. Office of Land and Emergency Management, USEPA
2016-03-14 Regulatory impact analysisEPA. February 23, 2016. Interagency Communications Rgarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Notice of Proposed Rulemaking Comments (redline) and Regulatory Impact Analysis Comments (redline)
2016-03-14 Regulatory impact analysisEPA. January 11, 2016. Interagency Communications regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8,_Regulatory Impact Analysis, comment from SBA. Office of Land and Emergency Management, USEPA
2016-03-14 Regulatory impact analysisEPA. February 24, 2016. Regulatory Impact Analysis for Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7)
2016-03-14 Regulatory impact analysisEPA. February 24, 2016. EO 12866 Interagency Review Communications on Risk Management Modernization RIN 2050-AG82 regarding Notice of Proposed Rulemaking and Regulatory Impact Analysis (clean versions)
2016-03-14 Regulatory impact analysisEPA. February 19, 2016. Interagency Communications regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Regulatory Impact Analysis (redline version)
2016-03-14 Regulatory impact analysisEPA. February 19, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Revised Regulatory Impact Analysis (redline). Office of Land and Emergency Management, USEPA
2016-03-14 Regulatory impact analysisEPA. February 24, 2016. Documentation of Changes Made During OMB Review Under E.O. 12866: Risk Management Program Proposed Rule- Regulatory Impact Analysis - Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7)
2016-03-14 Regulatory impact analysisEPA. February 24, 2016. EO 12866 Interagency Review Communications on Risk Management Modernization RIN 2050-AG82 regarding Notice of Proposed Rulemaking and Regulatory Impact Analysis (compare versions) (redline)
2016-03-14 Regulatory impact analysisEPA. February 22, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG82 Regulatory Impact Analysis (redline version)
2016-03-14 Regulatory impact analysisEPA. February 24, 2016. Interagency Communications regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG82_Regulatory Impact Analysis section 5.7. Office of Land and Emergency Management, USEPA.
2016-03-14 Regulatory impact analysisEPA. February 12, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Regulatory Impact Analysis New Section in Chapter 5. Office of Land and Emergency Management, USEPA
2016-03-14 Regulatory impact analysisMason, Steve. September 01, 2015. Email from Steve Mason, EPA Region 6 to Jim Belke, Office of Emergency Management, USEPA, regarding accounting for state/local government costs in RIA
2016-03-14 Regulatory impact analysisEPA. June 1996. Economic Analysis in Support of Final Rule on Risk Management Program Regulations for Chemical Accident Release Prevention, As Required by Section 112(r) of the Clean Air Act
2016-03-14 Regulatory impact analysisEPA. June 1996. Economic Analysis in Support of Final Rule on Risk Management Program Regulations for Chemical Accident Release Prevention. Provided to Small Entity Representatives for EPA RMP Small Business Advocacy Review Panel
2016-03-14 Regulatory impact analysisEPA. December 17, 2015. Document submitted to OMB on 12/22/15 to initiate E.O. 12866 review: Risk Management Program Proposed Rule, Regulatory Impact Analysis - Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7)
2016-03-14 Docket documentEPA. December 17, 2010 (updated May 2014). Guidelines for Preparing Economic Analyses
2016-03-14 Docket documentEPA. February 10, 2016. Interagency Communications regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Comment on Notice of Proposed Rulemaking and OSHA feasibility. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. January 5, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Briefing for OMB and Interagency Reviewers. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. January 13, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Interagency Comments on Notice of Proposed Rulemaking. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. January 14, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Interagency Comments on Notice of Proposed Rulemaking. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 11, 2016. Interagency Communications regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Comment on Notice of Proposed Rulemaking and OSHA feasibility Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 18, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernizatio RIN 2050-AG8, Comments from SBA on Notice of Proposed Rulemaking. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. January 29, 2016. Interagency Meeting Agenda and Meeting Summary Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG82_Notice of Proposed Rulemaking
