{"document":{"doc_id":11676,"source":"fr_rule","org":"DEPARTMENT OF LABOR; Occupational Safety and Health Administration","doc_type":"Rule","title":"Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment","date":"2014-04-11","url":"https://www.federalregister.gov/documents/2014/04/11/2013-29579/electric-power-generation-transmission-and-distribution-electrical-protective-equipment","source_native_id":"2013-29579","status":"fetched","abstract":"OSHA last issued rules for the construction of transmission and distribution installations in 1972. Those provisions are now out of date and inconsistent with the more recently promulgated general industry standard covering the operation and maintenance of electric power generation, transmission, and distribution lines and equipment. OSHA is revising the construction standard to make it more consistent with the general industry standard and is making some revisions to both the construction and general industry requirements. The final rules for general industry and construction include new or revised provisions on host employers and contractors, training, job briefings, fall protection, insulation and working position of employees working on or near live parts, minimum approach distances, protection from electric arcs, deenergizing transmission and distribution lines and equipment, protective grounding, operating mechanical equipment near overhead power lines, and working in manholes and vaults. The revised standards will ensure that employers, when appropriate, must meet consistent requirements for work performed under the construction and general industry standards. The final rule also revises the general industry and construction standards for electrical protective equipment. The existing construction standard for the design of electrical protective equipment, which applies only to electric power transmission and distribution work, adopts several national consensus standards by reference. The new standard for electrical protective equipment, which matches the corresponding general industry standard, applies to all construction work and replaces the incorporation of out-of-date consensus standards with a set of performance-oriented requirements that is consistent with the latest revisions of the relevant consensus standards. The final construction rule also includes new requirements for the safe use and care of electrical protective equipment to complement the equipment design provisions. Both the general industry and construction standards for electrical protective equipment will include new requirements for equipment made of materials other than rubber. OSHA is also revising the general industry standard for foot protection. This standard applies to employers performing work on electric power generation, transmission, and distribution installations, as well as employers in other industries. The final rule removes the requirement for employees to wear protective footwear as protection against electric shock.","action":"Final rule."},"dockets":["OSHA-S215-2006-0063"],"rins":["RIN 1218-AB67"],"related":[{"doc_id":10684,"source":"ria","org":"OSHA","doc_type":"economic_analysis","title":"Supporting Exhibit 7-3; PREPARATION OF AN ECONOMIC IMPACT STUDY FOR THE PROPOSED OSHA REGULATION COVERING ELECTRIC POWER GENERATION, TRANSMISSION, AND DISTRIBUTION. TASK ORDER NO. 1 CONTRACT NO. J-9-F-5-0057.","date":"1986-05-31"},{"doc_id":10668,"source":"ria","org":"OSHA","doc_type":"regulatory_analysis","title":"Supporting Exhibit 2; OFFICE OF REGULATORY ANALYSIS, OSHA","date":"1987-10-23"},{"doc_id":10662,"source":"ria","org":"OSHA","doc_type":"regulatory_flexibility_analysis","title":"Supporting Exhibit 32;  Regulatory Impact and Regulatory Flexibility Analysis of the Electrical Safety-Related Work Practices Standard for General Industry (29 CFR 1910, Subpart S)","date":"1990-06-12"},{"doc_id":10682,"source":"ria","org":"OSHA","doc_type":"economic_analysis","title":"Supporting Exhibit 2-4; A BRIEF SUMMARY OF OSHAS PRELIMINARY ESTIMATES OF THE ECONOMIC IMPACTS, COSTS, AND BENEFITS OF THE PROPOSED RULE AS A WHOLE. CONTRACT NO. J-9-F-9-0013. TASK ORDER NUMBER 29. OPTION YEAR 3.","date":"2003-02-14"},{"doc_id":10700,"source":"ria","org":"OSHA","doc_type":"economic_analysis","title":"Supporting Exhibit 3; FINAL REPORT. ANAYTICAL SUPPORT AND DATA GATHERING FOR A PRELIMINARY ECONOMIC ANALYSIS FOR A PROPOSED STANDARD FOR WORK ON ELEC POWER TRANSMISSION AND DISTRIBUTION LINES AND EQUIP (29 CFR 1910.269 AND 29 CFR 1926 - SUBPART V). CONTRACT NO. J-9-F-9-0013","date":"2003-02-14"},{"doc_id":10678,"source":"ria","org":"OSHA","doc_type":"regulatory_flexibility_analysis","title":"Supporting Exhibit 2-3; DRAFT COPY OF OSHAS PRELIMINARY INITIAL REGULATORY FLEXIBILITY ANALYSIS, WHICH INCLUDES THE AGENCYS ANALYSIS OF SOME ALTERNATIVES TO THE PROPOSED RULE.","date":"2003-04-07"},{"doc_id":10672,"source":"ria","org":"OSHA","doc_type":"economic_analysis","title":"Supporting Exhibit 7-1; REVISED FINAL REPORT - ANALYTICAL SUPPORT AND DATA GATHERING FRO A PRELIMINARY ECONOMIC ANALYSIS FOR PROPOSED STANDARDS FOR WORK ON ELECTRIC POWER GENERATION, TRANSMISSION, AND DISTRIBUTION LINES AND EQUIPMENT (29 CFR 1910.269 AND 29 CFR 1926-SUBPART V)","date":"2005-06-08"},{"doc_id":18249,"source":"fr_rule","org":"DEPARTMENT OF LABOR; Occupational Safety and Health Administration","doc_type":"Proposed Rule","title":"Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment","date":"2005-06-15"},{"doc_id":18098,"source":"fr_rule","org":"DEPARTMENT OF LABOR; Occupational Safety and Health Administration","doc_type":"Proposed Rule (administrative)","title":"Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Extension of Comment Period; Change in Date of Public Hearing","date":"2005-10-12"},{"doc_id":16405,"source":"fr_rule","org":"DEPARTMENT OF LABOR; Occupational Safety and Health Administration","doc_type":"Proposed Rule","title":"Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Limited Reopening of Record","date":"2008-10-22"},{"doc_id":15668,"source":"fr_rule","org":"DEPARTMENT OF LABOR; Occupational Safety and Health Administration","doc_type":"Proposed Rule","title":"Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Limited Reopening of Record; Notice of Informal Public Hearing","date":"2009-09-14"},{"doc_id":131216,"source":"docket_item","org":"OSHA","doc_type":"review_record","title":"Office of Management and Budget. 2003. Circular A-4","date":"2014-04-01"},{"doc_id":11287,"source":"fr_rule","org":"DEPARTMENT OF LABOR; Occupational Safety and Health Administration","doc_type":"Rule (administrative)","title":"Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Corrections","date":"2014-09-24"},{"doc_id":10390,"source":"fr_rule","org":"DEPARTMENT OF LABOR; Occupational Safety and Health Administration","doc_type":"Rule (administrative)","title":"Electrical Safety-Related Work Practices; Electric Power Generation, Transmission, and Distribution; Electrical Protective Equipment; Corrections","date":"2015-10-05"}],"references":[{"citation_id":64523,"raw_reference":"Hearon, B.F., Brinkley, J.W., \"Fall Arrest and Post-Fall Suspension: Literature Review and Directions for Further Research,\" AFAMRL-TR-84-021, April 1984.","cited_authors":"Hearon, B.F.; Brinkley, J.W.","cited_year":"1984","cited_title":"Fall Arrest and Post-Fall Suspension: Literature Review and Directions for Further Research","cited_venue":"AFAMRL-TR-84-021","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"fn 115","page":null,"context_sentence":"0088).