Policy Replication

Clean Water Act Hazardous Substance Facility Response Plans

Federal Register2024-03-28 · ENVIRONMENTAL PROTECTION AGENCY · Rule · 2024-05870
Final rule.

The U.S. Environmental Protection Agency (EPA or Agency) is finalizing facility response plan requirements for worst case discharges of Clean Water Act (CWA) hazardous substances for onshore non-transportation-related facilities that could reasonably be expected to cause substantial harm to the environment by discharging a CWA hazardous substance into or on the navigable waters, adjoining shorelines, or exclusive economic zone.

RIN 2050-AH17 · Docket EPA-HQ-OLEM-2021-0585

Other documents for the same rulemaking

2022-03-28 Regulatory impact analysisRegulatory Impact Analysis: Clean Water Act Hazardous Substance Worst Case Discharge Planning Regulations
2022-03-28 Regulatory impact analysis2019 Regulatory Impact Analysis, Clean Water Act Hazardous Substances Spill Prevention Final Action
2022-03-28 Regulatory impact analysis1994 Regulatory Impact Analysis of Revisions to the Oil Pollution Prevention Regulation (40 CFR 112) to Implement the Facility Response Planning Requirements of the Oil Pollution Act of 1990
2022-03-28 Regulatory impact analysis2016 Regulatory Impact Analysis, Accidental Release Prevention Requirements: Risk Management Programs Under the Clean Air Act, Section 112(r)(7)
2022-03-28 Regulatory impact analysisRegulatory Impact Analysis of Costs
2022-03-28 Regulatory impact analysisDocument showing Track Changes in Regulatory Impact Analysis: Clean Water Act Hazardous Substance Worst Case Discharge Planning Regulations during OMB Review
2022-03-28 Regulatory impact analysisIntroduction to Benefit-Cost Analysis
2022-03-28 Regulatory impact analysis2016 Guidance document on assessing Environmental Justice in Regulatory Analysis
2022-03-28 Regulatory impact analysis1996 Economic Analysis in Support of Final Rule on Risk Management Program Regulations for Chemical Accident Release Prevention, as Required by Section 112(r) of the Clean Air Act
2022-03-28 Federal RegisterClean Water Act Hazardous Substance Worst Case Discharge Planning Regulations
2022-03-28 Docket documentDocument showing Track Changes in Clean Water Act Hazardous Substance Worst Case Discharge Planning Regulations Notice of Proposed Rulemaking during OMB Review
2022-03-28 Docket documentCircular A-4
2022-05-16 Federal RegisterClean Water Act Hazardous Substance Worst Case Discharge Planning Regulations; Extension of Comment Period
2024-03-28 Regulatory impact analysisDocument Showing Track-Changes in Regulatory Impact Analysis: Clean Water Act Hazardous Substance Worst Case Discharge Planning Regulations
2024-03-28 Regulatory impact analysisRegulatory impact analysis of costs
2024-03-28 Regulatory impact analysisRegulatory Impact Analysis: Clean Water Act Hazardous Substance Worst Case Discharge Planning Regulations, for OMB Review
2024-03-28 Regulatory impact analysis7881 CWA Hazardous Substance Facility Response Plans FR Regulatory Impact Analysis 20230926 EO12866 Initiated
2024-03-28 Docket documentClean Water Act Hazardous Substance Facility Response Plan Regulations, ICR for OMB Review (OMB Control Number 2050-0228; EPA ICR No. 2710.02)
2024-03-28 Docket document7881 CWA Hazardous Substance Facility Response Plans FR ICR 20230926 EO12866 Initiated
2024-03-28 Docket document7881 CWA Hazardous Substance Facility Response Plans FR Preamble and Regulatory Text 20230927 EO12866 Initiated
2024-03-28 Docket documentDocument Showing Track-Changes in Final Preamble and Regulatory Text, Clean Water Act Hazardous Substance Facility Response Plans
2024-03-28 Docket documentFinal Preamble and Regulatory Text for OMB Review, Clean Water Act Hazardous Substance Facility Response Plans
2024-06-03 Regulatory impact analysisFinal Regulatory Impact Analysis: Clean Water Act Hazardous Substance Worst Case Discharge Planning Regulations
2026-03-05 Regulatory impact analysis7881.1 2050-AH38 CWA Haz Sub Delay Rule NPRM RIA Clean 20251222 EO 12866 Clearance
2026-03-05 Docket document7881.1 CWA HAZ Sub Delay Rule NPRM FRN 20260220 Redline
2026-10-13 Regulatory impact analysis7881.1 CWA Delay Final Rule RIA 9-11-2026 Redline
2026-10-13 Regulatory impact analysis7881.1 CWA Delay Final Rule RIA Final
2026-10-13 Docket document7881.1 CWA Delay Final Rule 20260615 Comment Response Final
2026-10-13 Docket document7881.1 CWA Delay Final Rule FRN 9-11-2026 Redline

References: 7 extracted, 1 linked to papers

Page 1Download these results: CSV · JSON
NOAA National Centers for Environmental Information (NCEI). (2023). U.S. Billion-Dollar Weather and Climate Disasters. https://www.ncei.noaa.gov/access/billions/, DOI: 10.25921/stkw-7w73.
This is especially true given trends in natural disasters in the US, with more than $1 trillion in damage from 2016-2022,\3\ illustrating that planning for severe weather events is critical as they become more common and intense and reflecting the long term challenges posed by climate change.\4\ Additionally, the requirements follow the statutory directives set forth in 33 U.S.C.
U.S. Global Change Research Program (USGCRP). (2017). Climate Science Special Report: Fourth National Climate Assessment, Volume I, Chapter 7: Precipitation Change in the United States. https://science2017.globalchange.gov/chapter/7/.
research reportNot linked to a paper · fn 4 · cited link
Burton, K., Maas, A., and Lee, K. (2022). A Case Study in Contamination: Persistent Home Value Losses Associated with the Elk River Spill. https://jareonline.org/articles/a-case-study-in-contamination-persistent-home-value-losses-associated-with-the-elk-river-spill/
journal articleNot linked to a paper · fn 5 · cited link
Occurrence of Releases with the Potential to Impact Sources of Drinking Water (EPA 817-R-21-001)
research reportNot linked to a paper · II.B / III.B.2.b (Zones of Concern)
ASTM E3241-20 Standard Guide for Coordination and Cooperation between Facilities, Local Emergency Planning Committees, and Emergency Responders
otherNot linked to a paper · v. Coordination Activities
Menominee Michigan Warehouse Fire, https://response.epa.gov/site/site_profile.aspx?site_id=15823
web pageNot linked to a paper · fn 9, Disposal Plans · cited link
Regulatory Impact Analysis, Clean Water Act Hazardous Substance Facility Response Plans
research reportNot linked to a paper · Discharge detection systems discussion (preamble)