Policy Replication

Document submitted to conclude E.O. 12866 and 13563 review - CPP Final FRN

Docket document2015-10-23 · EPA · review_record · EPA-HQ-OAR-2013-0602-36875
RIN 2060-AR33, RIN 2060-AR88 · Docket EPA-HQ-OAR-2013-0602

Other documents for the same rulemaking

2014-06-18 Federal RegisterCarbon Pollution Emission Guidelines for Existing Stationary Sources: Electric Utility Generating Units
2014-06-18 Regulatory impact analysisRIA for the Final Revisions to the National Ambient Air Quality Standards for Particulate Matter; 2012 [EPA-452/R-12-005]
2014-06-18 Regulatory impact analysisRegulatory Impact Analysis for the Proposed Carbon Pollution Guidelines for Existing Power Plants and Emission Standards for Modified and Reconstructed Power Plants - June 2014 [EPA -542/R-14-002]
2014-06-18 Regulatory impact analysis2008 Ozone NAAQS RIA Benefits Chapter
2014-06-18 Regulatory impact analysisEmail to OMB - Revisions to Chapter 9 of RIA (May 23, 2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding organization of meetings on the EGU GHG Existing Source NPRM for a legal discussion and RIA briefing (2060-AR33) (4/10/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding a meeting on the EGU GHG Existing Source NPRM RIA results compared to EIA and RFF projections (2060-AR33) (4/24/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Comments on the EGU GHG Existing Source NPRM RIA (single document) (2060-AR33) (5/28/2014)
2014-06-18 Regulatory impact analysisSummary of the Updated Regulatory Impact Analysis (RIA) for the Reconsideration of the 2008 Ozone National Ambient Air Quality Standard (NAAQS); Section 3: Re-analysis of the Benefits of Attaining Alternative Ozone Standards to Incorporate Current Methods
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Comments on the EGU GHG Existing Source NPRM RIA chapters (2060-AR33) (5/15/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding a meeting on the EGU GHG Existing Source NPRM RIA (2060-AR33) (5/21/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding Interagency request for EGU GHG Existing Source NPRM RIA IPM Output (2060-AR33) (4/17/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Comments on the EGU GHG Existing Source NPRM RIA, Chapter 4 (2060-AR33) (5/26/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Request to combine the EGU GHG Existing Source NPRM RIA chapters into one single document (2060-AR33) (5/16/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Comments on the EGU GHG Existing Source NPRM RIA and Alternative Renewable Energy (RE) Approach TSD (2060-AR33) (5/30/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Comments on the EGU GHG Existing Source NPRM RIA, Chapter 8 (2060-AR33) (5/30/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Comments on the EGU GHG Existing Source NPRM RIA (2060-AR33) (5/24/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding the EGU GHG Existing Source NPRM RIA (2060-AR33) (4/21/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Comments on the EGU GHG Existing Source NPRM Preamble and RIA (2060-AR33) (5/2/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Comments on the EGU GHG Existing Source NPRM RIA (Clean) (2060-AR33) (5/30/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding EGU GHG Existing Source NPRM Building Blocks 1 and 2 Memo and RIA (2060-AR33) (5/21/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Comments on the EGU GHG Existing Source NPRM RIA (2060-AR33) (5/30/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding a meeting on the EGU GHG Existing Source NPRM RIA (2060-AR33) (5/22/2014)
2014-06-18 Regulatory impact analysisRegulatory Impact Analysis for the Proposed Carbon Pollution Guidelines for Existing Power Plants and Emission Standards for Modified and Reconstructed Power Plants [EPA -542/R-14-002]
2014-06-18 Regulatory impact analysisFinal Ozone NAAQS Regulatory Impact Analysis; Chapter 6: Incremental Benefits of Attaining Alternative Ozone Standards Relative to the Current 8-hour Standard (0.08 ppm)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Comments on the EGU GHG Existing Source NPRM RIA (Redline and Clean) (2060-AR33) (5/30/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Request for EGU GHG Existing Source NPRM RIA briefing and the 111(b) regulatory text TSD (2060-AR33) (4/18/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Comments on the EGU GHG Existing Source NPRM RIA (2060-AR33) (5/28/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Comments on the EGU GHG Existing Source NPRM RIA, Executive Summary and Chapters 3 and 6 (2060-AR33) (5/29/2014)
2014-06-18 Regulatory impact analysisRegulatory Impact Analysis for the Final Revisions to the National Ambient Air Quality Standards for Particulate Matter [EPA-452/R-12-005]
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Comments on the EGU GHG Existing Source NPRM RIA (2060-AR33) (5/25/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Comments on the EGU GHG Existing Source NPRM RIA, Chapter 4 (2060-AR33) (5/28/2014)
2014-06-18 Regulatory impact analysisPart of E.O. 12866 and 13563 Review: Interagency Comments on the EGU GHG Existing Source NPRM RIA (2060-AR33) (5/14/2014)
2014-06-18 Regulatory impact analysisMemo: Emission Reductions, Costs, Benefits and Economic Impacts Associated with Buliding Blocks 1 and 2.