\\115\\ That same study showed that subjects suspended in full body harnesses could tolerate suspension for approximately 20 to 30 minutes (id.). --------------------------------------------------------------------------- ---------------------------------------------------------------------------","paper_id":70754,"paper_title":"Fall Arrest and Post-Fall Suspension: Literature Review and Directions for Further Research.","paper_year":1984,"paper_doi":null},{"citation_id":64524,"raw_reference":"ASTM F887-04, Standard Specifications for Personal Climbing Equipment","cited_authors":"ASTM International","cited_year":"2004","cited_title":"Standard Specifications for Personal Climbing Equipment","cited_venue":"ASTM","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Paragraph (b)(2) discussion, Standard Specifications for Personal Climbing Equipment","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64525,"raw_reference":"IEEE Std 1307-2004, Standard for Fall Protection for Utility Work","cited_authors":"IEEE","cited_year":"2004","cited_title":"Standard for Fall Protection for Utility Work","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Section on fall protection starting height (Southern Company recommendation)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64526,"raw_reference":"IEEE Std 516-2003, IEEE Guide for Maintenance Methods on Energized Power Lines","cited_authors":"IEEE","cited_year":"2003","cited_title":"IEEE Guide for Maintenance Methods on Energized Power Lines","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Section 1926.957 live-line tools","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64527,"raw_reference":"ASTM F711-02 (2007), Standard Specification for Fiberglass-Reinforced Plastic (FRP) Rod and Tube Used in Live-Line Tools","cited_authors":"ASTM International","cited_year":"2007","cited_title":"Standard Specification for Fiberglass-Reinforced Plastic (FRP) Rod and Tube Used in Live-Line Tools","cited_venue":"ASTM","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Section 1926.957 live-line tools","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64528,"raw_reference":"ANSI A14.3-2002, American National Standard for Ladders—Fixed—Safety Requirements","cited_authors":"ANSI","cited_year":"2002","cited_title":"American National Standard for Ladders—Fixed—Safety Requirements","cited_venue":"ANSI","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Section 1926.955 fixed ladders","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64629,"raw_reference":"Worker Deaths by Electrocution: A Summary of NIOSH Surveillance and Investigative Findings, Publication No. 98-131","cited_authors":"NIOSH","cited_year":"1998","cited_title":"Worker Deaths by Electrocution: A Summary of NIOSH Surveillance and Investigative Findings","cited_venue":"NIOSH Publication No. 98-131","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Discussion of grounding and minimum resistance of employee (fn none; section on mechanical equipment, paragraph (d)(3)(iii))","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64630,"raw_reference":"Vaisman, R., Fonseca, J. R., Andrade, V. H. G., Almeida, M. A., Hattori, H. K., Melo, M. O. B. C., Teivelis, F., Fernandes, J. H. M., Silva, J. T. S., Dias, L. E. N., Esmeraldo, P. C. V., and Samico, R. A. M., \"Switching Impulse Strength of Compact Transmission Lines,\" IEEE Transactions on Power Delivery, Vol. 8, No. 3, July 1993 (Ex. 0555).","cited_authors":"Vaisman, R.; Fonseca, J. R.; Andrade, V. H. G.; Almeida, M. A.; Hattori, H. K.; Melo, M. O. B. C.; Teivelis, F.; Fernandes, J. H. M.; Silva, J. T. S.; Dias, L. E. N.; Esmeraldo, P. C. V.; Samico, R. A. M.","cited_year":"1993","cited_title":"Switching Impulse Strength of Compact Transmission Lines","cited_venue":"IEEE Transactions on Power Delivery, Vol. 8, No. 3","cited_doi":"10.1109/tpwrd.1993.5742755","cited_url":null,"ref_kind":"journal_article","section":"fn 184","page":null,"context_sentence":"0545.1, 0551.1.) American Electric Power argued against adopting minimum approach distances different from the minimum approach differences in OSHA's proposal, relying on calculations they made that were taken from a paper by Vaisman et al.\\184\\ (Ex.","paper_id":16053,"paper_title":"Switching impulse strength of compact transmission lines","paper_year":1993,"paper_doi":"10.1109/tpwrd.1993.5742755"},{"citation_id":64631,"raw_reference":"IEEE Std 516-2009","cited_authors":"IEEE","cited_year":"2009","cited_title":"IEEE Guide for Maintenance Methods on Energized Power Lines","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Minimum Approach Distances section","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64632,"raw_reference":"IEEE Paper 91 SM 312-9 PWRD \"Test Results of Grounding Un-insulated Aerial Lift Vehicles Near Energized Distribution Lines\"","cited_authors":null,"cited_year":"1991","cited_title":"Test Results of Grounding Un-insulated Aerial Lift Vehicles Near Energized Distribution Lines","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"journal_article","section":"Mechanical equipment, paragraph (d)(3)(iii) discussion","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64633,"raw_reference":"Assessment of the Benefits of the Proposed Standard on Electric Power Generation, Transmission, and Distribution; Coding Results and Analysis (Ex. 0081)","cited_authors":null,"cited_year":null,"cited_title":"Assessment of the Benefits of the Proposed Standard on Electric Power Generation, Transmission, and Distribution; Coding Results and Analysis","cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"fn 172","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64634,"raw_reference":"IEC Standard 61472","cited_authors":"International Electrotechnical Commission","cited_year":null,"cited_title":"IEC Standard 61472","cited_venue":"International Electrotechnical Commission","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Maximum transient overvoltage discussion","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64635,"raw_reference":"Bonneville Power Administration report on overvoltage testing, Big Eddy-Chemewa 230-kV line (Ex. 0575.1)","cited_authors":"Bonneville Power Administration","cited_year":null,"cited_title":"Big Eddy-Chemewa 230-kV line overvoltage field test report","cited_venue":"Bonneville Power Administration","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Maximum transient overvoltages discussion","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64641,"raw_reference":"Ex. 0175 (Contracts between electric utilities and their contractors) — not a work","cited_authors":null,"cited_year":null,"cited_title":null,"cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"other","section":"fn 73","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64738,"raw_reference":"Jones, R. A., Liggett, D. P., Capelli-Schellpfeffer, M., Macalady, T., Saunders, L. F., Downey, R. E., McClung, L. B., Smith, A., Jamil, S., Saporita, V. J., “Staged