AK Steel, Middletown, OH (AKS-Middletown-OH) No. 16 BOF Vessel Venturi Scrubber SS&M Plan, May 7, 2008
Other documents for the same rulemaking
References: 7 extracted, 0 linked to papers
AKWEP 4.4.3.1 E Tools for the Job Task None Records None Job Procedures Notify pump tender by radio to check venturi pumps. If venturi pumps are OK, pump tender is to check hot well level and then go to quencher pit to restart quencher pump. After starting the quencher pumps, pump tender will notify melting pulpit. Furnace operator will monitor HMI Scrubbing Water Screen to confirm that the automatic valve is maintaining quencher tank level. Possible Quality Problem (to line item 2.1) If tank level is not controlling, electronic repair must inspect automatic valve and repair. Another problem could be the bubbler. Electronic repair must blow down the bubbler. If furnace operator still does not have enough flow, pump tender will switch quencher pumps and maintenance will inspect automatic valves above quencher pumps to confirm valve operation. Form No. AKQSOPE; Rev. 1; 1/05 •This document is only valid for 24 hours from 3:03 •m,November 8, 2011. AKSteei # 13-MELT-E8 E Steelmaking Department/Section Page 2 of 3 Version Level Revision Date 08/16/2002 *CON F DENTIAL'' rroperty (ri AK Sted O. No Dnplicare Electronic repair and maintenance will notify furnace operator that the vessel is safe to operate after they determine that the scrubbing water system is controlling. Call the Main Gate on ext. 3694 so that Environmental Affairs can be notified as per
AKWEP 4.4.3.1 E. 6. In the event of an environmental emergency, the department shall provide corrective and preventative action plans once the incident has been mitigated. Form No. AKQSOPE; Rev. 1; 1 /05 This document is only valid for 24 hours from 3:03 m November 8 2011. Steelmaking At AK Steel Department/Section Page 3 of 3 Version Level Revision Date # 13-MELT-E8 E 05116/2002
AKWEP 4.4.3.1E Tools for the Job Task None Records Melting Tum Delay Sheet MWBOF #046 Scrubber Differential Pressure and Water Flow Rate Corrective Action Plan MWBOF #112 Vessel Primary Emissions Control System Malfunction Procedure Reporting Form MWBOF #113 Job Procedures A report must be logged by telephone to Security - Main Gate - Phone 3694 whenever there is an occurrence such as: Pouring hot metal at emergency pouring station. Lancing vessel skulls with oxygen pipes. Failure of main hot metal pouring station baghouse system. Failure of main skimmer baghouse system. Vessel off-gas system control problems if significant. Outside desulf baghouse system failures. Whenever a heat is dumped on ground. Failure of the secondary emissions baghouse system. Form No. AKQSOPE; Rev. I; 1/05 This document is onl valid for 24 hours from 3:03 m November 8 2011.
AC AK Steel # 13-0172-04E Steelmaking. / Melting Department/Section Page 2 of 3 Version Level Revision Date 05/04/2009 *CONFIDENTIAL* Property Of AK Steel - Du Not Duplicate The report must detail: When was the occurrence? What caused occurrence? How long will this condition continue? Any other details pertaining to occurrence. In the event that an exceedance (i.e. a value below the operating limit) of an oxygen blow hour average differential pressure and/or water flow rate across the venturi scrubber occurs form MWBOF #112 (Scrubber Differential Pressure and Water Flow Rate Corrective Action Plan) will be filled out completely. Note that the investigation into the cause of the exceedance must begin within 1 hour of the event. This will be the responsibility of the Melter and BOF maintenance supervisor on duty. When finished it is to be faxed to Environmental Affairs at 3079. In the event that a vessel scrubber (primary emissions control systern) fails while the vessel is processing a heat forrn MWBOF #113 (Vessel Prirnary Emissions Control System Malfunction Procedure Reporting Form) is to be filled out by the melter and faxed to Environmental Affairs at 3079. (Note that Environmental Affairs must be notified according to AKWEP 4.4.3.1 E.)
AC AK Steel # 13-EMER-50-E Page 3 of 3 02/13/2008 Version Level Revision Date
RESPONSIBILITIES Department managers are responsible for communicating this information to their personnel and reporting such events to the Main Gate/Security at 3694. Security will then be responsible for contacting Middletown Works Environmental Affairs. Approved by: Works General Manager Environmental Affairs Form No. AKWEP; Rev. 0; 1101 This document is only valid for 24 hours from 2:54 m November 8 2011. Origination Date: 04/04/2002
LOCATION: Middletown SUBJECT: Environmental Notification For Spills,Upsets & Malfunctions Revision Date: 10/16/2008 AXS1eal Page 2 of 3 Examples of Air Pollution Control Equipment Malfunctions 1. All outages of scrubbers, baghouses, hood collection systems, etc.