2014-06-18 Regulatory impact analysisCalifornia Standard Practice Manual: Economic Analysis of Demand-Side Programs and Projects
2014-06-18 Regulatory impact analysisBenefit-Cost Analysis in Environmental, Health, and Safety Regulation: A Statement of Principles
2014-06-18 Regulatory impact analysisLBNL Energy and Economic Impacts of U.S. Federal Energy and Water Conservation Standards Adopted From 1987 Through 2012
2014-06-18 Regulatory impact analysisMemorandum: Emission Reductions, Costs, Benefits and Economic Impacts Associated with Building Blocks 1 & 2
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with the Large Public Power Council (2060-AR33) (4/17/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Transmittal of white paper from Pennsylvania Department of Environmental Protection under EO 12866 (2060-AR33) (4/10/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with the National Rural Electric Cooperative Association (2060-AR33) (4/17/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with the National Climate Coalition (2060-AR33) (4/29/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with the Canadian Electricity Association (2060-AR33) (5/2/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with RePower South (2060-AR33) (4/29/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with the Natural Resources Defense Council (2060-AR33) (5/2/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with the Association of Home Appliance Manufacturers (2060-AR33) (5/2/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with Sierra Club (2060-AR33) (5/2/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with Alevo (2060-AR33) (5/8/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Transmittal of white paper from Coalition for Innovative Climate Solutions under EO 12866 (2060-AR33) (4/9/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with the Coalition for Innovative Climate Solutions (2060-AR33) (4/11/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Meeting materials from E.O. 12866 meeting with Waste Management (2060-AR33) (5/2/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Request for multiple TSDs on the EGU GHG Existing Source NPRM (2060-AR33) (5/29/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Request for Alternative Renewable Energy (RE) Approach TSD on the EGU GHG Existing Source NPRM (2060-AR33) (5/29/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding Interagency Comments on the EGU GHG Existing Source NPRM GHG Abatement TSD, Chapter 5 (2060-AR33) (5/30/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding scheduling a meeting to discuss Interagency Comments on the EGU GHG Existing Source NPRM (2060-AR33) (5/30/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding organization of a meeting on the EGU GHG Existing Source NPRM with DOJ (2060-AR33) (4/17/2014)
2014-06-18 Docket documentDocument submitted to initiate E.O. 12866 and 13563 review - EGU GHG Existing Source NPRM
2014-06-18 Docket documentDocumentation of Changes Made During OMB Review Under E.O. 12866 and 13563 through May 28, 2014 - EGU GHG Existing Source NPRM
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: EPA Response to Interagency Request for EGU GHG Existing Source NPRM Survey of Existing State Policies and Programs (2060-AR33) (4/4/2014)
2014-06-18 Docket documentPart of E.O. 12866 and 13563 Review: Interagency Discussion regarding status of briefing materials for the overview briefing on the EGU GHG Existing Source NPRM (2060-AR33) (4/7/2014)

References: 29 extracted, 0 linked to papers

Page 1Download these results: CSV · JSON
Initially, states had broad authority to regulate public utilities, but gradually federal regulation increased. In 1920, Congress passed the Federal Water Power Act, creating the Federal Power Commission (FPC) and providing for the licensing of hydroelectric facilities on U.S. government lands and
research reportNot linked to a paper · refsec
Systems, IEEE Press, at 2-4 (2d ed. 2010). 66 Casazza, J. and Delea, F., Understanding Electric Power
research reportNot linked to a paper · refsec