Tests Increase Awareness of Arc-Flash Hazards in Electrical Equipment,” IEEE Transactions on Industry Applications Society, 36(2): 659-667, March-April 2000.","cited_authors":"Jones, R. A.; Liggett, D. P.; Capelli-Schellpfeffer, M.; Macalady, T.; Saunders, L. F.; Downey, R. E.; McClung, L. B.; Smith, A.; Jamil, S.; Saporita, V. J.","cited_year":"2000","cited_title":"Staged Tests Increase Awareness of Arc-Flash Hazards in Electrical Equipment","cited_venue":"IEEE Transactions on Industry Applications Society","cited_doi":"10.1109/28.833785","cited_url":null,"ref_kind":"journal_article","section":"fn 289","page":null,"context_sentence":"\\289\\ described the results of one arcing-fault test as follows: ``the fault blew the door open and progressed up the vertical bus, completely destroying the vertical section of the [motor control center]'' (id.).","paper_id":16075,"paper_title":"Staged tests increase awareness of arc-flash hazards in electrical equipment","paper_year":2000,"paper_doi":"10.1109/28.833785"},{"citation_id":64739,"raw_reference":"Land III, H. B., “The Behavior of Arcing Faults in Low Voltage Switchboards,” 2005 IEEE ESTS, Philadelphia, pp. 133-140, 2005.","cited_authors":"Land III, H. B.","cited_year":"2005","cited_title":"The Behavior of Arcing Faults in Low Voltage Switchboards","cited_venue":"2005 IEEE ESTS, Philadelphia","cited_doi":"10.1109/ests.2005.1524666","cited_url":null,"ref_kind":"conference_paper","section":"fn 290","page":null,"context_sentence":"A paper by Land \\290\\ described problems the Navy had in 1979 with arcing faults in switchboards: ``These arcs could completely destroy a switchboard within a matter of seconds'' (id.).","paper_id":16076,"paper_title":"The behavior of arcing faults in low voltage switchboards","paper_year":2005,"paper_doi":"10.1109/ests.2005.1524666"},{"citation_id":64740,"raw_reference":"Lee, R. H., “The Other Electrical Hazard: Electric Arc Blast Burns, ” IEEE Transactions on Industry Applications, 1A-18(3):246—251, May/June 1982 (Ex. 0433).","cited_authors":"Lee, R. H.","cited_year":"1982","cited_title":"The Other Electrical Hazard: Electric Arc Blast Burns","cited_venue":"IEEE Transactions on Industry Applications","cited_doi":"10.1109/tia.1982.4504068","cited_url":null,"ref_kind":"journal_article","section":"fn 296","page":null,"context_sentence":"It should be noted that NFPA 70E-2004 Annex D contains three different methods of estimating incident heat energy: (1) a method based on a paper by Lee entitled ``The Other Electrical Hazard: Electric Arc Blast Burns,'' \\296\\ also known as the ``Lee equation''; (2) a method based on the Doughty, Neal, and Floyd paper, which Table 10 lists separately; and (3) the IEEE 1584 method, which Table 10 also lists separately.\\297\\ The following discussion refers to the method based on the Lee equation as the NFPA 70E Annex D method.\\298\\ ---------------------------------------------------------------------------","paper_id":16077,"paper_title":"The Other Electrical Hazard: Electric Arc Blast Burns","paper_year":1982,"paper_doi":"10.1109/tia.1982.4504068"},{"citation_id":64741,"raw_reference":"Doughty, T. E., Neal, T. E., and Floyd II, H. L., “Predicting Incident Energy to Better Manage the Electric Arc Hazard on 600 V Power Distribution Systems,” Record of Conference Papers IEEE IAS 45th Annual Petroleum and Chemical Industry Conference, September 28-30, 1998.","cited_authors":"Doughty, T. E.; Neal, T. E.; Floyd II, H. L.","cited_year":"1998","cited_title":"Predicting Incident Energy to Better Manage the Electric Arc Hazard on 600 V Power Distribution Systems","cited_venue":"Record of Conference Papers IEEE IAS 45th Annual Petroleum and Chemical Industry Conference","cited_doi":"10.1109/28.821823","cited_url":null,"ref_kind":"conference_paper","section":"Table 10","page":null,"context_sentence":null,"paper_id":16078,"paper_title":"Predicting incident energy to better manage the electric arc hazard on 600-V power distribution systems","paper_year":2000,"paper_doi":"10.1109/28.821823"},{"citation_id":64742,"raw_reference":"Guide for Performing Arc Flash Hazard Calculations, IEEE Std 1584-2002.","cited_authors":"IEEE","cited_year":"2002","cited_title":"Guide for Performing Arc Flash Hazard Calculations","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Table 10","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64743,"raw_reference":"Stokes, A. D., Sweeting, D. K., “Electric Arcing Burn Hazards,” IEEE Transactions on Industry Applications. Vol. 42. No. 1, January/February 2006, pp. 134-141.","cited_authors":"Stokes, A. D.; Sweeting, D. K.","cited_year":"2006","cited_title":"Electric Arcing Burn Hazards","cited_venue":"IEEE Transactions on Industry Applications","cited_doi":"10.1109/pcicon.2004.1352821","cited_url":null,"ref_kind":"journal_article","section":"fn 309","page":null,"context_sentence":"0452).\\309\\ That paper notes that the NFPA and IEEE methods use a predominantly radiant model of incident heat energy from an electric arc, in which 90 percent of the heat is radiant heat and in which the entire exposure will be outside the electric arc plasma.","paper_id":16079,"paper_title":"Electric arcing burn hazards","paper_year":2004,"paper_doi":"10.1109/pcicon.2004.1352821"},{"citation_id":64744,"raw_reference":"IEEE Std 1584a-2004 (Amendment 1 to IEEE Std 1584-2002)","cited_authors":"IEEE","cited_year":"2004","cited_title":"IEEE Guide for Performing Arc-Flash Hazard Calculations—Amendment 1","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"fn 307","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64998,"raw_reference":"Ashford, N.A., 2007. “Workers' Compensation,” in Environmental and Occupational Medicine, Fourth Edition, W.N. Rom & S. Markowitz (Eds.), Lippincott-Raven Publishers, Philadelphia, pp. 1712-1719.","cited_authors":"Ashford, N.A.","cited_year":"2007","cited_title":"Workers' Compensation","cited_venue":"Lippincott-Raven Publishers","cited_doi":null,"cited_url":null,"ref_kind":"book_chapter","section":"References, ref. 3","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":64999,"raw_reference":"Leigh, J.P., and Marcin, J.P. 2012. “Workers' compensation benefits and shifting costs for occupational injury and illness,” Journal of Occupational and Environmental Medicine, April, 54(4): 445-450.","cited_authors":"Leigh, J.P.; Marcin, J.P.","cited_year":"2012","cited_title":"Workers' compensation benefits and shifting costs for occupational injury and illness","cited_venue":"Journal of Occupational and Environmental Medicine","cited_doi":"10.1097/jom.0b013e3182451e54","cited_url":null,"ref_kind":"journal_article","section":"References, ref. 21","page":null,"context_sentence":null,"paper_id":10439,"paper_title":"Workers' Compensation Benefits and Shifting Costs for Occupational Injury and Illness","paper_year":2012,"paper_doi":"10.1097/jom.0b013e3182451e54"},{"citation_id":65000,"raw_reference":"Magat, W.A, Viscusi, W.K, and Huber, J, 1996. “A Reference Lottery Metric for Valuing Health.” Management Science 42: 1118-1130.","cited_authors":"Magat, W.A.; Viscusi, W.K.; Huber, J.","cited_year":"1996","cited_title":"A Reference Lottery Metric for Valuing Health","cited_venue":"Management Science","cited_doi":"10.1287/mnsc.42.8.1118","cited_url":null,"ref_kind":"journal_article","section":"References, ref. 22","page":null,"context_sentence":null,"paper_id":15339,"paper_title":"A Reference Lottery Metric for Valuing Health","paper_year":1996,"paper_doi":"10.1287/mnsc.42.8.1118"},{"citation_id":65001,"raw_reference":"National Academy of Social Insurance. 