2016-03-14 Docket documentEPA. February 22, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Comments on Notice of Proposed Rulemaking and EPA Response. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 17, 2016. Interagency Communications regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, comment on Notice of Proposed Rulemaking. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 16, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Notice of Proposed Rulemaking Comments (redline) and Interagency Comments. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 22, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Response to SBA Comment on Notice of Proposed Rulemaking. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 18, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Notice of Proposed Rulemaking Comments (redline) and Interagency Comments. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 9, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Comment on Notice of Proposed Rulemaking and OSHA Feasibility. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 23, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, Conference Call Request. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. February 22, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG8, SBA Comment on Notice of Proposed Rulemaking. Office of Land and Emergency Management, USEPA
2016-03-14 Docket documentEPA. December 17, 2015. Document submitted to OMB on 12/22/15 to Initiate E.O. 12866 review: Risk Management Program Proposed Rule FR notice - Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7)
2016-03-14 Docket documentEPA. February 24, 2016. Documentation of Changes Made During OMB Review Under E.O. 12866: Risk Management Program Proposed Rule- Federal Register notice - Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7)
2016-03-14 Federal RegisterAccidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act
2016-03-22 Docket documentEPA. February 22, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG82, Comments on RMP NPRM and EPA Response. Office of Land and Emergency Management, USEPA
2016-03-22 Docket documentEPA. February 19, 2016. Interagency Communications Regarding EO 12866 Interagency Review Risk Management Modernization RIN 2050-AG82, Minor Edits on RMP NPRM. Office of Land and Emergency Management, USEPA
2017-01-13 Regulatory impact analysisEPA. December 19, 2016. Interagency Review Communications Between OMB and EPA - Email from Gerain Cogliano of EPA to OMB Regarding Redline Versions of Final RMP Rule and RIA for EO 12866 Interagency Review. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Regulatory impact analysisEPA. December 16, 2016. Regulatory Impact Analysis: Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7). Office of Emergency Management, US Environmental Protection Agency, Washington, DC
2017-01-13 Regulatory impact analysisEPA. December 19, 2016. Documentation of Changes Made During OMB Review Under E.O. 12866: Risk Management Program Final Rule- Regulatory Impact Analysis - Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7). Office of Emergency Management, Office of Land and Emergency Management, US EPA, Washington, DC
2017-01-13 Regulatory impact analysisEPA. October 13, 2016. Document submitted to OMB on 10/13/16 to initiate E.O. 12866 review: Risk Management Program Final Rule, Regulatory Impact Analysis - Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7). Office of Emergency Management, Office of Solid Waste and Emergency Response, US EPA, Washington, DC
2017-01-13 Docket documentEPA. December 16, 2016. Interagency Review Communications Between OMB and EPA - Email from Bill Noggle of EPA to OMB with Attached Response to Follow Up Comments for EO 12866 Interagency Review on Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. December 14, 2016. Interagency Review Communications Between OMB and EPA - Email from Danielle Jones of OMB to EPA With Attached EPA Responses to EO 12866 Interagency Review Follow Up Comments on Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. December 15, 2016. Interagency Review Communications Between OMB and EPA - Email from Danielle Jones of OMB to EPA with Attached Follow Up Comments for EO 12866 Interagency Review on Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. November 17, 2016. Interagency Review Communications Between OMB and EPA - Email from Danielle Jones of OMB to EPA with EO 12866 Interagency Review Comments on Final RMP Rule Regarding Water and Wastewater Sectors. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. December 20, 2016. Interagency Review Communications Between OMB and EPA - Email from Danielle Jones of OMB to EPA Concluding Review of EO 12866 Interagency Review on Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. November 7, 2016. Interagency Review Communications Between OMB and EPA - Email from Danielle Jones of OMB to EPA with Attached EO 12866 Interagency Review Comments on Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. November 22, 2016. Interagency Review Communications Between OMB and EPA - Email from Danielle Jones of OMB to EPA with EO 12866 Interagency Review Additional Comments on Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. November 22, 2016. Interagency Review Communications Between OMB and EPA - Email Invitation from Bill Noggle of EPA to OMB with Attached Response to Comments on EO 12866 Interagency Review of Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. December 7, 2016. Interagency Review Communications Between OMB and EPA - Email from Danielle Jones of OMB to EPA with Attached EO 12866 Interagency Review Comments on Final RMP Rule. Office of Land and Emergency Management, USPEA, Washington, DC
2017-01-13 Docket documentEPA. December 20, 2016. Interagency Review Communications Between OMB and EPA - Email from Gerain Cogliano of EPA to OMB Regarding Uploading Documents to ROCIS for EO 12866 Interagency Review on Final RMP Rule. Office of Land and Emergency Management, USPEA, Washington, DC
2017-01-13 Docket documentEPA. December 12, 2016. Interagency Review Communications Between OMB and EPA - Email Invitation from Gerain Cogliano of EPA for Meeting of Discussion of Comments on EO 12866 Interagency Review of Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. December 14, 2016. Interagency Review Communications Between OMB and EPA - Email Invitation from Gerain Cogliano of EPA for Meeting of Discussion of Comments on EO 12866 Interagency Review of Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. October 19, 2016. Interagency Review Communications Between OMB and EPA - Email Invitation from Gerain Cogliano of EPA for Briefing for EO 12866 Interagency Review of Final RMP Rule with Attached Briefing Materials. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. October 14, 2016. Interagency Review Communications Between OMB and EPA - Email from Danielle Jones of OMB Requesting Briefing for EO 12866 Interagency Review of Final RMP Rule. Office of Land and Emergency Management, USEPA, Washington, DC
2017-01-13 Docket documentEPA. October 13, 2016. Document submitted to OMB on October 13, 2016 to initiate E.O. 12866 review: Risk Management Program Final Rule FR Notice - Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7). Office of Emergency Management, Office of Solid Waste and Emergency Response, US EPA, Washington, DC
2017-01-13 Docket documentDOE. May 9, 2011. Cost Estimating Guide, DOE G 413.3-21. US Department of Energy, Washington, DC
2017-01-13 Docket documentUSEPA. October 19, 2016. EO 12866 Interagency Briefing on Modernization of the Accidental Release Prevention Regulation under Clean Air Act (RIN 2050-AG82) with list of attendees. USEPA, Office of Emergency Management, Washington, DC

References: 28 extracted, 3 linked to papers

Page 1Download these results: CSV · JSON
Kearney/Centaur. proDosed OSHA Rule for the Process Hazards Manaaement of Hiahlv Hazardous Chemicals: An Industrv Profile, Cost Assessment and Benefits Analvs is, Final ReDort. Prepared for OSHA under Contract No. J-9-F-8-0032, January 1990. [Ex. 51
research reportNot linked to a paper · VII References, ref. 1
Charles River Associates Incorporated. Industrv Prof ile and Cost Assessment of a Proposed OSHA Standard Coverina Process Hazard M anaaement in the Chemical and Petroleum Industries, Final Reportt Prepared for OSHA under Contract No. S-9-F-50059, February 1989. [Ex. 101
research reportNot linked to a paper · VII References, ref. 2
Department of Labor, Bureau of Labor Statistics. Occupational Injuries and Illnesses in the United States bv Industrv. 1987 Bulletin 2328, May 1989.
government reportNot linked to a paper · VII References, ref. 3
Harms-Ringdahl, L. "Safety Analysis in Design Evaluation of Case Study. I) Accident Analysis and Prevention, Vol. 19, No. 4, 1987, pp. 305-317.
journal articleSafety analysis in design—Evaluation of a case study (1987) · VII References, ref. 6
Viscusi, W. Kip. "Procedures for Valuing Job Risk Reduction Benefits: A Report Prepared for the OSHA Office of Regulatory Analysis," Washington, D.C., June 1983.
research reportNot linked to a paper · VII References, ref. 9
Bureau of Labor Statistics, "Employer Costs For Employee Compensation -March 1990," U.S. Dept. of Labor News, USDL: 90-317, June 19, 1990.
government reportNot linked to a paper · VII References, ref. 21
Bureau of Labor Statistics, "White-Collar Pay: Private Goods-Producing Industries, March 1990," U.S. Dept. of Labor, Bulletin 2374, October 1990.
government reportNot linked to a paper · VII References, ref. 22
Rasmussen, B. "Occurence and Impact of Unwanted Chemical Reactions. Journal of Loss Prevention in the Process Industries, Vol 1. (April 1988), pp. 92-95.