NGA also gave the FPC the jurisdiction to “grant certificates allowing construction and operation of facilities used in interstate gas transmission and authorizing the provision of services.”76 In 1977, the FPC became FERC after Congress passed the Department of Energy Organization Act. 16 U.S.C. § 824(b)(1). 16 U.S.C. § 824d. 74 16 U.S.C. § 824e. 75 Energy Information Administration, Natural Gas Act of 1938, available at http://www.eia.gov/oil_gas/natural_gas/analysis_publications/ngm ajorleg/ngact1938.html. 76 Energy Information Administration, Natural Gas Act of 1938, available at http://www.eia.gov/oil_gas/natural_gas/analysis_publications/ngm ajorleg/ngact1938.html. *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 149 of 1615 By the 1930s, regulated electric utilities that provided the major components of the electrical system - generation, transmission, and distribution - were common.77 These regulated monopolies are referred to as vertically-integrated utilities. As utilities built larger and larger electric generation plants, the cost per unit to generate electricity decreased.78
journal articleNot linked to a paper · refsec · cited link
Systems, IEEE Press, at 159 (2d ed. 2010). In an amicus brief to the Supreme Court, a group of electrical engineers, economists, and physicists specializing in electricity explained, “Energy is transmitted, not electrons. Energy transmission is accomplished through the propagation of an electromagnetic wave. The electrons merely oscillate in place, but the energy – the electromagnetic wave – moves at the speed of light. The energized electrons making the lightbulb in a house glow are not the same electrons that were induced to oscillate in the *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 155 of 1615 Diverse resources generate electricity that is transmitted and distributed through a complex system of interconnected components to industrial, business, and residential consumers. Unlike other industries where sources make operational decisions independently, the utility power sector is unique in that electricity system resources operate in a complex, interconnected grid system that is physically interconnected and operated on an integrated basis across large regions.
journal articleNot linked to a paper · refsec
Systems, IEEE Press, at 159 (2d ed. 2010). 103 Casazza, J. and Delea, F., Understanding Electric Power
research reportNot linked to a paper · refsec
Systems, IEEE Press, at 160 (2d ed. 2010). *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 157 of 1615 similarly recognized the interconnected nature of the electricity grid.104
journal articleNot linked to a paper · refsec
Today, federal, state, and local entities regulate electricity providers.105 Overlaid on the physical electricity network is a regulatory network that has developed over the last century or more. This regulatory network “plays a vital role in the functioning of all other networks, sometimes providing specific rules for functioning while at other times providing restraints within which their operation must be conducted.”106 Federal Power Comm’n v. Florida Power & Light Co., 404 U.S. 453, at 460 (1972) (quoting a Federal Power Commission hearing examiner, "`If a housewife in Atlanta on the Georgia system turns on a light, every generator on Florida’s system almost instantly is caused to produce some quantity of additional electric energy which serves to maintain the balance in the interconnected system between generation and load.’”) (citation omitted). See also New York v. FERC, 535 U.S. 1, at 7 (2002) (stating that “any electricity that enters the grid immediately becomes a part of a vast pool of energy that is constantly moving in interstate commerce.”) (citation omitted). In Federal Power Comm’n v. Southern California Edison Co., 376 U.S. 205 (1964), the Supreme Court found that a sale for resale of electricity from Southern California Edison to the City of
research reportNot linked to a paper · refsec
Colton, which took place solely in California, was under Federal Power Commission jurisdiction because some of the electricity that Southern California Edison marketed came from out of state. The Supreme Court stated that, “`federal jurisdiction was to follow the flow of electric energy, an engineering and scientific, rather than a legalistic or governmental, test.’” Id. at 210 (quoting Connecticut Light & Power Co. v. Federal Power Commission, 324 U.S. 515, 529 (1945) (emphasis omitted)).
research reportNot linked to a paper · refsec
Systems, IEEE Press, at 214 (2d ed. 2010).