2012. “Workers' Compensation: Benefits, Coverage, and Costs, 2010,” August.","cited_authors":"National Academy of Social Insurance","cited_year":"2012","cited_title":"Workers' Compensation: Benefits, Coverage, and Costs, 2010","cited_venue":"National Academy of Social Insurance","cited_doi":null,"cited_url":"http://www.nasi.org/research/2012/report-workers-compensation-benefits-coverage-costs-2010","ref_kind":"research_report","section":"References, ref. 23","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65002,"raw_reference":"Neuhauser, F.W., Seabury, S.S., and Mendeloff, J. 2013. “The Impact of Experience Rating on Small Employers: Would Lowering the Threshold for Experience Rating Improve Safety?” Rand Working Papers WR-955.","cited_authors":"Neuhauser, F.W.; Seabury, S.S.; Mendeloff, J.","cited_year":"2013","cited_title":"The Impact of Experience Rating on Small Employers: Would Lowering the Threshold for Experience Rating Improve Safety?","cited_venue":"Rand Working Papers WR-955","cited_doi":null,"cited_url":"http://www.rand.org/jie/centers/workplace-health-safety/projects/experience-rating.html","ref_kind":"working_paper","section":"References, ref. 27","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65003,"raw_reference":"Viscusi, W.K., and Aldy, J.E. 2003. “The Value of a Statistical Life: A Critical Review of Market Estimates Throughout the World.” Journal of Risk and Uncertainty, 27(1): 5-76.","cited_authors":"Viscusi, W.K.; Aldy, J.E.","cited_year":"2003","cited_title":"The Value of a Statistical Life: A Critical Review of Market Estimates Throughout the World","cited_venue":"Journal of Risk and Uncertainty","cited_doi":"10.1023/a:1025598106257","cited_url":"http://camra.msu.edu/documents/ViscusiandAldy2003.pdf","ref_kind":"journal_article","section":"References, ref. 53","page":null,"context_sentence":null,"paper_id":1481,"paper_title":"The Value of a Statistical Life: A Critical Review of Market Estimates Throughout the World","paper_year":2003,"paper_doi":"10.1023/a:1025598106257"},{"citation_id":65004,"raw_reference":"Occupational Safety and Health Administration Small Business Advocacy Review Panel. 2003. “Report of the Small Business Advocacy Review Panel on the Draft OSHA Standard for Electric Power Generation, Transmission, and Distribution,” June 17, 2003. Ex. 0019.","cited_authors":"Occupational Safety and Health Administration Small Business Advocacy Review Panel","cited_year":"2003","cited_title":"Report of the Small Business Advocacy Review Panel on the Draft OSHA Standard for Electric Power Generation, Transmission, and Distribution","cited_venue":"U.S. Department of Labor, OSHA","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"References, ref. 29","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65005,"raw_reference":"Urban Institute/Brookings, 2012. “Historical Average Federal Tax Rates for All Households,” Tax Policy Center, October.","cited_authors":"Urban Institute/Brookings","cited_year":"2012","cited_title":"Historical Average Federal Tax Rates for All Households","cited_venue":"Tax Policy Center","cited_doi":null,"cited_url":"http://www.taxpolicycenter.org/taxfacts/displayafact.cfm?Docid=456","ref_kind":"dataset","section":"References, ref. 52","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65232,"raw_reference":"NFPA 70E-2004, Section 110.1, which sets the scope for Article 110, General Requirements for Electrical Safety-Related Work Practices (Ex. 0134).","cited_authors":null,"cited_year":"2004","cited_title":"NFPA 70E, Standard for Electrical Safety in the Workplace, Section 110.1","cited_venue":"National Fire Protection Association","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"fn 41","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65233,"raw_reference":"ANSI Z133.1-1982[, American National Standard for Tree Care Operations—Pruning, Trimming, Repairing, Maintaining, and Removing Trees, and Cutting Brush—Safety Requirements ]","cited_authors":"American National Standards Institute","cited_year":"1982","cited_title":"American National Standard for Tree Care Operations—Pruning, Trimming, Repairing, Maintaining, and Removing Trees, and Cutting Brush—Safety Requirements (ANSI Z133.1)","cited_venue":"American National Standards Institute","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"fn 48","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65234,"raw_reference":"Training Requirements in OSHA Standards and Training Guidelines","cited_authors":"OSHA","cited_year":null,"cited_title":"Training Requirements in OSHA Standards and Training Guidelines","cited_venue":"Occupational Safety and Health Administration","cited_doi":null,"cited_url":"http://www.osha.gov/pls/publications/publication.html","ref_kind":"other","section":"fn 55","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65817,"raw_reference":"Leigh and Marcin estimate that the average indemnity benefits for a fatality are $225,919 [21]","cited_authors":"Leigh and Marcin","cited_year":null,"cited_title":null,"cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"other","section":"fn 482","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65818,"raw_reference":"Viscusi and Aldy [53]","cited_authors":"Viscusi and Aldy","cited_year":null,"cited_title":null,"cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Wage premiums / Valuation of fatalities section","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65819,"raw_reference":"CONSAD [5]","cited_authors":"CONSAD","cited_year":null,"cited_title":null,"cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Profile of Affected Industries","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65820,"raw_reference":"U.S. Census' County Business Patterns data [47]","cited_authors":"U.S. Census Bureau","cited_year":null,"cited_title":"County Business Patterns","cited_venue":"U.S. Census Bureau","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Profile of Affected Industries","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65821,"raw_reference":"Energy Information Administration (EIA)'s Form EIA-860 Database Annual Electric Generator Report [49]","cited_authors":"Energy Information Administration","cited_year":null,"cited_title":"Form EIA-860 Database Annual Electric Generator Report","cited_venue":"EIA","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Profile of Affected Industries","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65822,"raw_reference":"EIA's Form-861 Annual Electric Power Industry Report [50]","cited_authors":"Energy Information Administration","cited_year":null,"cited_title":"Form EIA-861 Annual Electric Power Industry Report","cited_venue":"EIA","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Profile