journal articleOccurrence and impact of unwanted chemical reactions (1988) · VII References, ref. 24
Dyer, Alexander P., "A Commitment to Excellence in Safety," CGA Safety Seminar Speech, January 27, 1987, 74th Annual Compressed Gas Association Meeting.
otherNot linked to a paper · VII References, ref. 25
"Powerplant Safety: From the Top Down," Electrical World. Vol. 200, No. 12 (December 1986), pp. 62-64.
journal articleNot linked to a paper · VII References, ref. 26
Catanzaro, G.J. and Richardson, M.R., "Introduction to the VPP," Job Safety and Health Quarterly, Vol. 1, No. 1, (Fall 1989), pp. 16-18.
journal articleNot linked to a paper · VII References, ref. 27
Lutness, J. "Managing Safety in the Industrial Environment," Best's Safety Directory 1987, pp. 46-50.
book chapterNot linked to a paper · VII References, ref. 28
"Profiting from Disaster," Forbes, November 27, 1989, pp. 203-206.
newsNot linked to a paper · VII References, ref. 31
Kearney/Centaur Division, Proposed OSHA Rule for the Process Hazards Management of Highly Hazardous Chemicals: An Industry Profile, Cost Assessment and Benefits Analysis [Ex. 5]
research reportNot linked to a paper · Executive Summary / Affected Industries and Current Compliance
Charles River Associates [Ex. 10]
research reportNot linked to a paper · Benefits / Baseline Profile of Hazardous Chemical Accidents
Organization Resources Counselors, Inc. "Recommendations for Process Hazards Management of Substances with Catastrophic Potential." December 1988 [Ex. 2-10]
research reportNot linked to a paper · IV. Technological Feasibility
American Petroleum Institute. "Management of Process Hazards." API Recommended Practice 750, First Edition. January 1990. [Ex. 2-11]
research reportNot linked to a paper · IV. Technological Feasibility
Chemical Manufacturers Association. "Evaluating Process Safety in the Chemical Industry," A Manager's Guide to Quantitative Risk Assessment. June 1989. [Ex. 11-26]
research reportNot linked to a paper · IV. Technological Feasibility
Center for Chemical Process Safety of the American Institute of Chemical Engineers. "Guidelines for Technical Management of Chemical Process Safety." 1989. [Ex. 11-18]
research reportNot linked to a paper · IV. Technological Feasibility
Rasmussen, B., "Occurrence and Impact of Unwanted Chemical Reactions," Journal of Loss Prevention in the Process Industries [24].
journal articleOccurrence and impact of unwanted chemical reactions (1988) · V. Effectiveness of the Process Safety Management Standard
Dyer, Alexander P., "A Commitment to Excellence in Safety," CGA Safety Seminar Speech 1/27/87, 74th Annual Meeting (reprinted in Compressions) [25].
otherNot linked to a paper · V. Effectiveness of the Process Safety Management Standard
"Powerplant Safety: From the Top Down," Electrical World [26].
journal articleNot linked to a paper · V. Effectiveness of the Process Safety Management Standard
Catanzaro, G.J. and Richardson, M.R., "Managing Safety in the Industrial Environment," Best's Safety Directory [27].
otherNot linked to a paper · V. Effectiveness of the Process Safety Management Standard
Lutness, J.O., "Introduction to the Job Safety & Health Quarterly [28]."
journal articleNot linked to a paper · V. Effectiveness of the Process Safety Management Standard
Bureau of Labor Statistics Survey of Occupational Injuries and Illnesses for the years 1984-1988 [3]
datasetNot linked to a paper · V. Benefits / Baseline Catastrophic Events
Dun & Bradstreet [15, 29]
datasetNot linked to a paper · VI. Economic Impact
M&M Protection Consultants, "Large Property Damage Losses in the Hydrocarbon-Chemical Industries, A Thirty Year Review" [Ex. 11-6]
research reportNot linked to a paper · IV. Property Damage
Forbes magazine article [Ex. 11-30]
newsNot linked to a paper · IV. Lost Production