research reportNot linked to a paper · refsec
Systems, IEEE Press, at 213 (2d ed. 2010). *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 158 of 1615 This unique regulatory network results in an electricity grid that is both physically interconnected and connected through a network of regulation on the local, state, and federal levels. This regulation seeks to reconcile the fact that electricity is a public good with the fact that facilities providing that electricity are privately owned.107 While this regulation began on the state and local levels, federal regulation of the electricity system increased over time. With the passage of the EPAct 1992 and the EPAct 2005, the federal government’s role in electricity regulation greatly increased.108 “The role of the regulator now includes support for the development of open and fair wholesale electric markets, ensuring equal access to the transmission system and more hands-on oversight and control of the planning and operating rules for the industry.”109 2. Electric system dispatch System operators typically dispatch the electric system through a process known as Security Constrained Economic
journal articleNot linked to a paper · refsec
Systems, IEEE Press, at 213 (2d ed. 2010).
research reportNot linked to a paper · refsec
Systems, IEEE Press, at 214 (2d ed. 2010). *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 159 of 1615 Dispatch.110 Security Constrained Economic Dispatch has two components – economic generation of generation facilities and ensuring that the electric system remains reliable.111 Electricity demand varies across geography and time in response to numerous conditions, such that electric generators are constantly responding to changes in the most reliable and costeffective manner possible. The cost of operating electric generation varies based on a number of factors, such as fuel and generator efficiency. The decision to dispatch any particular electric generator depends upon the relative operating cost, or marginal cost, of generating electricity to meet the last increment of electric demand. Fuel is one common variable cost – especially for fossil-fueled generators. Coal plants will often have considerable variable costs associated with running pollution Economic Dispatch: Concepts, Practices and Issues, FERC Staff Presentation to the Joint Board for the Study of Economic
journal articleNot linked to a paper · refsec
Ontario, Canada experienced the largest power blackout to date, impacting 30 million people.114 In response to the 1965 blackout and a Federal Power Commission recommendation,115 industry developed the National Electric Reliability Council (NERC) and nine reliability councils. The organization later became known as the North American Electric Reliability Council to recognize Canada’s participation.116 The North American Electric Reliability Council became the North American Electric Reliability Corporation in 2007.117 North American Electric Reliability Corporation, History of
research reportNot linked to a paper · refsec
NERC, at 1 (2013), available at http://www.nerc.com/AboutNERC/Documents/History%20AUG13.pdf. 114 Federal Energy Regulatory Commission, Energy Primer: A Handbook of Energy Market Basics, at 39 (2012), available at http://www.ferc.gov/market-oversight/guide/energy-primer.pdf. 115 The Federal Power Commission, a precursor to FERC, recommended “the formation of a council on power coordination made up of representatives from each of the nation’s regional coordinating organizations, to exchange and disseminate information and to review, discuss and assist in resolving interregional coordination matters.” North American Electric Reliability Corporation, History of NERC, at 1 (2013), available at http://www.nerc.com/AboutNERC/Documents/History%20AUG13.pdf. 116 North American Electric Reliability Corporation, History of
journal articleNot linked to a paper · refsec · cited link
NERC, at 2 (2013), available at http://www.nerc.com/AboutNERC/Documents/History%20AUG13.pdf. 117 North American Electric Reliability Corporation, History of
research reportNot linked to a paper · refsec · cited link
NERC, at 4 (2013), available at http://www.nerc.com/AboutNERC/Documents/History%20AUG13.pdf. *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 162 of 1615 In August 2003, North America experienced its worst blackout to date creating an outage in the Midwest, Northeast, and Ontario, Canada.118 This blackout was massive in scale impacting an area with an estimated 50 million people and 61,800 megawatts of electric load.119 The U.S. and Canada formed a joint task force to investigate the causes of the blackout and made recommendations to avoid similar outages in the future. One of the task force’s major recommendations was that the U.S. Congress should pass legislation making electric reliability standards mandatory and enforceable.120 Congress responded to this recommendation in EPAct 2005, adding a new section 215 to the Federal Power Act making reliability standards mandatory and enforceable and authorizing the creation of a new Electric Reliability Organization (ERO). North American Electric Reliability Corporation, History of