of Affected Industries","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65823,"raw_reference":"BLS Occupational Employment Statistics data [34]","cited_authors":"Bureau of Labor Statistics","cited_year":"2007","cited_title":"Occupational Employment Statistics","cited_venue":"BLS","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Profile of Affected Industries","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65824,"raw_reference":"Census of Fatal Occupational Injuries (CFOI) developed by the Bureau of Labor Statistics","cited_authors":"Bureau of Labor Statistics","cited_year":null,"cited_title":"Census of Fatal Occupational Injuries","cited_venue":"BLS","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Benefits, Net Benefits, and Cost Effectiveness","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65825,"raw_reference":"Statistics of U.S. Businesses [43]","cited_authors":"U.S. Census Bureau","cited_year":"2007","cited_title":"Statistics of U.S. Businesses","cited_venue":"U.S. Census Bureau","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Profile of Affected Industries","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65826,"raw_reference":"Viscusi and Aldy conducted a metaanalysis of studies in the economics literature","cited_authors":"W. Kip Viscusi and Joseph E. Aldy","cited_year":"2003","cited_title":"The Value of a Statistical Life: A Critical Review of Market Estimates Throughout the World","cited_venue":"Journal of Risk and Uncertainty","cited_doi":"10.3386/w9487","cited_url":null,"ref_kind":"journal_article","section":"Benefits, Net Benefits, and Cost Effectiveness","page":null,"context_sentence":null,"paper_id":10726,"paper_title":"The Value of a Statistical Life: A Critical Review of Market Estimates throughout the World","paper_year":2003,"paper_doi":"10.3386/w9487"},{"citation_id":65827,"raw_reference":"National Safety Council's (NSC) valuation of $1 million per fatality [26]","cited_authors":"National Safety Council","cited_year":null,"cited_title":null,"cited_venue":"National Safety Council","cited_doi":null,"cited_url":null,"ref_kind":"web_page","section":"Benefits, Net Benefits, and Cost Effectiveness","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65828,"raw_reference":"a study of burn injuries (Ex. 0424)","cited_authors":null,"cited_year":null,"cited_title":null,"cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"journal_article","section":"fn 498","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65829,"raw_reference":"Office of Regulatory Analysis, OSHA. See text.","cited_authors":"OSHA","cited_year":null,"cited_title":null,"cited_venue":"OSHA","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"Costs of Compliance","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":65960,"raw_reference":"Doughty, T.E., Neal, T.E., and Floyd II, H.L., \"Predicting Incident Energy to Better Manage the Electric Arc Hazard on 600 V Power Distribution Systems,\" Record of Conference Papers IEEE IAS 45th Annual Petroleum and Chemical Industry Conference, September 28-30, 1998.","cited_authors":"Doughty, T.E.; Neal, T.E.; Floyd II, H.L.","cited_year":"1998","cited_title":"Predicting Incident Energy to Better Manage the Electric Arc Hazard on 600 V Power Distribution Systems","cited_venue":"Record of Conference Papers IEEE IAS 45th Annual Petroleum and Chemical Industry Conference","cited_doi":"10.1109/28.821823","cited_url":null,"ref_kind":"conference_paper","section":"Appendix E, Table 2","page":null,"context_sentence":null,"paper_id":16078,"paper_title":"Predicting incident energy to better manage the electric arc hazard on 600-V power distribution systems","paper_year":2000,"paper_doi":"10.1109/28.821823"},{"citation_id":65961,"raw_reference":"Stoll, A. M., and Chianta, M. A., \"Method and Rating System for Evaluations of Thermal Protection,\" Aerospace Medicine, Vol 40, 1969, pp. 1232-1238","cited_authors":"Stoll, A. M.; Chianta, M. A.","cited_year":"1969","cited_title":"Method and Rating System for Evaluations of Thermal Protection","cited_venue":"Aerospace Medicine, Vol 40","cited_doi":null,"cited_url":null,"ref_kind":"journal_article","section":"Appendix E, footnote 25","page":null,"context_sentence":null,"paper_id":70714,"paper_title":"Method and rating system for evaluation of thermal protection.","paper_year":1969,"paper_doi":null},{"citation_id":65962,"raw_reference":"Stoll, A. M., and Chianta, M. A., \"Heat Transfer through Fabrics as Related to Thermal Injury,\" Transactions—New York Academy of Sciences, Vol 33(7), Nov. 1971, pp. 649-670.","cited_authors":"Stoll, A. M.; Chianta, M. A.","cited_year":"1971","cited_title":"Heat Transfer through Fabrics as Related to Thermal Injury","cited_venue":"Transactions—New York Academy of Sciences, Vol 33(7)","cited_doi":"10.1111/j.2164-0947.1971.tb02630.x","cited_url":null,"ref_kind":"journal_article","section":"Appendix E, footnote 25","page":null,"context_sentence":null,"paper_id":16284,"paper_title":"HEAT TRANSFER THROUGH FABRICS AS RELATED TO THERMAL INJURY*†","paper_year":1971,"paper_doi":"10.1111/j.2164-0947.1971.tb02630.x"},{"citation_id":66160,"raw_reference":"IEEE Std 516-2009, IEEE Guide for Maintenance Methods on Energized Power Lines","cited_authors":"IEEE","cited_year":"2009","cited_title":"IEEE Guide for Maintenance Methods on Energized Power Lines","cited_venue":"IEEE","cited_doi":"10.1109/ieeestd.1995.122635","cited_url":null,"ref_kind":"book","section":"Appendix B, Section III.B","page":null,"context_sentence":null,"paper_id":16320,"paper_title":"IEEE Guide for Maintenance Methods on Energized Power Lines","paper_year":1995,"paper_doi":"10.1109/ieeestd.1995.122635"},{"citation_id":66161,"raw_reference":"IEEE Std 4-1995, Standard Techniques for High-Voltage Testing","cited_authors":"IEEE","cited_year":"1995","cited_title":"Standard Techniques for High-Voltage Testing","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"book","section":"Appendix B, Section III.B","page":null,"context_sentence":null,"paper_id":71116,"paper_title":"IEEE Standard Techniques for High-Voltage Testing","paper_year":1995,"paper_doi":"10.1109/ieeestd.1995.81695"},{"citation_id":66162,"raw_reference":"IEEE Std 1048-2003, IEEE Guide for Protective Grounding of Power Lines","cited_authors":"IEEE","cited_year":"2003","cited_title":"IEEE Guide for Protective Grounding of Power Lines","cited_venue":"IEEE","cited_doi":"10.1109/ieeestd.1990.94619","cited_url":null,"ref_kind":"book","section":"Appendix C, Section III.D.1","page":null,"context_sentence":null,"paper_id":16319,"paper_title":"IEEE Guide for Protective Grounding of Power Lines","paper_year":1990,"paper_doi":"10.1109/ieeestd.1990.94619"},{"citation_id":66163,"raw_reference":"IEEE Std 80-2000, IEEE Guide for Safety in AC Substation Grounding","cited_authors":"IEEE","cited_year":"2000","cited_title":"IEEE Guide for Safety in AC Substation Grounding","cited_venue":"IEEE","cited_doi":"10.1109/ieeestd.2000.91902","cited_url":null,"ref_kind":"book","section":"§ 1910.269(u)(3) note","page":null,"context_sentence":null,"paper_id":16321,"paper_title":"IEEE Guide for Safety in AC Substation Grounding","paper_year":2000,"paper_doi":"10.1109/ieeestd.2000.91902"},{"citation_id":66164,"raw_reference":"ASTM