journal articleNot linked to a paper · refsec · cited link
NERC, at 3 (2013), available at http://www.nerc.com/AboutNERC/Documents/History%20AUG13.pdf. 119 U.S.-Canada Power System Outage Task Force, Final Report on the August 14, 2003 Blackout in the United States and Canada: Causes and Recommendations, at 1 (Apr. 2004), available at http://www.ferc.gov/industries/electric/indusact/reliability/blackout/ch1-3.pdf. The outage impacted areas within Ohio, Michigan, Pennsylvania, New York, Vermont,
research reportNot linked to a paper · refsec · cited link
Massachusetts, Connecticut, New Jersey, and the Canadian province of Ontario. Id. 120 U.S.-Canada Power System Outage Task Force, Final Report on the August 14, 2003 Blackout in the United States and Canada: Causes and Recommendations, at 2 (Apr. 2004), available at http://www.ferc.gov/industries/electric/indusact/reliability/blackout/ch1-3.pdf. *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 163 of 1615 Under this new system, FERC certifies an entity as the ERO. The
journal articleNot linked to a paper · refsec · cited link
ERO develops reliability standards, which are subject to FERC review and approval. Once FERC approves reliability standards the ERO may enforce those standards or FERC can do so independently.121 In 2006, the Federal Energy Regulatory Commission (FERC) certified NERC as the ERO.122 “NERC develops and enforces Reliability Standards; monitors the Bulk-Power System; assesses adequacy annually via a 10-year forecast and winter and summer forecasts; audits owners, operators and users for preparedness; and educates and trains industry personnel.”123 The United States, Canada, and part of Mexico are divided up into eight reliability regional entities.124 These regional entities include Florida Reliability Coordinating Council (FRCC), Midwest Reliability Organization (MRO), Northeast Power Coordinating Council (NPCC), Reliability First Corporation Mandatory Reliability Standards for the Bulk-Power System, Order No. 693, 118 FERC ¶ 61,218, at P 3 (2007) (citing 16
research reportNot linked to a paper · refsec
U.S.C. 824o(e)(3)). 122 Rules Concerning Certification of the Electric Reliability Organization; and Procedures for the Establishment, Approval, and Enforcement of Electric Reliability Standards, Order No. 672, 114 FERC ¶ 61,104 (2006). 123 North American Electric Reliability Corporation, Frequently Asked Questions, at 2 (Aug. 2013), available at http://www.nerc.com/AboutNERC/Documents/NERC%20FAQs%20AUG13.pdf. 124 Federal Energy Regulatory Commission, Energy Primer: A Handbook of Energy Market Basics, at 49-50 (2012), available at http://www.ferc.gov/market-oversight/guide/energy-primer.pdf. *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 164 of 1615 (RFC), SERC Reliability Corporation (SERC), Southwest Power
journal articleNot linked to a paper · refsec · cited link
Sustainable Energy, 2015 Factbook: Sustainable Energy in
research reportNot linked to a paper · refsec
RPS or similar laws.146 Use of RE continues to grow rapidly in the U.S. In 2013, electricity generated from renewable technologies, including conventional hydropower, represented 13 percent of total U.S. electricity, up from 9 percent in 2005.147 In 2013, U.S. non-
research reportNot linked to a paper · refsec
Systems, IEEE Press, at 220-221 (2d ed. 2010). 144 Cogeneration facilities utilize a single source of fuel to produce both electricity and another form of energy such as heat or steam. Casazza, J. and Delea, F., Understanding Electric Power Systems, IEEE Press, at 220-221 (2d ed. 2010). 145 Casazza, J. and Delea, F., Understanding Electric Power
research reportNot linked to a paper · refsec
Systems, IEEE Press, at 220-221 (2d ed. 2010). 146 U.S. Energy Information Administration (EIA), Annual Energy Outlook 2014 with Projections to 2040, at LR-5 (2014), available at http://www.eia.gov/forecasts/aeo/pdf/0383(2014).pdf (last visited May 26, 2015). 147 Energy Information Administration, Annual Energy Outlook 2015 with Projections to 2040, at ES-6 (2014) and Energy Information
research reportNot linked to a paper · refsec · cited link