F855-09, Standard Specifications for Temporary Protective Grounds to Be Used on De-Energized Electric Power Lines and Equipment","cited_authors":"ASTM","cited_year":"2009","cited_title":"Standard Specifications for Temporary Protective Grounds to Be Used on De-Energized Electric Power Lines and Equipment","cited_venue":"ASTM","cited_doi":null,"cited_url":null,"ref_kind":"book","section":"§ 1910.269(n)(4) note","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":66165,"raw_reference":"ANSI/IEEE C2-2012, National Electrical Safety Code","cited_authors":"ANSI/IEEE","cited_year":"2012","cited_title":"National Electrical Safety Code","cited_venue":"ANSI/IEEE","cited_doi":null,"cited_url":null,"ref_kind":"book","section":"§ 1910.269(u)(1) note","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":66241,"raw_reference":"Ex. 0430 (heat energy inverse proportion to square of distance)","cited_authors":null,"cited_year":null,"cited_title":null,"cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Head and face protection, fn 365 area","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":66242,"raw_reference":"NIOSH recommended flash protection boundaries (Ex. 0130)","cited_authors":"National Institute for Occupational Safety and Health","cited_year":null,"cited_title":null,"cited_venue":null,"cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Heat stress / Ex. 0505 discussion","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":66243,"raw_reference":"Lukens Steel Co., 10 BNA OSHC 1115 (No. 76-1053, 1981)","cited_authors":null,"cited_year":"1981","cited_title":"Lukens Steel Co.","cited_venue":"Occupational Safety and Health Review Commission","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Are FR and arc-rated clothing PPE","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":66244,"raw_reference":"Table 17 typical heat loss values through clothing (Ex. 0363)","cited_authors":"Thomas Neal, Neal Associates","cited_year":null,"cited_title":"Typical Heat Loss Values Through Clothing","cited_venue":"Neal Associates","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Heat stress","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":66245,"raw_reference":"NFPA 70E-2004","cited_authors":"National Fire Protection Association","cited_year":"2004","cited_title":"NFPA 70E Standard for Electrical Safety in the Workplace","cited_venue":"NFPA","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Other issues relating to selection of protective clothing","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":66246,"raw_reference":"ASTM F1796-09 Standard Specification for High Voltage Detectors—Part 1 Capacitive Type to be Used for Voltages Exceeding 600 Volts AC","cited_authors":"ASTM International","cited_year":"2009","cited_title":"Standard Specification for High Voltage Detectors—Part 1 Capacitive Type to be Used for Voltages Exceeding 600 Volts AC","cited_venue":"ASTM International","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Grounding and testing for deenergized lines","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":66247,"raw_reference":"ASTM F855-04 Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment","cited_authors":"ASTM International","cited_year":"2004","cited_title":"Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment","cited_venue":"ASTM International","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Protective grounds discussion","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":67417,"raw_reference":"IEEE Std 516, IEEE Guide for Maintenance Methods on Energized Power-Lines","cited_authors":"Institute of Electrical and Electronic Engineers (IEEE)","cited_year":null,"cited_title":"IEEE Guide for Maintenance Methods on Energized Power-Lines","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Section III.B, Relevant Consensus Standards","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":67418,"raw_reference":"IEEE Std 1048, IEEE Guide for Protective Grounding of Power Lines.","cited_authors":"Institute of Electrical and Electronic Engineers (IEEE)","cited_year":null,"cited_title":"IEEE Guide for Protective Grounding of Power Lines","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Section III.B, Relevant Consensus Standards","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":68259,"raw_reference":"ANSI/IEEE C2-2012","cited_authors":null,"cited_year":"2012","cited_title":"National Electrical Safety Code","cited_venue":"ANSI/IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Section 1926.966(b) note","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":68260,"raw_reference":"ANSI/IEEE Std 18-2012, IEEE Standard for Shunt Power Capacitors","cited_authors":null,"cited_year":"2012","cited_title":"IEEE Standard for Shunt Power Capacitors","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Section 1926.967(a)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":68261,"raw_reference":"IEEE Std 1048-2003","cited_authors":null,"cited_year":"2003","cited_title":"IEEE Guide for Protective Grounding of Power Lines","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Appendix C discussion","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":68262,"raw_reference":"ASTM F1891-12, Standard Specification for Arc and Flame Resistant Rainwear","cited_authors":null,"cited_year":"2012","cited_title":"Standard Specification for Arc and Flame Resistant Rainwear","cited_venue":"ASTM International","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Appendix E discussion","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":68263,"raw_reference":"FCC OET Bulletin 65, Edition 97-01, Evaluating Compliance with FCC Guidelines for Human Exposure to Radiofrequency Electromagnetic Fields","cited_authors":null,"cited_year":"1997","cited_title":"Evaluating Compliance with FCC Guidelines for Human Exposure to Radiofrequency Electromagnetic Fields","cited_venue":"Federal Communications Commission","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"Section 1926.967(k) discussion","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":68713,"raw_reference":"CIGRÉ/SC 33, \"Phase-to-Phase Insulation Coordination,\" ELECTRA, no. 64, 1979","cited_authors":"CIGRÉ/SC 33","cited_year":"1979","cited_title":"Phase-to-Phase Insulation Coordination","cited_venue":"ELECTRA","cited_doi":null,"cited_url":null,"ref_kind":"journal_article","section":"fn 217","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":68714,"raw_reference":"Esmeraldo, P. C. V., and Fonseca, C. S., \"Evaluation of the Phase-to-Phase Overvoltage Characteristics due to Switching Surges for Application on Risk of Failure Statistical Methods in Non- Conventional Power Design,\" Paper 34.01, 6th ISH, New Orleans, 1989","cited_authors":"Esmeraldo, P. C. V.; Fonseca, C. S.","cited_year":"1989","cited_title":"Evaluation of the Phase-to-Phase Overvoltage Characteristics due to Switching Surges for Application on Risk of Failure Statistical Methods in Non-Conventional Power Design","cited_venue":"6th ISH, New Orleans","cited_doi":null,"cited_url":null,"ref_kind":"conference_paper","section":"fn 217","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":68715,"raw_reference":"Gallet, G., Leroy, G., Lacey, R., and Kromer, I., \"General expression for positive switching impulse strength valid up to extra line air gaps,\" IEEE Transaction on Power Apparatus and Systems, vol. PAS-94, pp. 1989-1993, Nov./Dec. 1975","cited_authors":"Gallet, G.; Leroy, G.; Lacey, R.; Kromer, I.","cited_year":"1975","cited_title":"General expression for positive switching impulse strength valid up to extra line air gaps","cited_venue":"IEEE Transaction on Power Apparatus and Systems","cited_doi":"10.1109/t-pas.1975.32045","cited_url":null,"ref_kind":"journal_article","section":"fn 229","page":null,"context_sentence":"Consequently, the Agency decided against adopting this method in the final rule. The second method, adopted by IEEE Std 516-2009, uses equations based on the paper by Vaisman,\\228\\ and two papers by Gallet,\\229\\ to determine minimum approach distances (Ex.","paper_id":16698,"paper_title":"General expression for positive switching impulse strength valid up to extra long air gaps","paper_year":1975,"paper_doi":"10.1109/t-pas.1975.32045"},{"citation_id":68716,"raw_reference":"Gallet, G., Hutzler, B., and Riu, J-P., \"Analysis of the switching impulse strength of phase-to-phase air gaps,\" IEEE Transactions on Power Delivery, vol. PAS-97, no. 2, Mar./Apr. 1978","cited_authors":"Gallet, G.; Hutzler, B.; Riu, J-P.","cited_year":"1978","cited_title":"Analysis of the switching impulse strength of phase-to-phase air gaps","cited_venue":"IEEE Transactions on Power Delivery","cited_doi":"10.1109/tpas.1978.354509","cited_url":null,"ref_kind":"journal_article","section":"fn 229","page":null,"context_sentence":"Consequently, the Agency decided against adopting this method in the final rule. The second method, adopted by IEEE Std 516-2009, uses equations based on the paper by Vaisman,\\228\\ and two papers by Gallet,\\229\\ to determine minimum approach distances (Ex.","paper_id":16699,"paper_title":"Analysis of the Switching Impulse Strength of Phase-To-Phase Air Gaps","paper_year":1978,"paper_doi":"10.1109/tpas.1978.354509"},{"citation_id":68717,"raw_reference":"Elek, A., and Simpson, J. W., \"Safe clearance and protection against shocks during live-line work,\" AIEE Transaction on Power Apparatus and Systems, vol. 80, pt. III, pp. 897-902, Feb. 1962","cited_authors":"Elek, A.; Simpson, J. W.","cited_year":"1962","cited_title":"Safe clearance and protection against shocks during live-line work","cited_venue":"AIEE Transaction on Power Apparatus and Systems","cited_doi":null,"cited_url":null,"ref_kind":"journal_article","section":"fn 235","page":null,"context_sentence":"In addition, the IEEE committee chose not to use it for phase-to-ground exposures, presumably because the papers supporting the method for phase-to-ground exposures examined the safety of employees performing live-line maintenance.\\235\\ OSHA believes that these papers support the method used in the final rule to calculate minimum approach distances for phase-to-phase exposures, as well as phase-to-ground exposures.","paper_id":70890,"paper_title":"Safe Clearances and Protection against Shocks during Live-Line Work","paper_year":1961,"paper_doi":"10.1109/aieepas.1961.4501169"},{"citation_id":68718,"raw_reference":"IEEE Committee Report, \"Live-line maintenance methods,\" IEEE Transactions on Power Apparatus and Systems, vol. PAS-92, pp. 1642-1648, Sept./Oct. 1973","cited_authors":"IEEE Committee","cited_year":"1973","cited_title":"Live-line maintenance methods","cited_venue":"IEEE Transactions on Power Apparatus and Systems","cited_doi":null,"cited_url":null,"ref_kind":"journal_article","section":"fn 235","page":null,"context_sentence":"In addition, the IEEE committee chose not to use it for phase-to-ground exposures, presumably because the papers supporting the method for phase-to-ground exposures examined the safety of employees performing live-line maintenance.\\235\\ OSHA believes that these papers support the method used in the final rule to calculate minimum approach distances for phase-to-phase exposures, as well as phase-to-ground exposures.","paper_id":70860,"paper_title":"Live-Line Maintenance Methods","paper_year":1973,"paper_doi":"10.1109/tpas.1973.293712"},{"citation_id":68719,"raw_reference":"IEEE Committee Report, \"Recommendations for safety in live-line maintenance,\" IEEE Transactions on Power Apparatus and Systems, vol. PAS-87, no. 2, pp. 346-352, Feb. 1968","cited_authors":"IEEE Committee","cited_year":"1968","cited_title":"Recommendations for safety in live-line maintenance","cited_venue":"IEEE Transactions on Power Apparatus and Systems","cited_doi":"10.1109/tpas.1968.292028","cited_url":null,"ref_kind":"journal_article","section":"fn 235","page":null,"context_sentence":"In addition, the IEEE committee chose not to use it for phase-to-ground exposures, presumably because the papers supporting the method for phase-to-ground exposures examined the safety of employees performing live-line maintenance.\\235\\ OSHA believes that these papers support the method used in the final rule to calculate minimum approach distances for phase-to-phase exposures, as well as phase-to-ground exposures.","paper_id":16700,"paper_title":"Recommendations for Safety in Live Line Maintenance","paper_year":1968,"paper_doi":"10.1109/tpas.1968.292028"},{"citation_id":68720,"raw_reference":"EPRI Transmission Line Reference Book: 115-345-kV Compact Line Design, 2007 (Blue Book)","cited_authors":"EPRI","cited_year":"2007","cited_title":"Transmission Line Reference Book: 115-345-kV Compact Line Design","cited_venue":"EPRI","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"fn 233","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69356,"raw_reference":"Doughty, T.E., Neal, T.E., and Floyd II, H.L., \"Predicting Incident Energy to Better Manage the Electric Arc Hazard on 600 V Power Distribution Systems,\" Record of Conference Papers IEEE IAS 45th Annual Petroleum and Chemical Industry Conference, September 28—30, 1998.","cited_authors":"Doughty, T.E.; Neal, T.E.; Floyd II, H.L.","cited_year":"1998","cited_title":"Predicting Incident Energy to Better Manage the Electric Arc Hazard on 600 V Power Distribution Systems","cited_venue":"Record of Conference Papers IEEE IAS 45th Annual Petroleum and Chemical Industry Conference","cited_doi":"10.1109/28.821823","cited_url":null,"ref_kind":"conference_paper","section":"Appendix E, Table 2","page":null,"context_sentence":null,"paper_id":16078,"paper_title":"Predicting incident energy to better manage the electric arc hazard on 600-V power distribution systems","paper_year":2000,"paper_doi":"10.1109/28.821823"},{"citation_id":69357,"raw_reference":"Stoll, A.M., and Chianta, M.A., 'Method and Rating System for Evaluations of Thermal Protection,' Aerospace Medicine, Vol 40, 1969, pp. 1232-1238","cited_authors":"Stoll, A.M.; Chianta, M.A.","cited_year":"1969","cited_title":"Method and Rating System for Evaluations of Thermal Protection","cited_venue":"Aerospace Medicine, Vol 40","cited_doi":null,"cited_url":null,"ref_kind":"journal_article","section":"Appendix E, footnote 5","page":null,"context_sentence":null,"paper_id":70714,"paper_title":"Method and rating system for evaluation