Administration, Monthly Energy Review, May 2015, Table 7.2b, *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 172 of 1615 hydro RE capacity for the total electric power industry exceeded 80,000 MW, reflecting a fivefold increase in just 15 years.148 In particular, there has been substantial growth in the wind and photovoltaic (PV) markets in the past decade. Since 2009, U.S. wind generation has tripled and solar generation has grown twenty-fold.149 The global market for RE is projected to grow to $460 billion per year by 2030.150 RE growth is further encouraged by the significant amount of existing natural resources that can support RE production in the United States.151 In the Energy Information Administration’s Annual Energy Outlook 2015, RE generation grows substantially from 2013 to 2040 in the reference case and all alternative cases.152 In the reference available at http://www.eia.gov/totalenergy/data/monthly/pdf/sec7_6.pdf. 148 Non-hydro RE capacity for the total electric power industry was more than 16,000 megawatts (MW) in 1998. Energy Information
journal articleNot linked to a paper · refsec · cited link
EPA set state emission “budgets” for upwind states based in part on emissions reductions achievable by EGUs through application of cost-effective controls. Each rule also adopted a phased rely on one or more alternative methods of compliance in the manner and time authorized under [Title IV].” 42 U.S.C. § 7651g(b). 167 42 U.S.C. § 7410(a)(2)(D)(i)(I). 168 EPA v. EME Homer City Generation, L.P., 134 S. Ct. 1584, 1600–01 (2014) (citing 42 U.S.C. § 7410(c)). 169 63 FR 57356 (Oct. 27, 1998). 170 70 FR 25162 (May 12, 2005). 171 76 FR 48208 (Aug. 8, 2011). *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 178 of 1615 approach to reducing emissions with both interim and final goals. a. NOx SIP Call. In 1998, the EPA promulgated the NOx SIP Call, which required 23 upwind states to reduce emissions of NOx that would impact downwind areas with ozone problems. The EPA determined emission reduction requirements based on reductions achievable through “highly cost-effective” controls—i.e., controls that would cost on average no more than $2,000 per ton of emissions reduced.172 The EPA determined that a uniform emission rate on large EGUs coupled with a cap-and-trade program was one such set of highly cost-effective controls.173
journal articleNot linked to a paper · refsec
The D.C. Circuit upheld the NOx SIP Call in most significant respects, including its use of costs to apportion emission reduction responsibilities.174 b. Clean Air Interstate Rule (CAIR). In 2005, the EPA promulgated CAIR, which required 28 upwind states to reduce emissions of NOx and SO2 that would impact downwind areas with 63 FR at 57377–78. 63 FR at 57377–78. In addition to EGUs, the NOx SIP Call also set budgets based on highly cost-effective emission reductions from certain other large sources. Id. 174 Michigan v. EPA, 213 F.3d 663 (D.C. Cir. 2000). *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 179 of 1615 projected nonattainment and maintenance problems for ozone and PM2.5. The EPA determined emission reduction requirements based on “controls that are known to be highly cost effective for EGUs.”175 The EPA established cap-and-trade programs for sources of NOx and SO2 in states that chose to participate in the trading programs via their SIPs and for states ultimately subject to a
journal articleNot linked to a paper · refsec
CAA section 111(d), states would be required to submit plans to the EPA “detailing the controls that will be implemented to meet its specified budget for reductions from coal-fired Utility Units.”186 Of course, states were “not required to adopt and implement” the emission trading program, “but they [were] required to be in compliance with their statewide Hg emission budget.”187 4. Mercury Air Toxics Rule On February 16, 2012, the EPA issued the MATS rule (77 FR 9304) to reduce emissions of toxic air pollutants from new and existing coal- and oil-fired EGUs. The MATS rule will reduce emissions of heavy metals, including mercury, arsenic, chromium, and nickel; and acid gases, including hydrochloric acid and hydrofluoric acid. These toxic air pollutants, also known as hazardous air pollutants or air toxics, are known to cause, or suspected of causing, nervous system damage, cancer, and other serious health effects. The MATS rule will also reduce SO2 and fine particle pollution, which will reduce particle 70 FR 28606, at 28621. 70 FR 28606, at 28621. That said, states could “require reductions beyond those required by the [s]tate budget.” Id. at 28621. *** E.O. 12866 Review – Revised Version – Do Not Cite, Quote or Release During Review *** Page 183 of 1615 concentrations in the air and prevent thousands of premature deaths and tens of thousands of heart attacks, bronchitis cases
journal articleNot linked to a paper · refsec
http://journals.ametsoc.org/doi/pdf/10.1175/2008BAMS2370.1.
journal articleNot linked to a paper · doi · cited link