of thermal protection.","paper_year":1969,"paper_doi":null},{"citation_id":69358,"raw_reference":"Stoll A.M., and Chianta, M.A., 'Heat Transfer through Fabrics as Related to Thermal Injury,' Transactions—New York Academy of Sciences, Vol 33(7), Nov. 1971, pp. 649-670.","cited_authors":"Stoll, A.M.; Chianta, M.A.","cited_year":"1971","cited_title":"Heat Transfer through Fabrics as Related to Thermal Injury","cited_venue":"Transactions—New York Academy of Sciences, Vol 33(7)","cited_doi":"10.1111/j.2164-0947.1971.tb02630.x","cited_url":null,"ref_kind":"journal_article","section":"Appendix E, footnote 5","page":null,"context_sentence":null,"paper_id":16284,"paper_title":"HEAT TRANSFER THROUGH FABRICS AS RELATED TO THERMAL INJURY*†","paper_year":1971,"paper_doi":"10.1111/j.2164-0947.1971.tb02630.x"},{"citation_id":69359,"raw_reference":"IEEE Std 516-2009, IEEE Guide for Maintenance Methods on Energized Power Lines.","cited_authors":"IEEE","cited_year":"2009","cited_title":"IEEE Guide for Maintenance Methods on Energized Power Lines","cited_venue":"IEEE","cited_doi":"10.1109/ieeestd.1995.122635","cited_url":null,"ref_kind":"book","section":"Appendix B, Section III.B","page":null,"context_sentence":null,"paper_id":16320,"paper_title":"IEEE Guide for Maintenance Methods on Energized Power Lines","paper_year":1995,"paper_doi":"10.1109/ieeestd.1995.122635"},{"citation_id":69360,"raw_reference":"IEEE Std 1048-2003, IEEE Guide for Protective Grounding of Power Lines.","cited_authors":"IEEE","cited_year":"2003","cited_title":"IEEE Guide for Protective Grounding of Power Lines","cited_venue":"IEEE","cited_doi":"10.1109/ieeestd.1990.94619","cited_url":null,"ref_kind":"book","section":"Appendix C, Section III.D.1","page":null,"context_sentence":null,"paper_id":16319,"paper_title":"IEEE Guide for Protective Grounding of Power Lines","paper_year":1990,"paper_doi":"10.1109/ieeestd.1990.94619"},{"citation_id":69361,"raw_reference":"IEEE Std 1584b-2011 (Amendment 2 to IEEE Std 1584-2002), Guide for Performing Arc-Flash Hazard Calculations.","cited_authors":"IEEE","cited_year":"2011","cited_title":"Guide for Performing Arc-Flash Hazard Calculations","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"book","section":"Appendix E, Table 2","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69362,"raw_reference":"ARCPRO, a commercially available software program developed by Kinectrics, Toronto, ON, CA.","cited_authors":"Kinectrics","cited_year":null,"cited_title":"ARCPRO","cited_venue":"Kinectrics","cited_doi":null,"cited_url":null,"ref_kind":"other","section":"Appendix E, Table 2","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69469,"raw_reference":"CONSAD report in support of the PRIA [5]","cited_authors":"CONSAD","cited_year":"2005","cited_title":null,"cited_venue":"CONSAD","cited_doi":null,"cited_url":null,"ref_kind":"research_report","section":"fn 538","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69470,"raw_reference":"the 2003 report of the Small Business Advocacy Review Panel [29]","cited_authors":"Small Business Advocacy Review Panel","cited_year":"2003","cited_title":"Report of the Small Business Advocacy Review Panel","cited_venue":"Small Business Advocacy Review Panel","cited_doi":null,"cited_url":null,"ref_kind":"government_report","section":"fn 538","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69471,"raw_reference":"industry-specific wage rates published by BLS [37]... National Compensation Survey [36]","cited_authors":"Bureau of Labor Statistics","cited_year":null,"cited_title":"National Compensation Survey","cited_venue":"Bureau of Labor Statistics","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Profile of Affected Industries (fn 537)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69472,"raw_reference":"Federal Energy Regulatory Commission's Form No. 1: Annual Report of Major Electric Utilities [10]","cited_authors":"Federal Energy Regulatory Commission","cited_year":null,"cited_title":"Form No. 1: Annual Report of Major Electric Utilities","cited_venue":"Federal Energy Regulatory Commission","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Costs Related to Minimum Approach Distances (section 14)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69473,"raw_reference":"Energy Information Administration Form EIA-861 Final Data File for 2008 [50]","cited_authors":"Energy Information Administration","cited_year":"2008","cited_title":"Form EIA-861 Final Data File","cited_venue":"Energy Information Administration","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Costs Related to Minimum Approach Distances (section 14)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69474,"raw_reference":"2008 EIA Form 860 database, which provides a nationwide census of generating plants by owner [49]","cited_authors":"Energy Information Administration","cited_year":"2008","cited_title":"Form EIA-860 database","cited_venue":"Energy Information Administration","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Costs for Providing Arc-Flash Protective Equipment / arc-hazard assessment (section 10)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69475,"raw_reference":"U.S. Census Bureau's Statistics of U.S. Businesses [43]","cited_authors":"U.S. Census Bureau","cited_year":null,"cited_title":"Statistics of U.S. Businesses","cited_venue":"U.S. Census Bureau","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Economic Feasibility and Impacts (section 16)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69476,"raw_reference":"Internal Revenue Service's (IRS) Corporation Sourcebook","cited_authors":"Internal Revenue Service","cited_year":null,"cited_title":"Corporation Sourcebook","cited_venue":"Internal Revenue Service","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"Economic Feasibility and Impacts (section 16)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69477,"raw_reference":"Bureau of Economic Analysis' Implicit Price Deflator for Gross Domestic Product [32]","cited_authors":"Bureau of Economic Analysis","cited_year":null,"cited_title":"Implicit Price Deflator for Gross Domestic Product","cited_venue":"Bureau of Economic Analysis","cited_doi":null,"cited_url":null,"ref_kind":"dataset","section":"One-Time Costs for Additional Training for Employees Not Already Receiving Training (section 'One-Time Costs')","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69736,"raw_reference":"IEEE Std 80, Guide for Safety in AC Substation Grounding","cited_authors":"IEEE","cited_year":null,"cited_title":"Guide for Safety in AC Substation Grounding","cited_venue":"IEEE","cited_doi":null,"cited_url":null,"ref_kind":"book","section":"Section 1926.963 summary (testing and test facilities)","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null},{"citation_id":69737,"raw_reference":"ASTM F855-09, Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment","cited_authors":"ASTM","cited_year":"2009","cited_title":"Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment","cited_venue":"ASTM","cited_doi":null,"cited_url":null,"ref_kind":"book","section":"fn 414","page":null,"context_sentence":null,"paper_id":null,"paper_title":null,"paper_year":null,"paper_doi":null}]}